L-PI-16-098, Followup to Interim Report Submitted Under 10 CFR 21.21(a)(2) Regarding a Failed Bench Test of a Clark Relay Model 4U3-130: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 21: Line 21:


Xcel Energy RESPONSIBLE BY NATUR L-PI-16-098 10 CFR 21.21(a)(2)
Xcel Energy RESPONSIBLE BY NATUR L-PI-16-098 10 CFR 21.21(a)(2)
: 1. S. Northard, NSPM, letter to NRC Document Control Desk, "Interim Report of a Deviation or Failure to Comply," L-PI-16-089, 11/04/2016 (ADAMS Accession Number ML 16309A597)
: 1. S. Northard, NSPM, letter to NRC Document Control Desk, "Interim Report of a Deviation or Failure to Comply," L-PI-16-089, 11/04/2016 (ADAMS Accession Number ML16309A597)
Northern States Power Company, a Minnesota Corporation, (NSPM), doing business as Xcel Energy, hereby submits this followup report to the interim report (Reference
Northern States Power Company, a Minnesota Corporation, (NSPM), doing business as Xcel Energy, hereby submits this followup report to the interim report (Reference
: 1) submitted pursuant to 10 CFR 21.21(a)(2) regarding a failed bench test of a Clark Relay Modei4U3-130.
: 1) submitted pursuant to 10 CFR 21.21(a)(2) regarding a failed bench test of a Clark Relay Modei4U3-130.

Revision as of 20:55, 19 June 2019

Followup to Interim Report Submitted Under 10 CFR 21.21(a)(2) Regarding a Failed Bench Test of a Clark Relay Model 4U3-130
ML16336A842
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 12/01/2016
From: Northard S
Northern States Power Company, Minnesota, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-PI-16-098
Download: ML16336A842 (2)


Text

1717 Wakonade Drive Welch, MN 55089 800.895.4999 xcelenergy.com DEC 0 1 2016 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant, Unit 1 Docket No. 50-282 Renewed Facility Operating License No. DPR-42 Followup to Interim Report Submitted under 10 CFR 21.21(a)(2)

Reference:

Xcel Energy RESPONSIBLE BY NATUR L-PI-16-098 10 CFR 21.21(a)(2)

1. S. Northard, NSPM, letter to NRC Document Control Desk, "Interim Report of a Deviation or Failure to Comply," L-PI-16-089, 11/04/2016 (ADAMS Accession Number ML16309A597)

Northern States Power Company, a Minnesota Corporation, (NSPM), doing business as Xcel Energy, hereby submits this followup report to the interim report (Reference

1) submitted pursuant to 10 CFR 21.21(a)(2) regarding a failed bench test of a Clark Relay Modei4U3-130.

NSPM returned the relay to the vendor to evaluate.

The vendor's as-found inspection identified that the threads of the upper fixed contact mounting screw of the third pole were stripped out. The vendor's Commercial Grade Dedication (CGD) process includes checking for this stripped condition.

Therefore, the vendor concluded the relay was damaged at Prairie Island Nuclear Generating Plant. No nonconformance was identified, and the relay was not modified, or altered, or repaired.

As a result, this condition is not reportable under 10 CFR 21. If there is any question or if additional information is needed, please contact Frank Sienczak, at 651-267-1740.

Document Control Desk Page 2 Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.

Scott Northard Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company-Minnesota cc: Administrator, Region Ill, USNRC Project Manager, Prairie Island, USNRC Resident Inspector, Prairie Island, USNRC