| {{#Wiki_filter:September 7, 2010 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD | | {{#Wiki_filter:September 7, 2010 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of ) |
| | ) |
| | TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-391-OL |
| | ) |
| | (Watts Bar Unit 2) ) |
| | NRC STAFFS SEPTEMBER 2010 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2 LICENSE RENEWAL APPLICATION The Staff of the Nuclear Regulatory Commission (Staff) hereby provides the information the Atomic Safety and Licensing Board (Board) requested in its May 26, 2010 Scheduling Order (Order). In the Order, the Board instructed the Staff to submit a report on July 2, 2010, to be updated on the first Tuesday of every other month thereafter, updating its estimates of the dates on which the Final Environmental Impact Statement (FEIS) and the Final Safety Evaluation Report (FSER) will be issued. |
| | The FEIS and FSER are currently scheduled to be issued in June 2011. The Staff notes that these dates are unchanged from the Staffs initial report filed on July 2, 2010. |
| | Respectfully submitted, |
| | /Signed (electronically) by/ |
| | Michael G. Dreher Counsel for NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555-0001 (301) 415-2314 michael.dreher@nrc.gov |
|
| |
|
| In the Matter of ) | | UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of ) |
| )
| | ) |
| TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-391-OL ) (Watts Bar Unit 2) ) | | TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL |
| | ) |
| | (Watts Bar Nuclear Plant, Unit 2) ) |
| | CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing NRC STAFFS SEPTEMBER 2010 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2 LICENSE RENEWAL APPLICATION, dated September 7, 2010, have been served upon the following by the Electronic Information Exchange, this 7th day of September, 2010: |
| | Administrative Judge Office of Commission Appellate Lawrence G. McDade, Chair Adjudication Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: O-16G4 Mail Stop: T-3 F23 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: OCAAMAIL.resource@nrc.gov E-mail: lgm1@nrc.gov Administrative Judge Office of the Secretary Paul B. Abramson Attn: Rulemaking and Adjudications Staff Atomic Safety and Licensing Board Panel Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: Hearing.Docket@nrc.gov E-mail: pba@nrc.gov Administrative Judge Edward Vigluicci, Esq. |
| | Gary S. Arnold Christopher C. Chandler, Esq. |
| | Atomic Safety and Licensing Board Panel Scott A. Vance, Esq. |
| | U.S. Nuclear Regulatory Commission Tennessee Valley Authority Mail Stop: T-3 F23 400 West Summit Hill Drive, WT 6A-K Washington, DC 20555-0001 Knoxville, TN 37902 E-mail: gxa1@nrc.gov E-mail: ejvigluicci@tva.gov ccchandler0@tva.gov savance@tva.gov |
|
| |
|
| NRC STAFF'S SEPTEMBER 2010 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2 LICENSE RENEWAL APPLICATION The Staff of the Nuclear Regulatory Commission ("Staff") hereby provides the information the Atomic Safety and Licensing Board ("Board") requested in its May 26, 2010
| | 2 Kathryn M. Sutton, Esq. Diane Curran Paul M. Bessette, Esq. for Southern Alliance for Clean Energy Morgan, Lewis & Bockius, LLP (SACE) 1111 Pennsylvania Avenue, NW Harmon, Curran, Spielberg & Eisenberg, LLP Washington, D.C. 20004 1726 M Street N.W., Suite 600 E-mail: ksutton@morganlewis.com Washington, DC 20036 E-mail: pbessette@morganlewis.com E-mail: dcurran@harmoncurran.com |
| | | /Signed (electronically) by/ |
| Scheduling Order ("Order"). In the Order, the Board instructed the Staff to submit a report on
| | Michael G. Dreher Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555 (301) 415-2314 E-Mail: Michael.Dreher@nrc.gov Signed: September 7, 2010}} |
| | |
| July 2, 2010, to be updated on the first Tuesday of every other month thereafter, updating its
| |
| | |
| estimates of the dates on which the Final Environmental Impact Statement ("FEIS") and the
| |
| | |
| Final Safety Evaluation Report ("FSER") will be issued.
| |
| The FEIS and FSER are currently scheduled to be issued in June 2011. The Staff notes that these dates are unchanged from the Staff's initial report filed on July 2, 2010.
| |
| | |
| Respectfully submitted, /Signed (electronically) by/
| |
| Michael G. Dreher Counsel for NRC Staff
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Mail Stop O15-D21
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| (301) 415-2314
| |
| | |
| michael.dreher@nrc.gov UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
| |
| | |
| In the Matter of )
| |
| )
| |
| TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL ) (Watts Bar Nuclear Plant, Unit 2) )
| |
| | |
| CERTIFICATE OF SERVICE
| |
| | |
| I hereby certify that copies of the foregoing "NRC STAFF'S SEPTEMBER 2010 BIMONTHLY
| |
| | |
| REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2
| |
| | |
| LICENSE RENEWAL APPLICATION," dated September 7, 2010, have been served upon the
| |
| | |
| following by the Electronic Information Exchange, this 7 th day of September, 2010:
| |
| | |
| Administrative Judge
| |
| | |
| Lawrence G. McDade, Chair
| |
| | |
| Atomic Safety and Licensing Board Panel
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Mail Stop: T-3 F23
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| E-mail: lgm1@nrc.gov Office of Commission Appellate Adjudication
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Mail Stop: O-16G4
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| E-mail: OCAAMAIL.resource@nrc.gov Administrative Judge Paul B. Abramson
| |
| | |
| Atomic Safety and Licensing Board Panel
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Mail Stop: T-3 F23
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| E-mail: pba@nrc.gov Office of the Secretary Attn: Rulemaking and Adjudications Staff
| |
| | |
| Mail Stop: O-16G4
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| E-mail: Hearing.Docket@nrc.gov Administrative Judge Gary S. Arnold
| |
| | |
| Atomic Safety and Licensing Board Panel
| |
| | |
| U.S. Nuclear Regulatory Commission
| |
| | |
| Mail Stop: T-3 F23
| |
| | |
| Washington, DC 20555-0001
| |
| | |
| E-mail: gxa1@nrc.gov Edward Vigluicci, Esq.
| |
| Christopher C. Chandler, Esq.
| |
| | |
| Scott A. Vance, Esq.
| |
| | |
| Tennessee Valley Authority
| |
| | |
| 400 West Summit Hill Drive, WT 6A-K
| |
| | |
| Knoxville, TN 37902
| |
| | |
| E-mail: ejvigluicci@tva.gov
| |
| | |
| ccchandler0@tva.gov
| |
| | |
| savance@tva.gov
| |
| | |
| 2 Kathryn M. Sutton, Esq. | |
| Paul M. Bessette, Esq. | |
| | |
| Morgan, Lewis & Bockius, LLP | |
| | |
| 1111 Pennsylvania Avenue, NW | |
| | |
| Washington, D.C. 20004 | |
| | |
| E-mail: ksutton@morganlewis.com E-mail: pbessette@morganlewis.com Diane Curran for Southern Alliance for Clean Energy (SACE) | |
| Harmon, Curran, Spielberg & Eisenberg, LLP
| |
| | |
| 1726 M Street N.W., Suite 600
| |
| | |
| Washington, DC 20036
| |
| | |
| E-mail: dcurran@harmoncurran.com | |
| /Signed (electronically) by/
| |
| Michael G. Dreher Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555 (301) 415-2314 E-Mail: Michael.Dreher@nrc.gov Signed: September 7, 2010}} | |
|
---|
Category:Legal-Correspondence/Miscellaneous
MONTHYEARML15125A5182015-05-0505 May 2015 Notification of NRC Staff Request for Authority to Issue License ML15049A3562015-02-18018 February 2015 Notice of Appearance of Jeremy L. Wachutka ML15048A0542015-02-17017 February 2015 Notice of Appearance of Christopher C. Chandler ML14245A0912014-09-0202 September 2014 NRC Staff'S September 2014 Bi-Monthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML14182A6562014-07-0101 July 2014 NRC Staff'S July 2014 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML14175A5362014-06-23023 June 2014 Curran Letter to Macfarlane Resubmitted Watts Bar Unit 2 Operating License Proceeding ML14126A4162014-05-0606 May 2014 NRC Staff'S May 2014 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML14063A0782014-03-0404 March 2014 NRC Staff'S March 2014 Bi-Monthly Report Regarding Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML14007A4562014-01-0707 January 2014 NRC Staff'S January 2014 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML13309B0302013-11-0505 November 2013 NRC Staff'S November 2013 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML13274A6502013-10-0101 October 2013 Notice of Withdrawal of Harriet A. Cooper on Behalf of Tennessee Valley Authority in the Matter of Watts Bar, Unit 2 ML13274A1712013-10-0101 October 2013 Notice of Withdrawal of Edward J. Vigluicci, on Behalf of Tennessee Valley Authority in the Matter of Tennessee Valley Authority (Watts Bar Nuclear Plant, Unit 2) ML13274A0622013-10-0101 October 2013 Notice of Withdrawal of Christopher C. Chandler on Behalf of the Tennessee Valley Authority in the Matter of Watts Bar, Unit 2 ML13246A3022013-09-0303 September 2013 NRC Staff'S September 2013 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant, Unit 2, License Application ML13196A4682013-07-15015 July 2013 Certificate of Services for Southern Alliance for Clean Energy'S 42nd Supplemental Mandatory Disclosures Pursuant to 10 C.F.R. Section 2.336 in the Matter of Watts Bar, Unit 2 ML13183A5442013-07-0202 July 2013 NRC Staff July 2013 Bi-Monthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML13155A5812013-06-0404 June 2013 NRC Staff'S Notification of Public Availability of Final Environmental Impact Statement Supplement Watts Bar Nuclear Plant Unit 2 License Application ML13127A3752013-05-0707 May 2013 NRC Staff'S May 2013 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Plant Unit 2 License Application ML13105A4292013-04-15015 April 2013 Certificate of Services for Southern Alliance for Clean Energy Submittal of the 39th Supplemental Mandatory Disclosures in the Matter of Watts Bar, Unit 2 ML13074A1472013-03-15015 March 2013 Certificate of Service for a Letter from Diane Curran to Counsel for TVA and the NRC Staff Regarding Saces Thirty Eighth Supplement to Its Mandatory Disclosures ML13064A1952013-03-0505 March 2013 NRC Staff'S March 2013 Bimonthy Report Regarding the Schedule for Review of the Watts Bar Nuclear, Unit 2, License Application ML13057A9832013-02-26026 February 2013 Comments on NRC Public Participation Process in the Matter of Watts Bar, Unit 2, Operating Licensing Proceeding ML13057A9822013-02-26026 February 2013 Transmittal of Letter to Commissioners Regarding Public Participation Regulations in the Matter of Watts Bar, Unit 2, Operating Licensing Proceeding ML13046A0632013-02-15015 February 2013 Certificate of Service for 02/15/2013 Letter from Diane Curran to Counsel for TVA and the NRC Staff Regarding Saces Thirty Seventh Supplement to Its Mandatory Disclosures ML13002A3082013-01-0202 January 2013 NRC Staff'S January 2013 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear, Unit 2 License Application ML12362A3172012-12-27027 December 2012 Proposed Scheduling Order Changes ML12352A1012012-12-17017 December 2012 Certificate of Service for Southern Alliance for Clean Energy Letter to Tennessee Valley Authority and Staff Thirty Fifth Supplemental Mandatory Disclosures ML12325A2852012-11-15015 November 2012 Certificate of Service for Southern Alliance for Clean Energy, Thirty Fourth Supplemental Initial Disclosures in the Matter of Watts Bar ML12325A2842012-11-15015 November 2012 Southern Alliance for Clean Energy, Thirty Fourth Supplemental Initial Disclosures in the Matter of Watts Bar ML12320A6732012-11-15015 November 2012 Certificate of Service for Southern Alliance for Clean Energy Thirty Third Supplement to Initial Disclosures of 01/15/2012 Pursuant to 10 CFR 2.336 ML12311A4712012-11-0606 November 2012 NRC Staff'S November 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Nuclear Unit 2 License Application ML12289A8082012-10-15015 October 2012 Certificate of Services for Southern Alliance for Clean Energy Thirty Third Supplement to Initial Disclosures of January 15, 2012 in the Matter of Watts Bar, Unit 2 ML12248A4142012-09-0404 September 2012 NRC Staff'S September 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML12198A3932012-07-16016 July 2012 Letter from Diane Curran Supplemental Mandatory Disclosures Pursuant to 10 C.F.R. 2.336 ML12185A1942012-07-0303 July 2012 NRC Staff'S July 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML12170B0422012-06-18018 June 2012 Certificate of Service for Petition to Suspend Final Decisions in All Pending Reactor Licensing Proceedings Etc ML12122A9622012-05-0101 May 2012 NRC Staff'S May 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML12066A0652012-03-0606 March 2012 NRC Staff'S March 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML12017A2552012-01-17017 January 2012 Southern Alliance for Clean Energy (Sace) 24th Supplemental Disclosures ML12003A1772012-01-0303 January 2012 NRC Staff'S January 2012 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML12003A0012011-12-30030 December 2011 Notice of Withdrawal of Andrea Jones, OGC Counsel ML11305A1832011-11-0101 November 2011 NRC Staff'S November 2011 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML11258A2062011-09-15015 September 2011 Sace Twentieth Supplemental Mandatory Disclosures Pursuant to 10 C.F.R Section 2.336 ML11249A2052011-09-0606 September 2011 NRC Staff'S September 6, 2011 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML11195A2502011-07-14014 July 2011 Sace Eighteenth Supplemental Mandatory Disclosures Pursuant to 10 C.F.R. 2.336 ML1116621882011-06-15015 June 2011 Sace Seventeenth Supplemental Mandatory Disclosures Pursuant to 10 C.F.R. Section ML1113206872011-05-12012 May 2011 Sace Sixteenth Supplemental Mandatory Disclosures ML1112307992011-05-0303 May 2011 NRC Staff'S March 2011 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application ML1107408562011-03-15015 March 2011 Sace Fourteenth Supplemental Mandatory Disclosures Pursuant to 10 C.F.R. Section 2.336 ML1106013022011-03-0101 March 2011 NRC Staff'S March 2011 Bimonthly Report Regarding the Schedule for Review of the Watts Bar Number 2 License Application 2015-05-05
[Table view] |
Text
September 7, 2010 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )
)
TENNESSEE VALLEY AUTHORITY ) Docket Nos. 50-391-OL
)
(Watts Bar Unit 2) )
NRC STAFFS SEPTEMBER 2010 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2 LICENSE RENEWAL APPLICATION The Staff of the Nuclear Regulatory Commission (Staff) hereby provides the information the Atomic Safety and Licensing Board (Board) requested in its May 26, 2010 Scheduling Order (Order). In the Order, the Board instructed the Staff to submit a report on July 2, 2010, to be updated on the first Tuesday of every other month thereafter, updating its estimates of the dates on which the Final Environmental Impact Statement (FEIS) and the Final Safety Evaluation Report (FSER) will be issued.
The FEIS and FSER are currently scheduled to be issued in June 2011. The Staff notes that these dates are unchanged from the Staffs initial report filed on July 2, 2010.
Respectfully submitted,
/Signed (electronically) by/
Michael G. Dreher Counsel for NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555-0001 (301) 415-2314 michael.dreher@nrc.gov
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )
)
TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL
)
(Watts Bar Nuclear Plant, Unit 2) )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing NRC STAFFS SEPTEMBER 2010 BIMONTHLY REPORT REGARDING THE SCHEDULE FOR REVIEW OF THE WATTS BAR NUMBER 2 LICENSE RENEWAL APPLICATION, dated September 7, 2010, have been served upon the following by the Electronic Information Exchange, this 7th day of September, 2010:
Administrative Judge Office of Commission Appellate Lawrence G. McDade, Chair Adjudication Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: O-16G4 Mail Stop: T-3 F23 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: OCAAMAIL.resource@nrc.gov E-mail: lgm1@nrc.gov Administrative Judge Office of the Secretary Paul B. Abramson Attn: Rulemaking and Adjudications Staff Atomic Safety and Licensing Board Panel Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop: T-3 F23 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: Hearing.Docket@nrc.gov E-mail: pba@nrc.gov Administrative Judge Edward Vigluicci, Esq.
Gary S. Arnold Christopher C. Chandler, Esq.
Atomic Safety and Licensing Board Panel Scott A. Vance, Esq.
U.S. Nuclear Regulatory Commission Tennessee Valley Authority Mail Stop: T-3 F23 400 West Summit Hill Drive, WT 6A-K Washington, DC 20555-0001 Knoxville, TN 37902 E-mail: gxa1@nrc.gov E-mail: ejvigluicci@tva.gov ccchandler0@tva.gov savance@tva.gov
2 Kathryn M. Sutton, Esq. Diane Curran Paul M. Bessette, Esq. for Southern Alliance for Clean Energy Morgan, Lewis & Bockius, LLP (SACE) 1111 Pennsylvania Avenue, NW Harmon, Curran, Spielberg & Eisenberg, LLP Washington, D.C. 20004 1726 M Street N.W., Suite 600 E-mail: ksutton@morganlewis.com Washington, DC 20036 E-mail: pbessette@morganlewis.com E-mail: dcurran@harmoncurran.com
/Signed (electronically) by/
Michael G. Dreher Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O15-D21 Washington, DC 20555 (301) 415-2314 E-Mail: Michael.Dreher@nrc.gov Signed: September 7, 2010