ML111030188: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
#REDIRECT [[RS-11-062, Report No. 901348-04, Exelon Relief Request 13R-19, Penetration 64, Page 3 of 4]]
{{Adams
| number = ML111030188
| issue date = 04/08/2011
| title = Enclosure 3 - Dose Estimates
| author name =
| author affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee name =
| addressee affiliation = NRC/NRR
| docket = 05000454
| license number = NPF-037
| contact person =
| case reference number = RS-11-062
| package number = ML111010578
| document type = - No Document Type Applies
| page count = 4
}}
 
=Text=
{{#Wiki_filter:ATTACHMENT 3 DOSE ESTIMATES
 
Dose Pen Ind Character/Loc.           Repair steps        Time        Repair Comments mRem 64  1                Mark indication                6  420 12:00 J-Weld Light Grinding                20  1400  Light Grind to reduce to 3/32" x 1/4" Welding Supv Perform Visual    2  140        acceptable Linear Weld over if depth required Rejectable  Remark Penetration and Clean    3  210 Enter/Exit All Jumps          94  6819 QC inspection @ 5X PT of area  20  1400 64  2                Mark indication                0    0 12:00 J-Weld 1/16" x 1/16" Light Grinding                  0    0  Repaired incidently with #1 Rounded    Welding Supv Perform Visual    2  140 Acceptable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 64  3                Mark indication                0    0 11:00                                              Light Grind to reduce to 1/16" x 1/2" Light Grinding                15  1050        acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 64  4                Mark indication                0    0 3:00                                              Light Grind to reduce to 1/4" x 1/4"  Light Grinding                22  1540        acceptable Rounded    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 64  5                Mark indication                0    0 3:00 Light Grinding                  0    0      Possibly will be 1/8" x 1/8" Repaired incidently with #1 Rounded    Welding Supv Perform Visual    0    0 Acceptable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 64  6                Mark indication                10  700 2:00                                              Light Grind to reduce to 1/8" x 1/2"  Light Grinding                15  1050        acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70
 
Dose Pen Ind Character/Loc.          Repair steps        Time        Repair Comments mRem 64  7                Mark indication                0    0 2:00 Light Grinding                15  1050  Light Grind to reduce to 0
acceptable Rounded    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1    70 64  8                Mark indication                0    0 5:00 Light Grinding                15  1050  Light Grind to reduce to 1/16" x 3/16" acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 64 9                Mark indication                0    0 6:00 Light Grinding                10  700  Light Grind to reduce to 1/16" x 3/16" acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 31  1                Mark indication                6  420 11:00 Light Grinding                15  1050  Light Grind to reduce to 1/8" x 3/8" acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area 15.5 1085 31  2                Mark indication                0    0 1:00 Light Grinding                15  1050  Light Grind to reduce to 1/16" x 1" acceptable Linear    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3  210 QC inspection @ 5X PT of area  1  70 31  3                Mark indication                0    0 1:00 Light Grinding                15  1050  Light Grind to reduce to 1/4" x 1/4" acceptable Rounded    Welding Supv Perform Visual    2  140 Weld over if depth required Rejectable Remark Penetration and Clean    3   210 QC inspection @ 5X PT of area  1    70
 
Dose Pen    Ind  Character/Loc.              Repair steps          Time                Repair Comments mRem 31    4                       Mark indication                    0        0 8:00 Light Grinding                    22      1540  Local Excavate to reduce to 1/2" x 5/8" acceptable Rounded        Welding Supv Perform Visual        2      140  Weld over if depth required Rejectable Remark Penetration and Clean      3      210 QC inspection @ 5X PT of area      1      70 Total                          REM      28..554 Assumptions:
Only covers penetration 64 and 31 Both options include grinding on 64-4 and 31-4 (pen-Indication)
Both options include weld repair (overlay) on all indications in 64 and 31 No extra time for chasing indications after grinding Actuals for dose used:
Dose at head 70 mrem/min Dose in and out 36 mrem/min Dose on turnovers .1 mrem/min
 
==
Conclusions:==
 
Relief request will yield a 7 REM savings for pen 64 and 31 MINIMUM Additional saving should be less for the remaining penetrations since we expect less indication repair.
Overall savings of approx 35% in dose.}}

Latest revision as of 01:00, 13 November 2019

Enclosure 3 - Dose Estimates
ML111030188
Person / Time
Site: Byron Constellation icon.png
Issue date: 04/08/2011
From:
Exelon Generation Co, Exelon Nuclear
To:
Office of Nuclear Reactor Regulation
Shared Package
ML111010578 List:
References
RS-11-062
Download: ML111030188 (4)


Text

ATTACHMENT 3 DOSE ESTIMATES

Dose Pen Ind Character/Loc. Repair steps Time Repair Comments mRem 64 1 Mark indication 6 420 12:00 J-Weld Light Grinding 20 1400 Light Grind to reduce to 3/32" x 1/4" Welding Supv Perform Visual 2 140 acceptable Linear Weld over if depth required Rejectable Remark Penetration and Clean 3 210 Enter/Exit All Jumps 94 6819 QC inspection @ 5X PT of area 20 1400 64 2 Mark indication 0 0 12:00 J-Weld 1/16" x 1/16" Light Grinding 0 0 Repaired incidently with #1 Rounded Welding Supv Perform Visual 2 140 Acceptable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 3 Mark indication 0 0 11:00 Light Grind to reduce to 1/16" x 1/2" Light Grinding 15 1050 acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 4 Mark indication 0 0 3:00 Light Grind to reduce to 1/4" x 1/4" Light Grinding 22 1540 acceptable Rounded Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 5 Mark indication 0 0 3:00 Light Grinding 0 0 Possibly will be 1/8" x 1/8" Repaired incidently with #1 Rounded Welding Supv Perform Visual 0 0 Acceptable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 6 Mark indication 10 700 2:00 Light Grind to reduce to 1/8" x 1/2" Light Grinding 15 1050 acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70

Dose Pen Ind Character/Loc. Repair steps Time Repair Comments mRem 64 7 Mark indication 0 0 2:00 Light Grinding 15 1050 Light Grind to reduce to 0

acceptable Rounded Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 8 Mark indication 0 0 5:00 Light Grinding 15 1050 Light Grind to reduce to 1/16" x 3/16" acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 64 9 Mark indication 0 0 6:00 Light Grinding 10 700 Light Grind to reduce to 1/16" x 3/16" acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 31 1 Mark indication 6 420 11:00 Light Grinding 15 1050 Light Grind to reduce to 1/8" x 3/8" acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 15.5 1085 31 2 Mark indication 0 0 1:00 Light Grinding 15 1050 Light Grind to reduce to 1/16" x 1" acceptable Linear Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 31 3 Mark indication 0 0 1:00 Light Grinding 15 1050 Light Grind to reduce to 1/4" x 1/4" acceptable Rounded Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70

Dose Pen Ind Character/Loc. Repair steps Time Repair Comments mRem 31 4 Mark indication 0 0 8:00 Light Grinding 22 1540 Local Excavate to reduce to 1/2" x 5/8" acceptable Rounded Welding Supv Perform Visual 2 140 Weld over if depth required Rejectable Remark Penetration and Clean 3 210 QC inspection @ 5X PT of area 1 70 Total REM 28..554 Assumptions:

Only covers penetration 64 and 31 Both options include grinding on 64-4 and 31-4 (pen-Indication)

Both options include weld repair (overlay) on all indications in 64 and 31 No extra time for chasing indications after grinding Actuals for dose used:

Dose at head 70 mrem/min Dose in and out 36 mrem/min Dose on turnovers .1 mrem/min

==

Conclusions:==

Relief request will yield a 7 REM savings for pen 64 and 31 MINIMUM Additional saving should be less for the remaining penetrations since we expect less indication repair.

Overall savings of approx 35% in dose.