| number = ML13064A430
| number = ML13064A430
| issue date = 03/12/2013
| issue date = 03/12/2013
| title = Correction FRN, Correct Date of Safety Evaluation in One Column; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License (TAC Nos. ME9767 and ME9768)
| title = Correction FRN, Correct Date of Safety Evaluation in One Column; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License
| author name = Bladey C
| author name = Bladey C
| author affiliation = NRC/ADM/DAS
| author affiliation = NRC/ADM/DAS
Line 9: Line 9:
| docket = 05000445, 05000446
| docket = 05000445, 05000446
| license number = NPF-087, NPF-089
| license number = NPF-087, NPF-089
| contact person = Singal B K
| contact person = Singal B
| case reference number = TAC ME9767, TAC ME9768
| case reference number = TAC ME9767, TAC ME9768
| document type = Federal Register Notice
| document type = Federal Register Notice
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:[7590-01-P]
{{#Wiki_filter:[7590-01-P]
NUCLEAR REGULATORY COMMISSION  
NUCLEAR REGULATORY COMMISSION
 
[NRC-2012-0310; Docket Nos.: 50-445 and 50-446; License Nos.: NPF-87 and NPF-89]
[NRC-2012-0310; Docket Nos.: 50-445 and 50-446; License Nos.: NPF-87 and NPF-89]
In the Matter of Luminant Generation Company LLC, Comanche Peak Nuclear Power Plant, Units 1 and 2; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License; Correction AGENCY: Nuclear Regulatory Commission.
In the Matter of Luminant Generation Company LLC, Comanche Peak Nuclear Power Plant, Units 1 and 2; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License; Correction AGENCY: Nuclear Regulatory Commission.
ACTION: Notice; correction.  
ACTION: Notice; correction.


==SUMMARY==
==SUMMARY==
: The U.S. Nuclear Regulatory Commission is correcting a notice that was published in the Federal Register (FR) on March 5, 2013 (78 FR 14361), regarding the order approving the proposed internal restructuring and indirect transfer of license. This action is necessary to correct the date of a safety evaluation that was incorrectly referenced in Section II of this notice. The safety evaluation date was corrected by letter dated February 25, 2013, which is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML13056A266.
: The U.S. Nuclear Regulatory Commission is correcting a notice that was published in the Federal Register (FR) on March 5, 2013 (78 FR 14361), regarding the order approving the proposed internal restructuring and indirect transfer of license. This action is necessary to correct the date of a safety evaluation that was incorrectly referenced in Section II of this notice. The safety evaluation date was corrected by letter dated February 25, 2013, which is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML13056A266.
FOR FURTHER INFORMATION CONTACT: Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Office of Administration, Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone 301-492-3667; e-mail: Cindy.Bladey@nrc.gov.
FOR FURTHER INFORMATION CONTACT: Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Office of Administration, Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone 301-492-3667; e-mail: Cindy.Bladey@nrc.gov.
 
Correction In the FR of March 5, 2013, in FR Doc. 2013-05021, on page 14362, second column, first complete paragraph, correct the last sentence to read:
Correction In the FR of March 5, 2013, in FR Doc. 2013-05021, on page 14362, second column, first complete paragraph, correct the last sentence to read:
The findings set forth above are supported by a safety evaluation dated February 22, 2013.
The findings set forth above are supported by a safety evaluation dated February 22, 2013.
Dated in Rockville, Maryland, this 12 th day of March 2013.
Dated in Rockville, Maryland, this 12th day of March 2013.
For the Nuclear Regulatory Commission. /RA/
For the Nuclear Regulatory Commission.
Cindy Bladey, Chief, Rules, Announcements, and Directives Branch,
                                              /RA/
 
Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Division of Administrative Services, Office of Administration.}}
Division of Administrative Services, Office of Administration.}}

Latest revision as of 08:24, 20 March 2020

Correction FRN, Correct Date of Safety Evaluation in One Column; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License
ML13064A430
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/12/2013
From: Cindy Bladey
Division of Administrative Services
To:
Singal B
References
TAC ME9767, TAC ME9768
Download: ML13064A430 (2)


Text

[7590-01-P]

NUCLEAR REGULATORY COMMISSION

[NRC-2012-0310; Docket Nos.: 50-445 and 50-446; License Nos.: NPF-87 and NPF-89]

In the Matter of Luminant Generation Company LLC, Comanche Peak Nuclear Power Plant, Units 1 and 2; Order Approving the Proposed Internal Restructuring and Indirect Transfer of License; Correction AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; correction.

SUMMARY

The U.S. Nuclear Regulatory Commission is correcting a notice that was published in the Federal Register (FR) on March 5, 2013 (78 FR 14361), regarding the order approving the proposed internal restructuring and indirect transfer of license. This action is necessary to correct the date of a safety evaluation that was incorrectly referenced in Section II of this notice. The safety evaluation date was corrected by letter dated February 25, 2013, which is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML13056A266.

FOR FURTHER INFORMATION CONTACT: Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Office of Administration, Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone 301-492-3667; e-mail: Cindy.Bladey@nrc.gov.

Correction In the FR of March 5, 2013, in FR Doc. 2013-05021, on page 14362, second column, first complete paragraph, correct the last sentence to read:

The findings set forth above are supported by a safety evaluation dated February 22, 2013.

Dated in Rockville, Maryland, this 12th day of March 2013.

For the Nuclear Regulatory Commission.

/RA/

Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Division of Administrative Services, Office of Administration.