{{#Wiki_filter:NFPA-805 Transition Pilot Plant Frequently Asked Questions Plant:                Harris Nuclear Plant (HNP)          FAQ # 06-0019 Rev. 0 Submittal Date:        11-30-06 Licensee Contact:     Alan Holder                          Tele/email 919-546-3372 NRC Contact:                                               Tele/email Subject Interpretive Guidance?          Yes / No Proposed New Guidance not currently in NEI 04-02?          Yes / No Details NEI 04-02 Guidance needing interpretation (include section, paragraph number, and line number as applicable):
{{#Wiki_filter:NFPA-805 Transition Pilot Plant Frequently Asked Questions Plant:                Harris Nuclear Plant (HNP)          FAQ # 06-0019 Rev. 0 Submittal Date:        11-30-06 Licensee
 
==Contact:==
Alan Holder                          Tele/email 919-546-3372 NRC
 
==Contact:==
Tele/email Subject Interpretive Guidance?          Yes / No Proposed New Guidance not currently in NEI 04-02?          Yes / No Details NEI 04-02 Guidance needing interpretation (include section, paragraph number, and line number as applicable):
NEI 04-02, Section 4.3.1, Fundamental Fire Protection Program and Design Elements Transition Review, appendices to list acceptable interpretations to the NFPA 805 standard (future).
NEI 04-02, Section 4.3.1, Fundamental Fire Protection Program and Design Elements Transition Review, appendices to list acceptable interpretations to the NFPA 805 standard (future).
Circumstances requiring guidance interpretation or new guidance:
Circumstances requiring guidance interpretation or new guidance:

Latest revision as of 15:56, 7 December 2019

NFPA 805 Transition Pilot Plant FAQ 06-0019, Rev. 0
ML070030437
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 11/30/2006
From: Holder A
Progress Energy Co
To:
Office of Nuclear Reactor Regulation
References
06-0019, Rev. 0
Download: ML070030437 (2)


Text

NFPA-805 Transition Pilot Plant Frequently Asked Questions Plant: Harris Nuclear Plant (HNP) FAQ # 06-0019 Rev. 0 Submittal Date: 11-30-06 Licensee

Contact:

Alan Holder Tele/email 919-546-3372 NRC

Contact:

Tele/email Subject Interpretive Guidance? Yes / No Proposed New Guidance not currently in NEI 04-02? Yes / No Details NEI 04-02 Guidance needing interpretation (include section, paragraph number, and line number as applicable):

NEI 04-02, Section 4.3.1, Fundamental Fire Protection Program and Design Elements Transition Review, appendices to list acceptable interpretations to the NFPA 805 standard (future).

Circumstances requiring guidance interpretation or new guidance:

Clarification of NFPA-805, Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition), Chapter 3, Section 3.3.1.2 Control of Combustibles. (1) Wood used within the power block shall be listed pressure-impregnated or coated with a listed fire-retardant application.

Specifically, the definition of Power Block and Plant and how these will be applied when reviewing Chapter 3 transition.

Detail contentious points if licensee and NRC have not reached agreement:

NA Potentially relevant existing FAQ numbers:

FAQ 06-0007 1 of 2

Response Section Proposed Resolution of FAQ and basis for the proposal:

This FAQ asks to define, where used in Chapter 3, power block and plant are intended to mean or are equivalent to, areas in which a fire could jeopardize the ability to meet the performance criteria described in section 1.5.1.

This is based on RIN 3150-AG48 (Statement of Considerations), which states in part, under NFPA 805, the 10CFR50.48(a)(2)(iii) requirement to limit fire damage to SSCs important to safety so that the capability to safely shut down the plant is ensured is satisfied by meeting the performance criteria in Section 1.5.1 of NFPA 805, the Chapter 3 applicability is limited to only these SSCs. Therefore for regulatory purposes, the power block and plant is synonymous with areas in which a fire could jeopardize the ability to meet the performance criteria described in section 1.5.1, Nuclear Safety Performance Criteria.

If appropriate, provide proposed rewording of guidance for inclusion in next revision.

As follows; Clarification NFPA 805 specific sections as may be applied under NEI 04-02, to be included in (New) Appendix K, to NEI 04-02 upon approval of specific clarification (final formatting to be provided by NEI contract writers).

Specific clarification to NFPA Chapter 3, from FAQ 06-0019, Where used in Chapter 3, power block and plant are equivalent to areas in which a fire could jeopardize the ability to meet the performance criteria described in section 1.5.1, Nuclear Safety Performance Criteria.

2 of 2