ML100770320: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Newport, Christopher From: Newport, Christopher Sent: Thursday, December 03, 2009 7:00 AM To: Kern, David  
{{#Wiki_filter:Newport, Christopher From:                       Newport, Christopher Sent:                       Thursday, December 03, 2009 7:00 AM To:                         Kern, David


==Subject:==
==Subject:==
RE: TMI 12/3 Plant Status Thanks Dave.From: Kern, David Sent: Thursday, December 03, 2009 6:59 AM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier; Bamford, Peter  
RE: TMI 12/3 Plant Status Thanks Dave.
From: Kern, David Sent: Thursday, December 03, 2009 6:59 AM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier; Bamford, Peter


==Subject:==
==Subject:==
TMI 12/3 Plant Status Ron, Chris: 12/3/09 (0645) status: Rx defueled S/D Risk = Yellow, due to 'B' 120 volt vital bus deenergized for planned work SFP TTB > 16 hours Both trains of SFP cooling available new 'B' SG was seated in place on floor of 'D' ring at 0500 today.one of the 'A' SG RCS cold legs is welded in place to 1" thickness.
TMI 12/3 Plant Status Ron, Chris:
More welding to follow.today's key work: setup weld equipment on 'B' SG RCS cold legs.overhaul 'B' vital inverter move RCS hot leg piping into the reactor building continue restoration of nuclear riverwater system start/continue RCS hot leg machining in preparation for welds (we'll watch for contamination controls in containment) continue welding 'A' SG RCS cold legs Dave From: Bellamy, Ronald Sent: Wednesday, December 02, 2009 4:00 PM To: Kern, David; Newport, Christopher Cc: Barber, Scott; Brand, Javier  
12/3/09 (0645) status:
Rx defueled S/D Risk = Yellow, due to 'B' 120 volt vital bus deenergized for planned work SFP TTB > 16 hours Both trains of SFP cooling available new 'B' SG was seated in place on floor of 'D' ring at 0500 today.
one of the 'A' SG RCS cold legs is welded in place to 1" thickness. More welding to follow.
today's key work:
setup weld equipment on 'B' SG RCS cold legs.
overhaul 'B' vital inverter move RCS hot leg piping into the reactor building continue restoration of nuclear riverwater system start/continue RCS hot leg machining in preparation for welds (we'll watch for contamination controls in containment) continue welding 'A' SG RCS cold legs Dave From: Bellamy, Ronald Sent: Wednesday, December 02, 2009 4:00 PM To: Kern, David; Newport, Christopher Cc: Barber, Scott; Brand, Javier


==Subject:==
==Subject:==
RE: TMI 12/3 Plant Status via E-Mail ok, thx From: Kern, David Sent: Wednesday, December 02, 2009 3:53 PM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier  
RE: TMI 12/3 Plant Status via E-Mail ok, thx From: Kern, David Sent: Wednesday, December 02, 2009 3:53 PM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier


==Subject:==
==Subject:==
TMI 12/3 Plant Status via E-Mail Ron: 1  
TMI 12/3 Plant Status via E-Mail Ron:
, We'll do plant status by e-mail prior to 0730 on 12/3. We will all be taking our licensee General Employee Training Refresher course and exam at the time of the call.Dave 2}}
1
 
, We'll do plant status by e-mail prior to 0730 on 12/3. We will all be taking our licensee General Employee Training Refresher course and exam at the time of the call.
Dave 2}}

Latest revision as of 21:40, 13 November 2019

E-mail from C. Newport of USNRC to D. Kern of USNRC, Regarding TMI 12/3 Plant Status
ML100770320
Person / Time
Site: Three Mile Island  Constellation icon.png
Issue date: 12/03/2009
From: Christopher Newport
NRC/RGN-I/DRP/PB6
To: David Kern
NRC/RGN-I/DRP/PB6
References
FOIA/PA-2010-0118
Download: ML100770320 (2)


Text

Newport, Christopher From: Newport, Christopher Sent: Thursday, December 03, 2009 7:00 AM To: Kern, David

Subject:

RE: TMI 12/3 Plant Status Thanks Dave.

From: Kern, David Sent: Thursday, December 03, 2009 6:59 AM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier; Bamford, Peter

Subject:

TMI 12/3 Plant Status Ron, Chris:

12/3/09 (0645) status:

Rx defueled S/D Risk = Yellow, due to 'B' 120 volt vital bus deenergized for planned work SFP TTB > 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> Both trains of SFP cooling available new 'B' SG was seated in place on floor of 'D' ring at 0500 today.

one of the 'A' SG RCS cold legs is welded in place to 1" thickness. More welding to follow.

today's key work:

setup weld equipment on 'B' SG RCS cold legs.

overhaul 'B' vital inverter move RCS hot leg piping into the reactor building continue restoration of nuclear riverwater system start/continue RCS hot leg machining in preparation for welds (we'll watch for contamination controls in containment) continue welding 'A' SG RCS cold legs Dave From: Bellamy, Ronald Sent: Wednesday, December 02, 2009 4:00 PM To: Kern, David; Newport, Christopher Cc: Barber, Scott; Brand, Javier

Subject:

RE: TMI 12/3 Plant Status via E-Mail ok, thx From: Kern, David Sent: Wednesday, December 02, 2009 3:53 PM To: Bellamy, Ronald; Newport, Christopher Cc: Barber, Scott; Brand, Javier

Subject:

TMI 12/3 Plant Status via E-Mail Ron:

1

, We'll do plant status by e-mail prior to 0730 on 12/3. We will all be taking our licensee General Employee Training Refresher course and exam at the time of the call.

Dave 2