05000382/FIN-2008004-02: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| CCA = P.2
| CCA = P.2
| INPO aspect = PI.2
| INPO aspect = PI.2
| description = The inspectors identified a noncited violation of 10 CFR 50, Appendix B, Criterion III (Design Control) for an inadequate "pressure locking" design calculation for shutdown cooling Valves SI-405A and SI-405B. Plant engineers also used the calculation to support valve operability following a valve malfunction, which appeared to be caused by pressure locking. Entergy engineers had derived valve bonnet leakage rates (for pressure locking conditions) from local leak rate testing results. However, a national laboratory had already proven the Entergy theory invalid and plant engineers had taken no steps to validate the theory themselves. Finally, in response to an NRC generic letter concerning pressure locking and thermal binding of valves, the licensee engineers' conclusions were based on incorrect facts and improper assumptions. Licensee personnel entered the noncited violation into the corrective action program as Condition Report CR-WF3-2008-4292. The failures to perform: (1) an adequate engineering calculation and (2) a valid operability determination were performance deficiencies. This finding was more than minor because it was similar to nonminor finding Example 3.j in NRC Inspection Manual Chapter 0612 Appendix E, Examples of Minor Issues, in that, there was a reasonable doubt concerning the operability of Valves SI- 405A/B. The inspectors utilized NRC Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process, to characterize the significance of the issue. Using the worst case scenario of having both SI-405A/B valves inoperable, the finding was of very low safety significance because multiple systems or components would still be available to remove decay heat and respond to a loss of inventory event. These systems included the emergency feedwater system, main feedwater system, auxiliary feed water system, atmospheric dump valves, charging pumps, safety injection tanks, and the high pressure safety injection system. This performance deficiency would not result in any loss of instrumentation needed for safe shutdown and cool down of the plant. The finding had a crosscutting aspect in the area of problem identification and resolution [P.1(c)] because engineers failed to thoroughly evaluate the potential for valve pressure locking. The calculation was completed in 2008 and was indicative of current performance
| description = The inspectors identified a noncited violation of 10 CFR 50, Appendix B, Criterion III (Design Control) for an inadequate \"pressure locking\" design calculation for shutdown cooling Valves SI-405A and SI-405B. Plant engineers also used the calculation to support valve operability following a valve malfunction, which appeared to be caused by pressure locking. Entergy engineers had derived valve bonnet leakage rates (for pressure locking conditions) from local leak rate testing results. However, a national laboratory had already proven the Entergy theory invalid and plant engineers had taken no steps to validate the theory themselves. Finally, in response to an NRC generic letter concerning pressure locking and thermal binding of valves, the licensee engineers\' conclusions were based on incorrect facts and improper assumptions. Licensee personnel entered the noncited violation into the corrective action program as Condition Report CR-WF3-2008-4292. The failures to perform: (1) an adequate engineering calculation and (2) a valid operability determination were performance deficiencies. This finding was more than minor because it was similar to nonminor finding Example 3.j in NRC Inspection Manual Chapter 0612 Appendix E, Examples of Minor Issues, in that, there was a reasonable doubt concerning the operability of Valves SI- 405A/B. The inspectors utilized NRC Manual Chapter 0609, Appendix G, Shutdown Operations Significance Determination Process, to characterize the significance of the issue. Using the worst case scenario of having both SI-405A/B valves inoperable, the finding was of very low safety significance because multiple systems or components would still be available to remove decay heat and respond to a loss of inventory event. These systems included the emergency feedwater system, main feedwater system, auxiliary feed water system, atmospheric dump valves, charging pumps, safety injection tanks, and the high pressure safety injection system. This performance deficiency would not result in any loss of instrumentation needed for safe shutdown and cool down of the plant. The finding had a crosscutting aspect in the area of problem identification and resolution [P.1(c)] because engineers failed to thoroughly evaluate the potential for valve pressure locking. The calculation was completed in 2008 and was indicative of current performance


}}
}}

Latest revision as of 20:35, 20 February 2018

02
Site: Waterford Entergy icon.png
Report IR 05000382/2008004 Section 1R15
Date counted Sep 30, 2008 (2008Q3)
Type: NCV: Green
cornerstone Mitigating Systems
Identified by: NRC identified
Inspection Procedure: IP 71111.15
Inspectors (proximate) B Henderson
S Graves
G Replogle
R Smith
W Sifre
C Paulk
R Azua
D Overland
S Makor
CCA P.2, Evaluation
INPO aspect PI.2
'