j r,                                                                                                           t ENCLOSURE 1 i
j r,
NOTICE OF VIOLATION                                             l Southern California Edison Co.                             Docket No.:     50-362                 l San Onofre Nuclear Generating Station                       License No.:   NPF-15                 )
t ENCLOSURE 1 i
                                                                                                            -1 During an NRC inspection conducted on February 23 through April 5, l'.,97, one violation           {
NOTICE OF VIOLATION l
of NRC requirements was identified. In accordance with the " General Statement of Policy           l and Procedure for NRC Enforcement Actions," NUREG-1600, the violation is listed below:             i i
Southern California Edison Co.
A. Technical Specification Surveillance Requirement 3.4.3.1.1 requires, in part, during       .
Docket No.:
a pressurizer cooldown operation, to verify at a frequency of 30 minutes that the           l pressurizer cooldown rate is within the limit of 200 F in any 1-hour period.
50-362 l
Contrary to the above, on March 4,1997, during a pressurizer .;ooldown operation,           j a pressurizer cooldown rate of about 265 F in a 1-hour period occurred because the         l operators failed to properly verify that the pressurizer cooldown rate was within the
San Onofre Nuclear Generating Station License No.:
                                                                                                            .l limit of 200 F in any 1 hour period.                                                       1 i
NPF-15
This is a Severity Level IV violation (Supplement 1) applicable to Unit 2                   ;
)
(Violation 361/97005-01).                                                                   !
-1 During an NRC inspection conducted on February 23 through April 5, l'.,97, one violation
Dated at Walnut Creek, California, this 15th day of April 1997                                                                       i i
{
t i
of NRC requirements was identified. In accordance with the " General Statement of Policy l
c l
and Procedure for NRC Enforcement Actions," NUREG-1600, the violation is listed below:
I l
i i
9704220104 970415                                                                                     !
A.
PDR   ADOCK 05000361                                                                                 '
Technical Specification Surveillance Requirement 3.4.3.1.1 requires, in part, during a pressurizer cooldown operation, to verify at a frequency of 30 minutes that the l
G                    PDR       .                                                                      1
pressurizer cooldown rate is within the limit of 200 F in any 1-hour period.
                                                                                                                \
Contrary to the above, on March 4,1997, during a pressurizer.;ooldown operation, j
                                                          .}}
a pressurizer cooldown rate of about 265 F in a 1-hour period occurred because the l
operators failed to properly verify that the pressurizer cooldown rate was within the
.l limit of 200 F in any 1 hour period.
1 i
This is a Severity Level IV violation (Supplement 1) applicable to Unit 2 (Violation 361/97005-01).
Dated at Walnut Creek, California, this 15th day of April 1997 i
i t
i c
l I
l 9704220104 970415 PDR ADOCK 05000361 G
PDR 1
\\
-}}

Latest revision as of 20:41, 11 December 2024

Notice of Violation from Insp on 970223-0405.Violation Noted:On 970304,during Pressurizer Cooldown Operation, Operator Failed to Properly Verify That Pressurizer Cooldown Rate Was within Limit of 200 F in Any 1 Hr Period
ML20137X643
Person / Time
Site: San Onofre  
Issue date: 04/15/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20137X597 List:
References
50-362-97-05, 50-362-97-5, NUDOCS 9704220104
Download: ML20137X643 (1)


Text

.-..

=-

j..

j r,

t ENCLOSURE 1 i

NOTICE OF VIOLATION l

Southern California Edison Co.

Docket No.:

50-362 l

San Onofre Nuclear Generating Station License No.:

NPF-15

)

-1 During an NRC inspection conducted on February 23 through April 5, l'.,97, one violation

{

of NRC requirements was identified. In accordance with the " General Statement of Policy l

and Procedure for NRC Enforcement Actions," NUREG-1600, the violation is listed below:

i i

A.

Technical Specification Surveillance Requirement 3.4.3.1.1 requires, in part, during a pressurizer cooldown operation, to verify at a frequency of 30 minutes that the l

pressurizer cooldown rate is within the limit of 200 F in any 1-hour period.

Contrary to the above, on March 4,1997, during a pressurizer.;ooldown operation, j

a pressurizer cooldown rate of about 265 F in a 1-hour period occurred because the l

operators failed to properly verify that the pressurizer cooldown rate was within the

.l limit of 200 F in any 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period.

1 i

This is a Severity Level IV violation (Supplement 1) applicable to Unit 2 (Violation 361/97005-01).

Dated at Walnut Creek, California, this 15th day of April 1997 i