{{#Wiki_filter:Nth-of | {{#Wiki_filter:Nth-of -a -Kind Licensing Considerations for Micro-Reactors Mission: L icenses and regulate the Nation's civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and security and to protect the environment. | ||
Enabling safe and timely decisions for advanced reactors. | Enabling safe and timely decisions for advanced reactors. | ||
Line 26: | Line 26: | ||
2 INNOVATION What is NeXT Licensing? | 2 INNOVATION What is NeXT Licensing? | ||
An approach by which a robust up-front approval of a common design enables efficient, predictable licensing of | An approach by which a robust up-front approval of a common design enables efficient, predictable licensing of nth-of-a-kind reactors | ||
* Standard design approved in a manufacturing license, design certification, construction permit and | * Standard design approved in a manufacturing license, design certification, construction permit and operating license, or combined operating license Up-Front Approval of | ||
* Technical issues resolved the | * Technical issues resolved the Common Plant | ||
* Standardized operational programs | * Standardized operational programs (as appropriate) | ||
* Generic environmental review | * Generic environmental review (as appropriate) | ||
* Hearing covering the | * Hearing covering the common design | ||
* Address administrative processes | * Address administrative processes | ||
* Confirmation of | * Confirmation of site suitability for design Nth-of-a-Kind | ||
* Closure of ITAAC/license conditions Licensing | * Closure of ITAAC/license conditions Licensing | ||
* Confirmatory site-specific inspection | * Confirmatory site-specific inspection | ||
Line 39: | Line 39: | ||
* Operating decision | * Operating decision | ||
3 The NRC staff is proactively | 3 The NRC staff is proactively enhancing clarity, reliability, and efficiency for licensing and regulation of micro-reactors | ||
Clear | Clear Reliable Efficient Coherent, logical, and Prompt, fair, and Risk-informed and practical regulatory decisive regulation performance-based approaches that will that lends stability to regulation that delivers allow for safe and licensing and timely results and uses secure deployment deployment resources effectively | ||
4 TRANSFORMATION Risk-informed licensing Consequence oriented | 4 TRANSFORMATION Risk-informed licensing Consequence oriented approaches Regulatory Advanced Reactor Generic Environmental Modernization I mp a c t S tatement Fees, ARCOP, Policy Issues, Guidance (ARCAP) | ||
Emergency Preparedness | Emergency Preparedness rule | ||
Pre -application Staged licensing Core teams Licensing Efficiencies | Pre -application Staged licensing Core teams Licensing Efficiencies International engagement Direct communication (audits) | ||
Focused ACRS interactions Streamlined documentation Optimized environmental reviews 5 | Focused ACRS interactions Streamlined documentation Optimized environmental reviews 5 | ||
ACTIONS | ACTIONS | ||
The NRC staff is taking actions to prioritize and address licensing and deployment considerations related to micro- | The NRC staff is taking actions to prioritize and address licensing and deployment considerations related to micro-reactors. | ||
* SECY-24-0008: Micro | * SECY-24-0008: Micro -Reactor Licensing and Deployment Considerations: Fuel Loading and Operational Testing at a Factory (ML23207A252) | ||
* Micro | * Micro -reactors Licensing Strategies White Paper (ML21235A418) | ||
* SECY-20-0093: Policy and Licensing Considerations Related to Micro | * SECY-20-0093: Policy and Licensing Considerations Related to Micro - | ||
Reactors ( | Reactors ( ML20254A363) | ||
6 ACTIONS SECY- | 6 ACTIONS SECY-24-0008 | ||
SECY | SECY 0008, Micro-Reactor Licensing and Deployment Considerations: Fuel Loading and Operational Testing at a Factory, seeks Commission policy direction on regulatory approaches related to three topics: | ||
(1) Features to preclude | (1) Features to preclude criticality (2) Fuel loading at a factory (3) Operational testing at a factory | ||
7 ACTIONS Catalyzing Micro-Reactors o | 7 ACTIONS Catalyzing Micro-Reactors o Loading Fuel and Operational Testing o Transportation of fueled reactors o Standardization of operational programs (as appropriate) o Environmental review o Site characterization o Timeframe for authorization to operate at the deployment site o Physical and Cyber Security o Emergency Preparedness o Decommissioning process and decommissioning funding assurance o Staffing, training, qualification requirements o Commercial mobile micro-reactors o Licensing replacement reactors o Autonomous operation and remote operation o Storage of fuel after irradiation in a power reactor o Siting in densely populated areas o Aircraft impact assessment o Commercial maritime and space applications 8 WHATS NEXT? | ||
Topics of interest: | Topics of interest: | ||
* Maximal design s | * Maximal design s tandardization | ||
* Standardization of | * Standardization of operation programs (as appropriate) | ||
* S | * S ite characterization | ||
* Streamlined licensing process and safety review | * Streamlined licensing process and safety review | ||
* Environmental review | * Environmental review | ||
Line 76: | Line 76: | ||
9 Success Strategies | 9 Success Strategies | ||
Optimizing Licensing | Optimizing Licensing Proactive Stakeholder Robust Preapplication Review s Engagement Activities | ||
10 Thank you. | 10 Thank you. | ||
11}} | 11}} |
Latest revision as of 13:59, 4 October 2024
ML24141A155 | |
Person / Time | |
---|---|
Issue date: | 05/20/2024 |
From: | Office of Nuclear Reactor Regulation |
To: | |
References | |
Download: ML24141A155 (1) | |
Text
Nth-of -a -Kind Licensing Considerations for Micro-Reactors Mission: L icenses and regulate the Nation's civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and security and to protect the environment.
Enabling safe and timely decisions for advanced reactors.
- Execute safety-focused regulatory actions
- Optimize regulatory framework
- Advance technology readiness
- Maximize benefits of standardization
- Enable efficient stakeholder engagement
2 INNOVATION What is NeXT Licensing?
An approach by which a robust up-front approval of a common design enables efficient, predictable licensing of nth-of-a-kind reactors
- Standard design approved in a manufacturing license, design certification, construction permit and operating license, or combined operating license Up-Front Approval of
- Technical issues resolved the Common Plant
- Standardized operational programs (as appropriate)
- Generic environmental review (as appropriate)
- Hearing covering the common design
- Address administrative processes
- Confirmation of site suitability for design Nth-of-a-Kind
- Closure of ITAAC/license conditions Licensing
- Confirmatory site-specific inspection
- Hearings on site-specific issues
- Operating decision
3 The NRC staff is proactively enhancing clarity, reliability, and efficiency for licensing and regulation of micro-reactors
Clear Reliable Efficient Coherent, logical, and Prompt, fair, and Risk-informed and practical regulatory decisive regulation performance-based approaches that will that lends stability to regulation that delivers allow for safe and licensing and timely results and uses secure deployment deployment resources effectively
4 TRANSFORMATION Risk-informed licensing Consequence oriented approaches Regulatory Advanced Reactor Generic Environmental Modernization I mp a c t S tatement Fees, ARCOP, Policy Issues, Guidance (ARCAP)
Pre -application Staged licensing Core teams Licensing Efficiencies International engagement Direct communication (audits)
Focused ACRS interactions Streamlined documentation Optimized environmental reviews 5
ACTIONS
The NRC staff is taking actions to prioritize and address licensing and deployment considerations related to micro-reactors.
- SECY-24-0008: Micro -Reactor Licensing and Deployment Considerations: Fuel Loading and Operational Testing at a Factory (ML23207A252)
- Micro -reactors Licensing Strategies White Paper (ML21235A418)
- SECY-20-0093: Policy and Licensing Considerations Related to Micro -
Reactors ( ML20254A363)
6 ACTIONS SECY-24-0008
SECY 0008, Micro-Reactor Licensing and Deployment Considerations: Fuel Loading and Operational Testing at a Factory, seeks Commission policy direction on regulatory approaches related to three topics:
(1) Features to preclude criticality (2) Fuel loading at a factory (3) Operational testing at a factory
7 ACTIONS Catalyzing Micro-Reactors o Loading Fuel and Operational Testing o Transportation of fueled reactors o Standardization of operational programs (as appropriate) o Environmental review o Site characterization o Timeframe for authorization to operate at the deployment site o Physical and Cyber Security o Emergency Preparedness o Decommissioning process and decommissioning funding assurance o Staffing, training, qualification requirements o Commercial mobile micro-reactors o Licensing replacement reactors o Autonomous operation and remote operation o Storage of fuel after irradiation in a power reactor o Siting in densely populated areas o Aircraft impact assessment o Commercial maritime and space applications 8 WHATS NEXT?
Topics of interest:
- Maximal design s tandardization
- Standardization of operation programs (as appropriate)
- S ite characterization
- Streamlined licensing process and safety review
- Environmental review
- Construction inspection
Continued stakeholder engagement
9 Success Strategies
Optimizing Licensing Proactive Stakeholder Robust Preapplication Review s Engagement Activities