| | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 February 7, 2017 Mr. Bryan C. Hanson Senior VP, Exelon Generation Co., LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 |
| | |
| | ==SUBJECT:== |
| | DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - OPERATOR LICENSING REEXAMINATION APPROVAL |
| | |
| | ==Dear Mr. Hanson:== |
| | The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing reexaminations at the Dresden Nuclear Power Station. The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license reapplications in connection with this reexamination and separately provided a list of approved applicants to Mr. Thomas Dean, Training Director. Note that any examination waivers and application denials have been addressed in separate correspondence. The NRC has approved the subject examinations. The NRC staff will administer the operating tests during the week of February 27, 2017. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630-829-9834. Please contact your Chief Examiner, Mr. Jesse Seymour, at 630-829-9561, if you have any questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. |
| | B. Hanson This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." Sincerely, /RA/ |
| | |
| | Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237, 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV Thomas Dean, Training Director B. Hanson Letter to Bryan C. Hanson from Robert J. Orlikowski dated February 7, 2017 |
| | |
| | ==SUBJECT:== |
| | DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - OPERATOR LICENSING REEXAMINATION APPROVAL DISTRIBUTION: Jeremy Bowen RidsNrrDorlLpl3-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Nancy Salgado, NRR Colleen Schmidt, DRS |
| | |
| | ADAMS Accession Number: ML17038A284 OFFICE RIII:DRS RIII:DRS RIII:DRS NAME RBaker for CSchmidt:jw RBaker for JSeymour ROrlikowski DATE 02/03/17 02/03/17 02/07/17 OFFICIAL RECORD COPY |
| }} | | }} |
Revision as of 06:05, 30 April 2018
|
---|
Category:Letter
MONTHYEARML24303A0712024-11-0404 November 2024 Letter to K. Meshigaud, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0992024-11-0101 November 2024 Lett to R. Carter, Principal Chief Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0152024-11-0101 November 2024 Letter to C. Harper, Chief Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0692024-11-0101 November 2024 Letter to J.A. Crawford, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1102024-11-0101 November 2024 Letter to R. Gasco, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1442024-11-0101 November 2024 Letter to V. Kitcheyna, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0272024-11-0101 November 2024 Letter to D. Rios, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0532024-11-0101 November 2024 Letter to J. Greendeer, President Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0492024-11-0101 November 2024 Letter G. Kakkak, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0892024-11-0101 November 2024 Letter to M. J. Wesaw, Chair Request to Initiate Section 106 Consultation for SLR of DNP Station RS-24-104, Nuclear Radiological Emergency Plan Document Revision2024-11-0101 November 2024 Nuclear Radiological Emergency Plan Document Revision ML24303A0172024-11-0101 November 2024 Letter to B. Peters, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0642024-11-0101 November 2024 Letter to J. Rupnick, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0432024-11-0101 November 2024 Letter to E. Elizondo, Sr. Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0302024-11-0101 November 2024 Letter to D.G. Lankford, Chief Request to Initiate Section 106 Consultation for SLR of DNP Station ML24291A0252024-11-0101 November 2024 Letter to R. Blanchard Tribal Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0552024-11-0101 November 2024 Letter to J. Keys, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0472024-11-0101 November 2024 Letter to G. Cheatham, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1342024-11-0101 November 2024 Letter to T. Carnes, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0202024-11-0101 November 2024 Letter to C. Chavers, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1462024-11-0101 November 2024 Letter to W. Gravelle, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1352024-11-0101 November 2024 Letter to T. Rhodd, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station IR 05000237/20254012024-11-0101 November 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000237/2025401 05000249/2025401 ML24303A1172024-11-0101 November 2024 Letter to R. Yob, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0132024-11-0101 November 2024 Letter to B. Barnes, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0512024-11-0101 November 2024 Letter to J. Barrett, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0242024-11-0101 November 2024 Letter to D. Kaskaske, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1422024-11-0101 November 2024 Letter to V. Jefferson, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0602024-11-0101 November 2024 Letter to J. R. Shotton, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24291A0272024-10-31031 October 2024 NRC Letter to C. Mayer Illinois SHPO Request to Initiate Section 106 Consultation for Subsequent License Renewal of Units 2 and 3 ML24291A0202024-10-31031 October 2024 NRC Letter to J. Loichinger Achp Request for Comments Concerning the Environmental Review of DNPS Units 2 and 3 Subsequent License Renewal Application IR 05000237/20240032024-10-29029 October 2024 Integrated Inspection Report 05000237/2024003 and 05000249/2024003 RS-24-103, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-10-21021 October 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-102, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-5912024-10-21021 October 2024 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-591 RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24225A2132024-09-26026 September 2024 Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval ML24253A0942024-09-23023 September 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID L-2024-Sle-0002) (Docket Numbers: 50-237 and 50-249) SVPLTR 24-0030, ISFSI Annual Effluent Release Report2024-09-20020 September 2024 ISFSI Annual Effluent Release Report ML24270A0332024-09-20020 September 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report IR 05000237/20244022024-09-19019 September 2024 – Security Baseline Inspection Report 05000237/2024402 and 05000249/2024402 - (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000237/20240022024-08-14014 August 2024 Integrated Inspection Report 05000237/2024002 and 05000249/2024002 ML24215A2912024-08-14014 August 2024 Request for Withholding Information from Public Disclosure Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations IR 05000237/20240102024-08-0909 August 2024 NRC Age-Related Degradation Inspection Report 05000237/2024010 and 05000249/2024010 2024-09-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 February 7, 2017 Mr. Bryan C. Hanson Senior VP, Exelon Generation Co., LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - OPERATOR LICENSING REEXAMINATION APPROVAL
Dear Mr. Hanson:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing reexaminations at the Dresden Nuclear Power Station. The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license reapplications in connection with this reexamination and separately provided a list of approved applicants to Mr. Thomas Dean, Training Director. Note that any examination waivers and application denials have been addressed in separate correspondence. The NRC has approved the subject examinations. The NRC staff will administer the operating tests during the week of February 27, 2017. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 630-829-9834. Please contact your Chief Examiner, Mr. Jesse Seymour, at 630-829-9561, if you have any questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
B. Hanson This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." Sincerely, /RA/
Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237, 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV Thomas Dean, Training Director B. Hanson Letter to Bryan C. Hanson from Robert J. Orlikowski dated February 7, 2017
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - OPERATOR LICENSING REEXAMINATION APPROVAL DISTRIBUTION: Jeremy Bowen RidsNrrDorlLpl3-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Nancy Salgado, NRR Colleen Schmidt, DRS
ADAMS Accession Number: ML17038A284 OFFICE RIII:DRS RIII:DRS RIII:DRS NAME RBaker for CSchmidt:jw RBaker for JSeymour ROrlikowski DATE 02/03/17 02/03/17 02/07/17 OFFICIAL RECORD COPY