{{#Wiki_filter:ES-201 Examination Preparation Checklist Form ES-201-1  Facility:
Clinton Power Station Date of Examination:
Week of 8/22/20 1 1 Developed by:  Written
- Facility    NRC    //  Operating
- Facility    NRC    Target Date*  Task Description (Reference)
Chief Examiner's Initials -180 1. Examination administration date confirmed (C.1.a; C.2.a and b) meb -120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) meb -120 3. Facility contact briefed on security and other requirements (C.2.c) meb -120 4. Corporate notification letter sent (C.2.d) meb [-90] [5. Reference material due (C.1.e; C.3.c; Attachment 3)]
NA {-75} 6. Integrated examination outline(s) due, including Forms ES
-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) meb {-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}
meb {-45} 8. Proposed examinations (including written, walk
-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) meb -30 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) meb -14 10. Final license applications due and Form ES
-201-4 prepared (C.1.l; C.2.i; ES-202) meb -14 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) meb -14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) meb -7 13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) meb -7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES
-202, C.2.e; ES-204) meb -7 15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) meb -7 16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) meb
* Target dates are generally based on facility
-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case
-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.}}

Revision as of 21:58, 1 August 2018

2011 Clinton Power Station Examination Preparation Checklist ES-201-1
ML12271A326
Person / Time
Site: Clinton Constellation icon.png
Issue date: 09/14/2011
From:
Operations Branch III
To:
Exelon Generation Co, Exelon Nuclear
References
ES-201-1, 50-461/11-301
Download: ML12271A326 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility:

Clinton Power Station Date of Examination:

Week of 8/22/20 1 1 Developed by: Written

- Facility NRC // Operating

- Facility NRC Target Date* Task Description (Reference)

Chief Examiner's Initials -180 1. Examination administration date confirmed (C.1.a; C.2.a and b) meb -120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) meb -120 3. Facility contact briefed on security and other requirements (C.2.c) meb -120 4. Corporate notification letter sent (C.2.d) meb [-90] [5. Reference material due (C.1.e; C.3.c; Attachment 3)]

NA {-75} 6. Integrated examination outline(s) due, including Forms ES

-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) meb {-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}

meb {-45} 8. Proposed examinations (including written, walk

-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) meb -30 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) meb -14 10. Final license applications due and Form ES

-201-4 prepared (C.1.l; C.2.i; ES-202) meb -14 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) meb -14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) meb -7 13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) meb -7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 5; ES

-202, C.2.e; ES-204) meb -7 15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) meb -7 16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) meb

  • Target dates are generally based on facility

-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case

-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.