Category:Letter
MONTHYEARCNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) CNL-24-031, Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-03-18018 March 2024 Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance CNL-24-028, Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 IR 05000390/20240102024-03-0808 March 2024 Age-Related Degradation Inspection Report 05000390/2024010 and 05000391/2024010 CNL-24-012, Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-02-28028 February 2024 Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance IR 05000390/20230062024-02-28028 February 2024 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - Report 05000390/2023006 and 05000391/2023006 CNL-24-023, Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 252024-02-20020 February 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 25 ML24009A1712024-02-16016 February 2024 Environmental Assessment and Finding of No Significant Impact Related to an Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods (EPID L-2023-LLA-0039) - Letter ML24019A0722024-02-14014 February 2024 Request for Withholding Information from Public Disclosure IR 05000390/20230042024-02-13013 February 2024 Integrated Inspection Report 05000390/2023004 and 05000391/2023004 and Apparent Violation 2024-09-05
[Table view] |
See also: IR 05000390/2013302
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257
June 6, 2013
Mr. Joseph W. Shea Vice President, Nuclear Licensing
Tennessee Valley Authority
1101 Market Street, LP 3D-C
Chattanooga, TN 37402-2801
SUBJECT: WATTS BAR NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION 05000390/2013302
Dear Mr. Shea:
In a telephone conversation on May 31, 2013, between Mr. K. Skubisz, Examination Project Manager, and Mr. M. Meeks, Senior Operations Engineer, arrangements were made for the
administration of licensing examinations at Watts Bar Nuclear Plant. The operating test is scheduled to be administered during the weeks of October 14 and October 21, 2013. The
written examination is scheduled to be administered the week of October 28, 2013. The on-site preparatory week is scheduled for the week of September 23, 2013.
As agreed during the telephone conversation, your staff will prepare both the operating test and
written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021,
"Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory
Commission (NRC) regional office will discuss
with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outline by July 31, 2013. Mr. Meeks provided the
written examination outline to your staff in June 2012. The operating test, written examination, and the supporting reference materials identified in Attachment 3 to ES-201 will be due by August 19, 2013. Pursuant to Title 10,
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outline, examination, and test before
they are submitted to the NRC for review and approval. All materials shall be complete and
ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
J. Shea 2
In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications, medical certifications, and waiver
requests (if any) at least 30 days before the first examination date. If the applications are not
received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the
Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget (OMB) under approval number 3150-0018, which expires on April 30, 2016. The public reporting burden for this collection of information is estimated to average 500
hours per response, including the time for reviewing instructions, gathering and maintaining the
data needed, writing the examinations, and completing and reviewing the collection of
information. Send comments on any aspect of this collection of information, including
suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,
Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component
of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).
J. Shea 3
Thank you for your cooperation in this matter. Mr. Skubisz has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Meeks at (404) 997-4467, (Internet E-mail: Michael.Meeks@nrc.gov), or me at (404) 997-4550, (Internet E-mail:
Malcolm.Widmann@nrc.gov
). Sincerely, /RA/ Malcolm T. Widmann, Chief
Operations Branch 1
Division of Reactor Safety
Docket No.: 50-390
License No.: NPF-90
cc: (See page 4)
_________________________ x SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE RA RA NAME MEEKS WIDMANN DATE 6/6/2013 6/6/2013 6/ /2013 6/ /2013 6/ /2013 6/ /2013 6/ /2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
J. Shea 4
cc: Mr. T. P. Cleary
Site Vice President Watts Bar Nuclear Plant Tennessee Valley Authority
Electronic Mail Distribution
David H. Gronek
Plant Manager Watts Bar Nuclear Plant Tennessee Valley Authority
Electronic Mail Distribution
Donna K. Guinn Manager, Site Licensing Watts Bar Nuclear Plant
Tennessee Valley Authority
Electronic Mail Distribution
Mr. E. D. Schrull Manager, Corporate Licensing
Watts Bar Nuclear Plant
Tennessee Valley Authority
1101 Market Street, LP 4B-C
Chattanooga, TN 37402-2801
Edward J. Vigluicci
Associate General Counsel, Nuclear
Tennessee Valley Authority
Electronic Mail Distribution
Gordon P. Arent
Senior Manager, Licensing WBN Unit 2
Watts Bar Nuclear Plant
Tennessee Valley Authority
Electronic Mail Distribution
County Mayor
Watts Bar Unit 1
P.O. Box 156
Decatur, TN 37322
County Executive
Watts Bar Unit 1
375 Church Street
Suite 215
Dayton, TN 37321
Tennessee Department of Environment &
Conservation
Division of Radiological Health
401 Church Street
Nashville, TN 37243
Senior Resident Inspector
U.S. Nuclear Regulatory Commission
Watts Bar Nuclear Plant 1260 Nuclear Plant Road
Spring City, TN 37381-2000
Ann Harris
341 Swing Loop
Rockwood, TN 37854
Tennessee Valley Authority
ATTN: Ms. Betsy Eiford-Lee
Training Manager Watts Bar Nuclear Plant P. O. Box 2000
Spring City, TN 37381
Letter to Joseph W. Shea from Malcolm T. Widmann dated June 6, 2013
SUBJECT: WATTS BAR NUCLEAR PLANT - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000390/2013302
DISTRIBUTION
- RIDSNRRDIRS
PUBLIC RidsNrrPMWattsBar1 Resource
RidsNrrPMWattsBar2 Resource