DCL-12-047, Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:Pacific Gas and Electric Company                                                                                     Diablo Canyon Power Plant James R. Becker Site Vice President      Mail Code 104/6 P. O. Box 56 Avila Beach, CA 93424 805.545.3462 April 30, 2012                                                                                       Internal: 691.3462 Fax: 805.545.6445 PG&E Letter DCL-12-047 u.s. Nuclear Regulatory Commission ATTN: Document Control Desk                                                   10 CFR 50.90 Washington, D.C. 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, "Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation"
{{#Wiki_filter:Pacific Gas and Electric Company April 30, 2012 PG&E Letter DCL-12-047 u.s. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 James R. Becker Site Vice President 10 CFR 50.90 Diablo Canyon Power Plant Mail Code 104/6 P. O. Box 56 Avila Beach, CA 93424 805.545.3462 Internal: 691.3462 Fax: 805.545.6445 Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, "Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation"  


==Dear Commissioners and Staff:==
==Dear Commissioners and Staff:==
Pursuant to 10 CFR 50.90, Pacific Gas and Electric Company (PG&E) submitted an application for amendment to Facility Operating License Nos. DPR-80 and DPR-82 by PG&E Letter DCL-11-072, "License Amendment Request 11-06, Revision to Technical Specification 3.3.5, 'Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation,'" dated October 24,2011. PG&E Letter DCL-11-072 submitted for Nuclear Regulatory Commission (NRC) review and approval proposed to revise Technical Specification (TS) 3.3.5, "Loss of Power (LOP) Diesel Generator (DG)
Pursuant to 10 CFR 50.90, Pacific Gas and Electric Company (PG&E) submitted an application for amendment to Facility Operating License Nos. DPR-80 and DPR-82 by PG&E Letter DCL-11-072, "License Amendment Request 11-06, Revision to Technical Specification 3.3.5, 'Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation,'" dated October 24,2011. PG&E Letter DCL-11-072 submitted for Nuclear Regulatory Commission (NRC) review and approval proposed to revise Technical Specification (TS) 3.3.5, "Loss of Power (LOP) Diesel Generator (DG)
Start Instrumentation," revise Final Safety Analysis Report Update (FSARU)
Start Instrumentation," revise Final Safety Analysis Report Update (FSARU)
Line 27: Line 26:
In PG&E letter DCL-11-072, PG&E requested that the license amendments be made effective upon NRC issuance, to be implemented during Unit 2 Refueling Outage 17 and Unit 1 Refueling Outage 18. To facilitate the actions required to implement the license amendments, PG&E requests that the implementation schedule be changed to "during Unit 1 Refueling Outage 18 and Unit 2 Refueling Outage 18."
In PG&E letter DCL-11-072, PG&E requested that the license amendments be made effective upon NRC issuance, to be implemented during Unit 2 Refueling Outage 17 and Unit 1 Refueling Outage 18. To facilitate the actions required to implement the license amendments, PG&E requests that the implementation schedule be changed to "during Unit 1 Refueling Outage 18 and Unit 2 Refueling Outage 18."
If you have any questions or require additional information, please contact Mr. Tom Baldwin at (805) 545-4720.
If you have any questions or require additional information, please contact Mr. Tom Baldwin at (805) 545-4720.
Sincerely, A member   of   the STARS   (Strategic Teaming   and Resource   Sharing)     Alliance Callaway
Sincerely, A
member of the STARS (Strategic Teaming and Resource Sharing)
Alliance Callaway
* Comanche Peak
* Comanche Peak
* Diablo Canyon
* Diablo Canyon
Line 33: Line 34:
* San Onofre
* San Onofre
* South Texas Project
* South Texas Project
* Wolf Creek
* Wolf Creek  


Document Control Desk                                                     PG&E Letter DCL-12-047 April 30, 2012 Page 2 d ngd/4955/5030 1167 cc:           Gary W. Butner, Branch Chief, California Department of Public Health Elmo E. Collins, NRC Region IV Michael S. Peck, NRC, Senior Resident Inspector Joseph M. Sebrosky, NRR Project Manager Diablo Distribution A member   of   the STARS   (Strategic Teaming   and Resource Sharing) Alliance Callaway
Document Control Desk April 30, 2012 PG&E Letter DCL-12-047 Page 2 d ngd/4955/5030 1167 cc:
Gary W. Butner, Branch Chief, California Department of Public Health Elmo E. Collins, NRC Region IV Michael S. Peck, NRC, Senior Resident Inspector Joseph M. Sebrosky, NRR Project Manager Diablo Distribution A
member of the STARS (Strategic Teaming and Resource Sharing)
Alliance Callaway
* Comanche Peak
* Comanche Peak
* Diablo Canyon
* Diablo Canyon

Latest revision as of 03:25, 12 January 2025

Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation
ML12122A012
Person / Time
Site: Diablo Canyon  
Issue date: 04/30/2012
From: Becker J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-12-047
Download: ML12122A012 (2)


Text

Pacific Gas and Electric Company April 30, 2012 PG&E Letter DCL-12-047 u.s. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 James R. Becker Site Vice President 10 CFR 50.90 Diablo Canyon Power Plant Mail Code 104/6 P. O. Box 56 Avila Beach, CA 93424 805.545.3462 Internal: 691.3462 Fax: 805.545.6445 Proposed Implementation Schedule for License Amendment Request 11-06, Revision to Technical Specification 3.3.5, "Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation"

Dear Commissioners and Staff:

Pursuant to 10 CFR 50.90, Pacific Gas and Electric Company (PG&E) submitted an application for amendment to Facility Operating License Nos. DPR-80 and DPR-82 by PG&E Letter DCL-11-072, "License Amendment Request 11-06, Revision to Technical Specification 3.3.5, 'Loss of Power (LOP) Diesel Generator (DG) Start Instrumentation,'" dated October 24,2011. PG&E Letter DCL-11-072 submitted for Nuclear Regulatory Commission (NRC) review and approval proposed to revise Technical Specification (TS) 3.3.5, "Loss of Power (LOP) Diesel Generator (DG)

Start Instrumentation," revise Final Safety Analysis Report Update (FSARU)

Appendix 6.20 and Sections 6.3, 15.3, and 15.4, revise the loss-of-coolant accident control room operator and offsite do~e analysis of record described in the FSARU, and provide a new process for revising input values to this analysis.

In PG&E letter DCL-11-072, PG&E requested that the license amendments be made effective upon NRC issuance, to be implemented during Unit 2 Refueling Outage 17 and Unit 1 Refueling Outage 18. To facilitate the actions required to implement the license amendments, PG&E requests that the implementation schedule be changed to "during Unit 1 Refueling Outage 18 and Unit 2 Refueling Outage 18."

If you have any questions or require additional information, please contact Mr. Tom Baldwin at (805) 545-4720.

Sincerely, A

member of the STARS (Strategic Teaming and Resource Sharing)

Alliance Callaway

  • Comanche Peak
  • Diablo Canyon
  • Palo Verde
  • San Onofre
  • Wolf Creek

Document Control Desk April 30, 2012 PG&E Letter DCL-12-047 Page 2 d ngd/4955/5030 1167 cc:

Gary W. Butner, Branch Chief, California Department of Public Health Elmo E. Collins, NRC Region IV Michael S. Peck, NRC, Senior Resident Inspector Joseph M. Sebrosky, NRR Project Manager Diablo Distribution A

member of the STARS (Strategic Teaming and Resource Sharing)

Alliance Callaway

  • Comanche Peak
  • Diablo Canyon
  • Palo Verde
  • San Onofre
  • Wolf Creek