ML110630123: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML110630123
| number = ML110630123
| issue date = 03/04/2011
| issue date = 03/04/2011
| title = Waterford Steam Electric Station, Unit 3 - Notification of Inspection (NRC Inspection Report 05000382-11-003) and Request for Information
| title = Notification of Inspection (NRC Inspection Report 05000382-11-003) and Request for Information
| author name = Werner G E
| author name = Werner G
| author affiliation = NRC/RGN-IV/DRS/PSB-2
| author affiliation = NRC/RGN-IV/DRS/PSB-2
| addressee name = Kowalewski J
| addressee name = Kowalewski J
Line 18: Line 18:
=Text=
=Text=
{{#Wiki_filter:March 4, 2011  
{{#Wiki_filter:March 4, 2011  
 
Joseph Kowalewski   Vice President, Operations Entergy Operations, Inc. Waterford Steam Electric Station, Unit 3 17265 River Road  
Joseph Kowalewski
  Vice President, Operations  
Entergy Operations, Inc.  
Waterford Steam Electric Station, Unit 3  
17265 River Road  
Killona, LA  70057-3093  
Killona, LA  70057-3093  
  SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000382/2011003) AND  
SUBJECT:  
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF  
INSPECTION (NRC INSPECTION REPORT 05000382/2011003) AND  
REQUEST FOR INFORMATION  
REQUEST FOR INFORMATION  
  Dear Mr. Kowalewski:
   
   
From April 11-15 and 25-29, 2011, reactor inspectors from the Nuclear Regulatory Commission's (NRC) Region IV office will perform the baseline inservice inspection at Waterford, using NRC Inspection Procedure 71111.08, "Inservice Inspection Activities," and TI 2515/172, "Reactor Coolant System Dissimilar Metal Butt Welds." Experience has shown that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.  In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.  These documents have  
been divided into two groups.  The first group (Section A of the enclosure), due by March 28, 2011, identifies information to be provided prior to the inspection to ensure that the inspectors are adequately prepared.  The second group (Section B of the enclosure) identifies the information the inspectors will need upon arrival at the site.  It is important that all of these documents are up to date and complete in order to minimize the number of additional  
Dear Mr. Kowalewski:
From April 11-15 and 25-29, 2011, reactor inspectors from the Nuclear Regulatory  
Commissions (NRC) Region IV office will perform the baseline inservice inspection at  
Waterford, using NRC Inspection Procedure 71111.08, Inservice Inspection Activities, and  
TI 2515/172, Reactor Coolant System Dissimilar Metal Butt Welds.  Experience has shown  
that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.   
In order to minimize the impact to your onsite resources and to ensure a productive inspection,  
we have enclosed a request for documents needed for this inspection.  These documents have  
been divided into two groups.  The first group (Section A of the enclosure), due by March 28,  
2011, identifies information to be provided prior to the inspection to ensure that the inspectors  
are adequately prepared.  The second group (Section B of the enclosure) identifies the  
information the inspectors will need upon arrival at the site.  It is important that all of these  
documents are up to date and complete in order to minimize the number of additional  
documents requested during the preparation and/or the onsite portions of the inspection.  
documents requested during the preparation and/or the onsite portions of the inspection.  
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Mr. Jim Pollock of your licensing organization.  Our inspection dates are subject to change based on your updated schedule of
outage activities.  If there are any questions about this inspection or the material requested, please contact the lead inspector Shiattin Makor (817) 276-6507 (shiattin.makor@nrc.gov) or Megan Williams at (817) 860-8076 (megan.williams@nrc.gov). UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125
Entergy Operations, Inc. - 2 -
  This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. 
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
  Sincerely,
  /RA/ James F. Drake for
  Gregory E. Werner, Chief  Plant Support Branch 2
Division of Reactor Safety
Docket No:  50-382 License No.  NPF-38
   
   
Enclosure: Inservice Inspection Document Request  
We have discussed the schedule for these inspection activities with your staff and understand
  Enclosure:  Inservice Inspection Document  
that our regulatory contact for this inspection will be Mr. Jim Pollock of your licensing
organization.  Our inspection dates are subject to change based on your updated schedule of
outage activities.  If there are any questions about this inspection or the material requested,
please contact the lead inspector Shiattin Makor (817) 276-6507 (shiattin.makor@nrc.gov) or
Megan Williams at (817) 860-8076 (megan.williams@nrc.gov).
UNITED STATES
NUCLEAR REGULATORY COMMISSION
R E GI ON  I V
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125
 
Entergy Operations, Inc.
- 2 -
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection
requirements were approved by the Office of Management and Budget, Control
Number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document
system (ADAMS).  ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ James F. Drake for
Gregory E. Werner, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket No:  50-382
License No.  NPF-38
Enclosure:  
Inservice Inspection Document Request  
   
Enclosure:   
Inservice Inspection Document  
   Request  
   Request  
cc w/enclosure: John T. Herron  Entergy Services, Inc.
President and CEO  Nuclear Operations/CNO P.O. Box 31995 Jackson, MS  39286-1995
Jeff Forbes Senior Vice President and 
  Chief Operating Officer Entergy Operations, Inc. P. O. Box 31995 Jackson, MS  39286-1995 
Entergy Operations, Inc. - 3 -
  Thomas Palmisano Vice President, Oversight Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS  39286-1995
Senior Manager, Nuclear Safety  and Licensing
Entergy Services, Inc. P. O. Box 31995 Jackson, MS  39286-1995
Kenny J. Christian, Director Nuclear Safety Assurance Entergy Operations, Inc.
17265 River Road Killona, LA 70057-0751
Joseph A. Aluise Associate General Council - Nuclear
Entergy Services, Inc. 639 Loyola Avenue New Orleans, LA  70113
Steven Adams, Acting Director
Nuclear Safety Assurance Entergy Operations, Inc. 17265 River Road Killona, LA  70057-0751
   
   
Charles F. Arnone General Manager, Plant Operations Waterford 3 SES Entergy Operations, Inc. 17265 River Road  
cc w/enclosure:
John T. Herron 
Entergy Services, Inc.
President and CEO 
Nuclear Operations/CNO
P.O. Box 31995
Jackson, MS  39286-1995
Jeff Forbes
Senior Vice President and 
  Chief Operating Officer
Entergy Operations, Inc.
P. O. Box 31995
Jackson, MS  39286-1995
 
Entergy Operations, Inc.
- 3 -
Thomas Palmisano
Vice President, Oversight
Entergy Operations, Inc.
P. O. Box 31995
Jackson, MS  39286-1995
Senior Manager, Nuclear Safety
and Licensing
Entergy Services, Inc.
P. O. Box 31995
Jackson, MS  39286-1995
Kenny J. Christian, Director
Nuclear Safety Assurance
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057-0751
Joseph A. Aluise
Associate General Council - Nuclear
Entergy Services, Inc.
639 Loyola Avenue
New Orleans, LA  70113
Steven Adams, Acting Director
Nuclear Safety Assurance
Entergy Operations, Inc.
17265 River Road
Killona, LA  70057-0751
Charles F. Arnone  
General Manager, Plant Operations  
Waterford 3 SES  
Entergy Operations, Inc.  
17265 River Road  
Killona, LA  70057-0751  
Killona, LA  70057-0751  
Manager, Licensing Entergy Operations, Inc. 17265 River Road Killona, LA  70057-0751
   
   
Chairman Louisiana Public Service Commission P. O. Box 91154 Baton Rouge, LA  70821-9154
Manager, Licensing
Entergy Operations, Inc. - 4 -  
Entergy Operations, Inc.
  Parish President Council St. Charles Parish P. O. Box 302  
17265 River Road
Killona, LA  70057-0751
Chairman  
Louisiana Public Service Commission  
P. O. Box 91154  
Baton Rouge, LA  70821-9154  
 
Entergy Operations, Inc.  
- 4 -  
Parish President Council  
St. Charles Parish  
P. O. Box 302  
Hahnville, LA  70057  
Hahnville, LA  70057  
  Billy Steelman, Manager  Licensing and Regulatory Affairs Entergy Operations, Inc.  
   
17265 River Road Killona, LA  70057-0751  
Billy Steelman, Manager   
  St. Charles Parish Dept. of Emergency Preparedness Emergency Operations Center P.O. Box 302  
Licensing and Regulatory Affairs  
Entergy Operations, Inc.  
17265 River Road  
Killona, LA  70057-0751  
   
St. Charles Parish  
Dept. of Emergency Preparedness  
Emergency Operations Center  
P.O. Box 302  
Hahnville, LA  70057  
Hahnville, LA  70057  
  Director, Nuclear Safety & Licensing Entergy, Operations, Inc. 440 Hamilton Avenue  
   
Director, Nuclear Safety & Licensing  
Entergy, Operations, Inc.  
440 Hamilton Avenue  
White Plains, NY 10601  
White Plains, NY 10601  
Louisiana Department of Environmental Quality  Radiological Emergency Planning    and Response Division
P. O. Box 4312 Baton Rouge, LA 70821-4312
Chief, Technological Hazards    Branch
FEMA Region VI 800 North Loop 288 Federal Regional Center Denton, TX  76209
   
   
Kenny J. Christian, Director Nuclear Safety Assurance Entergy Operations, Inc. 17265 River Road Killona, LA 70057-0751
Louisiana Department of Environmental Quality  
Entergy Operations, Inc. - 5 -
Radiological Emergency Planning
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) DRP Director (Kriss.Kennedy@nrc.gov)
  and Response Division
DRP Deputy Director (Troy.Pruett@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) DRS Deputy Director (Vacant) Senior Resident Inspector (Marlone.Davis@nrc.gov) Resident Inspector (Dean.Overland@nrc.gov)
P. O. Box 4312
Branch Chief, DRP/E (Jeff.Clark@nrc.gov) Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) Project Engineer (Jim.Melfi@nrc.gov) Project Engineer (William.Schaup@nrc.gov) WAT Administrative Assistant (Linda.Dufrene@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov)
Baton Rouge, LA 70821-4312
Project Manager (Kaly.Kalyanam@nrc.gov) Branch Chief, DRS/TSB (Michael.Hay@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource OEDO RIV Coordinator (James.Trapp@nrc.gov) DRS/TSB STA (Dale.Powers@nrc.gov)
 
   
   
SUNSI Review Completed:  ___Y___ ADAMS:  Yes  No        Initials: _JFD
_    Publicly Available        Non-Publicly Available        Sensitive    Non-Sensitive
ML EB1 C:PSB2    SMakor GWerner    /RA/  Telecon /RA/ JFDrake for    3/3/11 3/3/11    OFFICIAL RECORD COPY  T=Telephone          E=E-mail        F=Fax
   
   
 
Chief, Technological Hazards 
   - 1 - Enclosure INSERVICE INSPECTION DOCUMENT REQUEST
   Branch
  Inspection Dates: April 11-15 and 25-29, 2011
FEMA Region VI
800 North Loop 288
Federal Regional Center
Denton, TX  76209
   
   
Inspection Procedures: IP 71111.08 "Inservice Inspection (ISI) Activities" TI 2515/172 "Reactor Coolant System Dissimilar Metal Butt Welds"
Kenny J. Christian, Director
  Inspectors: Shiattin Makor, Reactor Inspector (Lead Inspector - ISI) Megan Williams, Reactor Inspector  
Nuclear Safety Assurance
  A. Information Requested for the In-Office Preparation Week
Entergy Operations, Inc.
  The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com preferred), in care of Shiattin Makor, by March 28, 2011, to facilitate the selection of specific items that will be reviewed during the onsite inspection week.  The inspectors will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week (Section B of this enclosure).  We ask that the specific items selected from the lists be available and ready for review on the first day of inspection.  Please provide requested documentation electronically if possible.  If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection.  If you have any questions regarding this information request, please call the inspector as soon as possible.  
17265 River Road
  A.1 ISI/Welding Programs and Schedule Information
Killona, LA  70057-0751
  a) A detailed schedule (including preliminary dates) of:  
 
  i)  Nondestructive examinations planned for Class 1 & 2 systems and containment, performed as part of your ASME Section XI, risk informed (if  
Entergy Operations, Inc.
applicable), and augmented inservice inspection programs during the upcoming outage  
- 5 -
  Provide a status summary of the nondestructive examination inspection activities vs. the required inspection period percentages for this interval  
by category per ASME Section XI, IWX-2400.  Do not provide separately if other documentation requested contains this information
Electronic distribution by RIV:
  ii)  Reactor pressure vessel head examinations planned for the upcoming outage  iii) Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope (If applicable)  
Regional Administrator (Elmo.Collins@nrc.gov)
  iv) Examinations planned as part of your boric acid corrosion control program (Mode 3 walkdowns, bolted connection walkdowns, etc.)   
Deputy Regional Administrator (Art.Howell@nrc.gov)
  - 2 - Enclosure  
DRP Director (Kriss.Kennedy@nrc.gov)
  v) Welding activities that are scheduled to be completed during the upcoming outage (ASME Class 1, 2, or 3 structures, systems, or components)  
DRP Deputy Director (Troy.Pruett@nrc.gov)
  b) A copy of ASME Section XI Code Relief Requests and associated NRC safety evaluations applicable to the examinations identified above.   
DRS Director (Anton.Vegel@nrc.gov)
  c) A list of nondestructive examination reports (ultrasonic, radiography, magnetic particle, dye penetrant, Visual VT-1, VT-2, and VT-3), which have identified  
DRS Deputy Director (Vacant)
relevant conditions on Code Class 1 & 2 systems since the beginning of the last refueling outage.  This should include the previous Section XI pressure test(s) conducted during start up and any evaluations associated with the results of the pressure tests.  Also, include in the list the nondestructive examination reports with relevant conditions in the reactor pressure vessel head penetration nozzles that have been accepted for continued service.  The list of nondestructive examination reports should include a brief description of the structures, systems,  
Senior Resident Inspector (Marlone.Davis@nrc.gov)
Resident Inspector (Dean.Overland@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)
Project Engineer (Jim.Melfi@nrc.gov)
Project Engineer (William.Schaup@nrc.gov)
WAT Administrative Assistant (Linda.Dufrene@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Kaly.Kalyanam@nrc.gov)
Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource
OEDO RIV Coordinator (James.Trapp@nrc.gov)
DRS/TSB STA (Dale.Powers@nrc.gov)
SUNSI Review Completed:  ___Y___
ADAMS:  7 Yes
  No        Initials: _JFD_ 
7  Publicly Available        Non-Publicly Available        Sensitive
7  Non-Sensitive
ML
EB1
C:PSB2
SMakor
GWerner 
/RA/  Telecon
/RA/ JFDrake for
3/3/11
3/3/11
OFFICIAL RECORD COPY  T=Telephone          E=E-mail        F=Fax
 
- 1 -
Enclosure
INSERVICE INSPECTION DOCUMENT REQUEST
Inspection Dates:
April 11-15 and 25-29, 2011
Inspection Procedures:  
IP 71111.08 Inservice Inspection (ISI) Activities  
TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds  
   
Inspectors:  
Shiattin Makor, Reactor Inspector (Lead Inspector - ISI)  
Megan Williams, Reactor Inspector  
   
A.  
Information Requested for the In-Office Preparation Week  
The following information should be sent to the Region IV office in hard copy or  
electronic format (ims.certrec.com preferred), in care of Shiattin Makor, by March 28,  
2011, to facilitate the selection of specific items that will be reviewed during the onsite  
inspection week.  The inspectors will select specific items from the information requested  
below and then request from your staff additional documents needed during the onsite  
inspection week (Section B of this enclosure).  We ask that the specific items selected  
from the lists be available and ready for review on the first day of inspection.  Please  
provide requested documentation electronically if possible.  If requested documents are  
large and only hard copy formats are available, please inform the inspector(s), and  
provide subject documentation during the first day of the onsite inspection.  If you have  
any questions regarding this information request, please call the inspector as soon as  
possible.  
   
A.1  
ISI/Welding Programs and Schedule Information  
a)  
A detailed schedule (including preliminary dates) of:  
   
i)   
Nondestructive examinations planned for Class 1 & 2 systems and  
containment, performed as part of your ASME Section XI, risk informed (if  
applicable), and augmented inservice inspection programs during the  
upcoming outage  
   
Provide a status summary of the nondestructive examination inspection  
activities vs. the required inspection period percentages for this interval  
by category per ASME Section XI, IWX-2400.  Do not provide separately  
if other documentation requested contains this information  
ii)   
Reactor pressure vessel head examinations planned for the upcoming  
outage  
   
iii)  
Examinations planned for Alloy 82/182/600 components that are not  
included in the Section XI scope (If applicable)  
   
iv)  
Examinations planned as part of your boric acid corrosion control  
program (Mode 3 walkdowns, bolted connection walkdowns, etc.)  
 
   
- 2 -  
Enclosure  
   
v)  
Welding activities that are scheduled to be completed during the  
upcoming outage (ASME Class 1, 2, or 3 structures, systems, or  
components)  
   
b)  
A copy of ASME Section XI Code Relief Requests and associated NRC safety  
evaluations applicable to the examinations identified above.   
c)  
A list of nondestructive examination reports (ultrasonic, radiography, magnetic  
particle, dye penetrant, Visual VT-1, VT-2, and VT-3), which have identified  
relevant conditions on Code Class 1 & 2 systems since the beginning of the last  
refueling outage.  This should include the previous Section XI pressure test(s)  
conducted during start up and any evaluations associated with the results of the  
pressure tests.  Also, include in the list the nondestructive examination reports  
with relevant conditions in the reactor pressure vessel head penetration nozzles  
that have been accepted for continued service.  The list of nondestructive  
examination reports should include a brief description of the structures, systems,  
or components where the relevant condition was identified.  
or components where the relevant condition was identified.  
  d) A list with a brief description (e.g., system, material, pipe size, weld number, and nondestructive examinations performed) of the welds in Code Class 1 and 2 systems which have been fabricated due to component repair/replacement  
   
activities since the beginning of the last refueling outage, or are planned to be fabricated this refueling outage.   
d)  
  e) If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to  
A list with a brief description (e.g., system, material, pipe size, weld number, and  
be examined and the extent of the planned examination.  Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.  
nondestructive examinations performed) of the welds in Code Class 1 and 2  
  f) Copy of any 10 CFR Part 21 reports applicable to your structures, systems, or components within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.  
systems which have been fabricated due to component repair/replacement  
  g)  A list of any temporary noncode repairs in service (e.g., pinhole leaks).  
activities since the beginning of the last refueling outage, or are planned to be  
  h) Please provide copies of the most recent self-assessments for the inservice inspection, welding, and Alloy 600 programs.   
fabricated this refueling outage.   
  A.2 Reactor Pressure Vessel Head  
   
  a)  Provide the detailed scope of the planned nondestructive examinations of the reactor vessel head which identifies the types of nondestructive examination  
e)  
methods to be used on each specific part of the vessel head to fulfill commitments made in response to NRC Bulletin 2002-02 and NRC Order EA-03-009.  Also, include examination scope expansion criteria and   
If reactor vessel weld examinations required by the ASME Code are scheduled to  
  - 3 - Enclosure planned expansion sample sizes if relevant conditions are identified. (If applicable)  
occur during the upcoming outage, provide a detailed description of the welds to  
  b)  A list of the standards and/or requirements that will be used to evaluate indications identified during nondestructive examination of the reactor vessel  
be examined and the extent of the planned examination.  Please also provide  
head (e.g., the specific industry or procedural standards which will be used to evaluate potential leakage and/or flaw indications).  
reference numbers for applicable procedures that will be used to conduct these  
  A.3 Boric Acid Corrosion Control Program
examinations.  
  a)  Copy of the procedures that govern the scope, equipment and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.  
   
  b) Please provide a list of leaks (including Code class of the components) that have been identified since the last refueling outage and associated corrective action documentation.  If during the last cycle, the unit was shutdown, please provide  
f)  
documentation of containment walkdown inspections performed as part of the boric acid corrosion control program.  
Copy of any 10 CFR Part 21 reports applicable to your structures, systems, or  
  c) Please provide a copy of the most recent self-assessment performed for the boric acid corrosion control program.  
components within the scope of Section XI of the ASME Code that have been  
  A.4 Steam Generator Tube Inspections
identified since the beginning of the last refueling outage.  
  a) A detailed schedule of:  
   
  i)  Steam generator tube inspection, data analyses, and repair activities for the upcoming outage (If occurring)  
g)   
  ii)  Steam generator secondary side inspection activities for the upcoming outage. (If occurring)  
A list of any temporary noncode repairs in service (e.g., pinhole leaks).  
  b) Please provide a copy of your steam generator inservice inspection program and plan.  Please include a copy of the operational assessment from last outage and a copy of the following documents as they become available:   
   
  i) Degradation assessment ii) Condition monitoring assessment   
h)  
  c) If you are planning on modifying your Technical Specifications such that they are consistent with Technical Specification Task Force Traveler TSTF-449, "Steam Generator Tube Integrity," please provide copies of your correspondence with the NRC regarding deviations from the standard technical specifications.  
Please provide copies of the most recent self-assessments for the inservice  
  d) Copy of steam generator history documentation given to vendors performing eddy current testing of the steam generators during the upcoming outage.  
inspection, welding, and Alloy 600 programs.   
 
   
  - 4 - Enclosure e) Copy of steam generator eddy current data analyst guidelines and site validated eddy current technique specification sheets.  Additionally, please provide a copy of EPRI Appendix H, "Examination Technique Specification Sheets," qualification records.  f) Identify and quantify any steam generator tube leakage experienced during the previous operating cycle.  Also provide documentation identifying which steam generator was leaking and corrective actions completed or planned for this condition (If applicable).  
A.2  
  g)  Provide past history of the condition and issues pertaining to the secondary side of the steam generators (including items such as loose parts, fouling, top of tube sheet condition, crud removal amounts, etc.)  
Reactor Pressure Vessel Head
  h) Provide copies of your most recent self assessments of the steam generator monitoring, loose parts monitoring, and secondary side water chemistry control programs.  
  i) Indicate where the primary, secondary, and resolution analyses are scheduled to take place.  
a)   
  j) Provide a summary of the scope of the steam generator tube examinations, including examination methods such as Bobbin, Rotating Pancake, or Plus Point, and the percentage of tubes to be examined. Do not provide these documents separately if already included in other information requested.
Provide the detailed scope of the planned nondestructive examinations of the  
  A.5 Materials Reliability Program:  Primary System Piping Butt Weld Inspection and Evaluation Guideline (MRP-139) Activities   a) A list, with verification, that the baseline inspections of all applicable dissimilar metal butt welds have been completed by December 31, 2010.  
reactor vessel head which identifies the types of nondestructive examination  
  b) Verification that baseline inspection of hot leg and cold leg temperature dissimilar metal butt welds have been included in the inspection program and that the schedules for the baseline inspections are consistent with the baseline schedules in MRP-139.  
methods to be used on each specific part of the vessel head to fulfill  
  c) A list and schedule (examination dates) of all dissimilar metal butt weld examinations planned for the upcoming refueling outage.  If none are scheduled, then data from previous examinations should be available for review.  
commitments made in response to NRC Bulletin 2002-02 and  
  d) A list and schedule for any welding to be performed on dissimilar metal butt welds in the upcoming outage.  If no welding will be performed then records of previous welding on dissimilar metal butt welds and postweld nondestructive  
NRC Order EA-03-009.  Also, include examination scope expansion criteria and  
 
   
- 3 -  
Enclosure  
planned expansion sample sizes if relevant conditions are identified. (If  
applicable)  
   
b)   
A list of the standards and/or requirements that will be used to evaluate  
indications identified during nondestructive examination of the reactor vessel  
head (e.g., the specific industry or procedural standards which will be used to  
evaluate potential leakage and/or flaw indications).  
   
A.3  
Boric Acid Corrosion Control Program  
a)   
Copy of the procedures that govern the scope, equipment and implementation of  
the inspections required to identify boric acid leakage and the procedures for  
boric acid leakage/corrosion evaluation.  
   
b)  
Please provide a list of leaks (including Code class of the components) that have  
been identified since the last refueling outage and associated corrective action  
documentation.  If during the last cycle, the unit was shutdown, please provide  
documentation of containment walkdown inspections performed as part of the  
boric acid corrosion control program.  
   
c)  
Please provide a copy of the most recent self-assessment performed for the  
boric acid corrosion control program.  
   
A.4  
Steam Generator Tube Inspections  
a)  
A detailed schedule of:  
   
i)   
Steam generator tube inspection, data analyses, and repair activities for  
the upcoming outage (If occurring)  
   
ii)   
Steam generator secondary side inspection activities for the upcoming  
outage. (If occurring)  
   
b)  
Please provide a copy of your steam generator inservice inspection program and  
plan.  Please include a copy of the operational assessment from last outage and  
a copy of the following documents as they become available:   
   
i)  
Degradation assessment  
ii)  
Condition monitoring assessment   
   
c)  
If you are planning on modifying your Technical Specifications such that they are  
consistent with Technical Specification Task Force Traveler TSTF-449, Steam  
Generator Tube Integrity, please provide copies of your correspondence with the  
NRC regarding deviations from the standard technical specifications.  
   
d)  
Copy of steam generator history documentation given to vendors performing  
eddy current testing of the steam generators during the upcoming outage.  
 
- 4 -  
Enclosure  
e)  
Copy of steam generator eddy current data analyst guidelines and site validated  
eddy current technique specification sheets.  Additionally, please provide a copy  
of EPRI Appendix H, Examination Technique Specification Sheets, qualification  
records.  
   
f)  
Identify and quantify any steam generator tube leakage experienced during the  
previous operating cycle.  Also provide documentation identifying which steam  
generator was leaking and corrective actions completed or planned for this  
condition (If applicable).  
   
g)   
Provide past history of the condition and issues pertaining to the secondary side  
of the steam generators (including items such as loose parts, fouling, top of tube  
sheet condition, crud removal amounts, etc.)  
   
h)  
Provide copies of your most recent self assessments of the steam generator  
monitoring, loose parts monitoring, and secondary side water chemistry control  
programs.  
   
i)  
Indicate where the primary, secondary, and resolution analyses are scheduled to  
take place.  
   
j)  
Provide a summary of the scope of the steam generator tube examinations,  
including examination methods such as Bobbin, Rotating Pancake, or Plus Point,  
and the percentage of tubes to be examined. Do not provide these documents  
separately if already included in other information requested.  
A.5  
Materials Reliability Program:  Primary System Piping Butt Weld Inspection and  
Evaluation Guideline (MRP-139) Activities  
a)  
A list, with verification, that the baseline inspections of all applicable dissimilar  
metal butt welds have been completed by December 31, 2010.  
   
b)  
Verification that baseline inspection of hot leg and cold leg temperature dissimilar  
metal butt welds have been included in the inspection program and that the  
schedules for the baseline inspections are consistent with the baseline schedules  
in MRP-139.  
   
c)  
A list and schedule (examination dates) of all dissimilar metal butt weld  
examinations planned for the upcoming refueling outage.  If none are scheduled,  
then data from previous examinations should be available for review.  
   
d)  
A list and schedule for any welding to be performed on dissimilar metal butt  
welds in the upcoming outage.  If no welding will be performed then records of  
previous welding on dissimilar metal butt welds and postweld nondestructive  
examination documentation.  
examination documentation.  
 
  - 5 - Enclosure e) A list and schedule of any stress improvement activities planned for the upcoming refueling outage.  If none are scheduled then have qualification reports for any stress improvements previously performed.  
 
  f) Documentation and description of how the baseline and inservice inspection specifications in MRP-139 are satisfied at your facility.  
  g) A list of weld locations controlled by MRP-139 which includes the MRP-139 weld category, pre-mitigation volumetric examination date, type of mitigation or stress improvement, post mitigation volumetric examination date, and plans for future  
- 5 -  
Enclosure  
e)  
A list and schedule of any stress improvement activities planned for the  
upcoming refueling outage.  If none are scheduled then have qualification reports  
for any stress improvements previously performed.  
   
f)  
Documentation and description of how the baseline and inservice inspection  
specifications in MRP-139 are satisfied at your facility.  
   
g)  
A list of weld locations controlled by MRP-139 which includes the MRP-139 weld  
category, pre-mitigation volumetric examination date, type of mitigation or stress  
improvement, post mitigation volumetric examination date, and plans for future  
MRP-139 required examinations.  
MRP-139 required examinations.  
  A.6 Additional Information Related to all Inservice Inspection Activities
   
  a)  A list with a brief description of inservice inspection, boric acid corrosion control program, and steam generator tube inspection related issues (e.g., condition reports) entered into your corrective action program since the beginning of the  
A.6  
last refueling outage (for Unit 2).  For example, a list based upon data base searches using key words related to piping or steam generator tube degradation such as: inservice inspection, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping/steam generator tube examinations.  
Additional Information Related to all Inservice Inspection Activities  
  b)  Please provide names and phone numbers for the following program leads:  
  Inservice inspection (examination, planning) Containment exams  
a)   
Reactor pressure vessel head exams Snubbers and supports Repair and replacement program  Licensing  Site welding engineer  
A list with a brief description of inservice inspection, boric acid corrosion control  
Boric acid corrosion control program Steam generator inspection activities (site lead and vendor contact)  
program, and steam generator tube inspection related issues (e.g., condition  
  B. Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 12, 2011):  B.1 Inservice Inspection / Welding Programs and Schedule Information
reports) entered into your corrective action program since the beginning of the  
  a) Updated schedules for inservice inspection/nondestructive examination activities, including steam generator tube inspections, planned welding activities, and schedule showing contingency repair plans, if available.  
last refueling outage (for Unit 2).  For example, a list based upon data base  
  b) For ASME Code Class 1 and 2 welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:  
searches using key words related to piping or steam generator tube degradation  
 
such as: inservice inspection, ASME Code, Section XI, NDE, cracks, wear,  
  - 6 - Enclosure i) Weld data sheet (traveler)
thinning, leakage, rust, corrosion, boric acid, or errors in piping/steam generator  
ii) Weld configuration and system location
tube examinations.  
  iii) Applicable Code Edition and Addenda for weldment
   
b)   
Please provide names and phone numbers for the following program leads:  
   
Inservice inspection (examination, planning)  
Containment exams  
Reactor pressure vessel head exams  
Snubbers and supports  
Repair and replacement program   
Licensing   
Site welding engineer  
Boric acid corrosion control program  
Steam generator inspection activities (site lead and vendor contact)  
   
B.  
Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 12,  
2011):  
   
B.1  
Inservice Inspection / Welding Programs and Schedule Information  
a)  
Updated schedules for inservice inspection/nondestructive examination activities,  
including steam generator tube inspections, planned welding activities, and  
schedule showing contingency repair plans, if available.  
   
b)  
For ASME Code Class 1 and 2 welds selected by the inspector from the lists  
provided from section A of this enclosure, please provide copies of the following  
documentation for each subject weld:  
   


iv) Applicable Code Edition and Addenda for welding procedures
v) Applicable weld procedures used to fabricate the welds
   
   
vi) Copies of procedure qualification records supporting the weld procedures from B.1.b.v
vii) Copies of mechanical test reports identified in the procedure qualification records above
viii) Copies of the nonconformance reports for the selected welds (If applicable)
ix) Radiographs of the selected welds and access to equipment to allow viewing radiographs (If radiographic testing was performed)
   
   
x) Copies of the preservice examination records for the selected welds  
  xi) Copies of welder performance qualifications records applicable to the selected welds, including documentation that welder maintained proficiency in the applicable welding processes specified in the weld  
- 6 -
Enclosure
i)
Weld data sheet (traveler)
ii)
Weld configuration and system location
iii)
Applicable Code Edition and Addenda for weldment
iv)
Applicable Code Edition and Addenda for welding procedures
v)
Applicable weld procedures used to fabricate the welds
vi)
Copies of procedure qualification records supporting the weld procedures
from B.1.b.v
vii)
Copies of mechanical test reports identified in the procedure qualification
records above
viii)
Copies of the nonconformance reports for the selected welds (If
applicable)
ix)
Radiographs of the selected welds and access to equipment to allow
viewing radiographs (If radiographic testing was performed)
x)  
Copies of the preservice examination records for the selected welds  
   
xi)  
Copies of welder performance qualifications records applicable to the  
selected welds, including documentation that welder maintained  
proficiency in the applicable welding processes specified in the weld  
procedures (at least 6 months prior to the date of subject work)  
procedures (at least 6 months prior to the date of subject work)  
  xii) Copies of nondestructive examination personnel qualifications (Visual inspection, penetrant testing, ultrasonic testing, radiographic testing), as applicable  
   
  c) For the inservice inspection related corrective action issues selected by the inspectors from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.  
xii)  
  d) For the nondestructive examination reports with relevant conditions on Code Class 1 and 2 systems selected by the inspectors from Section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.  
Copies of nondestructive examination personnel qualifications (Visual  
  e) A copy of (or ready access to) most current revision of the inservice inspection program manual and plan for the current Interval.   
inspection, penetrant testing, ultrasonic testing, radiographic testing), as  
  f) For the nondestructive examinations selected by the inspectors from section A of this enclosure, provide a copy of the nondestructive examination procedures used to perform the examinations (including calibration and flaw   
applicable  
  - 7 - Enclosure characterization/sizing procedures).  For ultrasonic examination procedures qualified in accordance with ASME Section XI, Appendix VIII, provide documentation supporting the procedure qualification (e.g., the EPRI performance demonstration qualification summary sheets).  Also, include qualification documentation of the specific equipment to be used (e.g., ultrasonic  
   
unit, cables, and transducers including serial numbers) and nondestructive examination personnel qualification records.  
c)  
  B.2 Reactor Pressure Vessel Head  
For the inservice inspection related corrective action issues selected by the  
  a) Provide the nondestructive personnel qualification records for the examiners who will perform examinations of the reactor pressure vessel head.   
inspectors from section A of this enclosure, provide a copy of the corrective  
  b) Provide drawings showing the following:  (If a visual examination is planned for the upcoming refueling outage)  
actions and supporting documentation.  
  i) Reactor pressure vessel head and control rod drive mechanism nozzle configurations   
   
  ii) Reactor pressure vessel head insulation configuration   
d)  
  Note: The drawings listed above should include fabrication drawings for  
For the nondestructive examination reports with relevant conditions on Code  
Class 1 and 2 systems selected by the inspectors from Section A above, provide  
a copy of the examination records, examiner qualification records, and  
associated corrective action documents.  
   
e)  
A copy of (or ready access to) most current revision of the inservice inspection  
program manual and plan for the current Interval.   
   
f)  
For the nondestructive examinations selected by the inspectors from section A of  
this enclosure, provide a copy of the nondestructive examination procedures  
used to perform the examinations (including calibration and flaw  
 
   
- 7 -  
Enclosure  
characterization/sizing procedures).  For ultrasonic examination procedures  
qualified in accordance with ASME Section XI, Appendix VIII, provide  
documentation supporting the procedure qualification (e.g., the EPRI  
performance demonstration qualification summary sheets).  Also, include  
qualification documentation of the specific equipment to be used (e.g., ultrasonic  
unit, cables, and transducers including serial numbers) and nondestructive  
examination personnel qualification records.  
   
B.2  
Reactor Pressure Vessel Head
a)  
Provide the nondestructive personnel qualification records for the examiners who  
will perform examinations of the reactor pressure vessel head.   
   
b)  
Provide drawings showing the following:  (If a visual examination is planned for  
the upcoming refueling outage)  
   
i)  
Reactor pressure vessel head and control rod drive mechanism nozzle  
configurations   
   
ii)  
Reactor pressure vessel head insulation configuration   
   
Note: The drawings listed above should include fabrication drawings for  
the nozzle attachment welds as applicable.   
the nozzle attachment welds as applicable.   
c) Copy of nondestructive examination reports from the last reactor pressure vessel head examination.
   
   
d) Copy of evaluation or calculation demonstrating that the scope of the visual examination of the upper head will meet the 95 percent minimum coverage required by NRC Order EA-03-009 (If a visual examination is planned for the upcoming refueling outage).  
c)  
Copy of nondestructive examination reports from the last reactor pressure vessel
head examination.  
   
   
e) Provide a copy of the procedures that will be used to identify the source of any boric acid deposits identified on the reactor pressure vessel headIf no explicit procedures exist which govern this activity, provide a description of the process to be followed including personnel responsibilities and expectations.
d)  
Copy of evaluation or calculation demonstrating that the scope of the visual
examination of the upper head will meet the 95 percent minimum coverage
required by NRC Order EA-03-009 (If a visual examination is planned for the  
upcoming refueling outage).  
   
   
f)  Provide a copy of the updated calculation of effective degradation years for the reactor pressure vessel head susceptibility ranking.  
e)
  g)  Provide copy of the vendor qualification report(s) that demonstrates the detection capability of the nondestructive examination equipment used for the reactor pressure vessel head examinations.  Also, identify any changes in equipment configurations used for the reactor pressure vessel head examinations which  
Provide a copy of the procedures that will be used to identify the source of any
differ from that used in the vendor qualification report(s).   
boric acid deposits identified on the reactor pressure vessel head.  If no explicit
  - 8 - Enclosure  
procedures exist which govern this activity, provide a description of the process
  B.3 Boric Acid Corrosion Control Program  
to be followed including personnel responsibilities and expectations. 
  a) Please provide boric acid walkdown inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action  
f)   
Provide a copy of the updated calculation of effective degradation years for the  
reactor pressure vessel head susceptibility ranking.  
   
g)   
Provide copy of the vendor qualification report(s) that demonstrates the detection  
capability of the nondestructive examination equipment used for the reactor  
pressure vessel head examinations.  Also, identify any changes in equipment  
configurations used for the reactor pressure vessel head examinations which  
differ from that used in the vendor qualification report(s).  
 
   
- 8 -  
Enclosure  
   
B.3  
Boric Acid Corrosion Control Program
a)  
Please provide boric acid walkdown inspection results, an updated list of boric  
acid leaks identified so far this outage, associated corrective action  
documentation, and overall status of planned boric acid inspections.   
documentation, and overall status of planned boric acid inspections.   
b) Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage.  Please include a status of corrective actions to repair and/or clean these boric acid leaks.  Please identify
specifically which known leaks, if any, have remained in service or will remain in service as active leaks. 
B.4 Steam Generator Tube Inspections
  a) Copies of the Examination Technique Specification Sheets and associated justification for any revisions.
b) Copy of the guidance to be followed if a loose part or foreign material is identified in the steam generators.
c) Please provide a copy of the eddy current testing procedures used to perform the steam generator tube inspections (specifically calibration and flaw characterization/sizing procedures, etc.).  Also include documentation for the specific equipment to be used.
d) Please provide copies of your responses to NRC and industry operating experience communications such as Generic Letters, Information Notices, etc. (as applicable to steam generator tube inspections)  Do not provide these documents separately if already included in other information requested such as the degradation assessment.
 
e) List of corrective action documents generated by the vendor and/or site with respect to steam generator inspection activities.
  B.5 Codes and Standards
  a) Ready access to (i.e., copies provided to the inspector(s) for use during the inspection at the onsite inspection location, or room number and location where available):
i)  Applicable Editions of the ASME Code (Sections V, IX, and XI) for the inservice inspection program and the repair/replacement program. 
   
   
ii)  EPRI and industry standards referenced in the procedures used to perform the steam generator tube eddy current examination.  
b)
 
Please provide any engineering evaluations completed for boric acid leaks
  - 9 - Enclosure Inspector Contact Information:  
identified since the end of the last refueling outage.  Please include a status of
  Shiattin Makor   Megan Williams     Reactor Inspector  Reactor Inspector   817-276-6507   817-860-8076    
corrective actions to repair and/or clean these boric acid leaks.  Please identify
shiattin.makor@nrc.gov
specifically which known leaks, if any, have remained in service or will remain in
megan.williams@nrc.gov     Mailing Address: US NRC Region IV Attn: Shiattin Makor  
service as active leaks. 
612 E. Lamar Blvd, Suite 400 Arlington, TX 76011
B.4
Steam Generator Tube Inspections
a)
Copies of the Examination Technique Specification Sheets and associated
justification for any revisions.
b)
Copy of the guidance to be followed if a loose part or foreign material is identified
in the steam generators.
c)
Please provide a copy of the eddy current testing procedures used to perform the
steam generator tube inspections (specifically calibration and flaw
characterization/sizing procedures, etc.).  Also include documentation for the
specific equipment to be used.
d)
Please provide copies of your responses to NRC and industry operating
experience communications such as Generic Letters, Information Notices, etc.
(as applicable to steam generator tube inspections)  Do not provide these
documents separately if already included in other information requested such as
the degradation assessment.
e)
List of corrective action documents generated by the vendor and/or site with
respect to steam generator inspection activities.
B.5
Codes and Standards
a)
Ready access to (i.e., copies provided to the inspector(s) for use during the
inspection at the onsite inspection location, or room number and location where
available):
i) 
Applicable Editions of the ASME Code (Sections V, IX, and XI) for the
inservice inspection program and the repair/replacement program. 
ii)   
EPRI and industry standards referenced in the procedures used to  
perform the steam generator tube eddy current examination.  
 
- 9 -  
Enclosure  
Inspector Contact Information:  
   
Shiattin Makor
Megan Williams  
Reactor Inspector  
   
Reactor Inspector  
817-276-6507
817-860-8076
shiattin.makor@nrc.gov  
megan.williams@nrc.gov  
Mailing Address:  
US NRC Region IV  
Attn: Shiattin Makor  
612 E. Lamar Blvd, Suite 400  
Arlington, TX 76011
}}
}}

Latest revision as of 23:38, 13 January 2025

Notification of Inspection (NRC Inspection Report 05000382-11-003) and Request for Information
ML110630123
Person / Time
Site: Waterford Entergy icon.png
Issue date: 03/04/2011
From: Greg Werner
NRC/RGN-IV/DRS/PSB-2
To: Kowalewski J
Entergy Operations
References
IR-11-003
Download: ML110630123 (14)


See also: IR 05000382/2011003

Text

March 4, 2011

Joseph Kowalewski

Vice President, Operations

Entergy Operations, Inc.

Waterford Steam Electric Station, Unit 3

17265 River Road

Killona, LA 70057-3093

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NOTIFICATION OF

INSPECTION (NRC INSPECTION REPORT 05000382/2011003) AND

REQUEST FOR INFORMATION

Dear Mr. Kowalewski:

From April 11-15 and 25-29, 2011, reactor inspectors from the Nuclear Regulatory

Commissions (NRC) Region IV office will perform the baseline inservice inspection at

Waterford, using NRC Inspection Procedure 71111.08, Inservice Inspection Activities, and

TI 2515/172, Reactor Coolant System Dissimilar Metal Butt Welds. Experience has shown

that this inspection is a resource intensive inspection both for the NRC inspectors and your staff.

In order to minimize the impact to your onsite resources and to ensure a productive inspection,

we have enclosed a request for documents needed for this inspection. These documents have

been divided into two groups. The first group (Section A of the enclosure), due by March 28,

2011, identifies information to be provided prior to the inspection to ensure that the inspectors

are adequately prepared. The second group (Section B of the enclosure) identifies the

information the inspectors will need upon arrival at the site. It is important that all of these

documents are up to date and complete in order to minimize the number of additional

documents requested during the preparation and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Mr. Jim Pollock of your licensing

organization. Our inspection dates are subject to change based on your updated schedule of

outage activities. If there are any questions about this inspection or the material requested,

please contact the lead inspector Shiattin Makor (817) 276-6507 (shiattin.makor@nrc.gov) or

Megan Williams at (817) 860-8076 (megan.williams@nrc.gov).

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Entergy Operations, Inc.

- 2 -

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document

system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ James F. Drake for

Gregory E. Werner, Chief

Plant Support Branch 2

Division of Reactor Safety

Docket No: 50-382

License No. NPF-38

Enclosure:

Inservice Inspection Document Request

Enclosure:

Inservice Inspection Document

Request

cc w/enclosure:

John T. Herron

Entergy Services, Inc.

President and CEO

Nuclear Operations/CNO

P.O. Box 31995

Jackson, MS 39286-1995

Jeff Forbes

Senior Vice President and

Chief Operating Officer

Entergy Operations, Inc.

P. O. Box 31995

Jackson, MS 39286-1995

Entergy Operations, Inc.

- 3 -

Thomas Palmisano

Vice President, Oversight

Entergy Operations, Inc.

P. O. Box 31995

Jackson, MS 39286-1995

Senior Manager, Nuclear Safety

and Licensing

Entergy Services, Inc.

P. O. Box 31995

Jackson, MS 39286-1995

Kenny J. Christian, Director

Nuclear Safety Assurance

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

Joseph A. Aluise

Associate General Council - Nuclear

Entergy Services, Inc.

639 Loyola Avenue

New Orleans, LA 70113

Steven Adams, Acting Director

Nuclear Safety Assurance

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

Charles F. Arnone

General Manager, Plant Operations

Waterford 3 SES

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

Manager, Licensing

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

Chairman

Louisiana Public Service Commission

P. O. Box 91154

Baton Rouge, LA 70821-9154

Entergy Operations, Inc.

- 4 -

Parish President Council

St. Charles Parish

P. O. Box 302

Hahnville, LA 70057

Billy Steelman, Manager

Licensing and Regulatory Affairs

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

St. Charles Parish

Dept. of Emergency Preparedness

Emergency Operations Center

P.O. Box 302

Hahnville, LA 70057

Director, Nuclear Safety & Licensing

Entergy, Operations, Inc.

440 Hamilton Avenue

White Plains, NY 10601

Louisiana Department of Environmental Quality

Radiological Emergency Planning

and Response Division

P. O. Box 4312

Baton Rouge, LA 70821-4312

Chief, Technological Hazards

Branch

FEMA Region VI

800 North Loop 288

Federal Regional Center

Denton, TX 76209

Kenny J. Christian, Director

Nuclear Safety Assurance

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057-0751

Entergy Operations, Inc.

- 5 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Vacant)

Senior Resident Inspector (Marlone.Davis@nrc.gov)

Resident Inspector (Dean.Overland@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

Project Engineer (Jim.Melfi@nrc.gov)

Project Engineer (William.Schaup@nrc.gov)

WAT Administrative Assistant (Linda.Dufrene@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Kaly.Kalyanam@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

OEDO RIV Coordinator (James.Trapp@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

SUNSI Review Completed: ___Y___

ADAMS: 7 Yes

No Initials: _JFD_

7 Publicly Available Non-Publicly Available Sensitive

7 Non-Sensitive

ML

EB1

C:PSB2

SMakor

GWerner

/RA/ Telecon

/RA/ JFDrake for

3/3/11

3/3/11

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

- 1 -

Enclosure

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates:

April 11-15 and 25-29, 2011

Inspection Procedures:

IP 71111.08 Inservice Inspection (ISI) Activities

TI 2515/172 Reactor Coolant System Dissimilar Metal Butt Welds

Inspectors:

Shiattin Makor, Reactor Inspector (Lead Inspector - ISI)

Megan Williams, Reactor Inspector

A.

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or

electronic format (ims.certrec.com preferred), in care of Shiattin Makor, by March 28,

2011, to facilitate the selection of specific items that will be reviewed during the onsite

inspection week. The inspectors will select specific items from the information requested

below and then request from your staff additional documents needed during the onsite

inspection week (Section B of this enclosure). We ask that the specific items selected

from the lists be available and ready for review on the first day of inspection. Please

provide requested documentation electronically if possible. If requested documents are

large and only hard copy formats are available, please inform the inspector(s), and

provide subject documentation during the first day of the onsite inspection. If you have

any questions regarding this information request, please call the inspector as soon as

possible.

A.1

ISI/Welding Programs and Schedule Information

a)

A detailed schedule (including preliminary dates) of:

i)

Nondestructive examinations planned for Class 1 & 2 systems and

containment, performed as part of your ASME Section XI, risk informed (if

applicable), and augmented inservice inspection programs during the

upcoming outage

Provide a status summary of the nondestructive examination inspection

activities vs. the required inspection period percentages for this interval

by category per ASME Section XI, IWX-2400. Do not provide separately

if other documentation requested contains this information

ii)

Reactor pressure vessel head examinations planned for the upcoming

outage

iii)

Examinations planned for Alloy 82/182/600 components that are not

included in the Section XI scope (If applicable)

iv)

Examinations planned as part of your boric acid corrosion control

program (Mode 3 walkdowns, bolted connection walkdowns, etc.)

- 2 -

Enclosure

v)

Welding activities that are scheduled to be completed during the

upcoming outage (ASME Class 1, 2, or 3 structures, systems, or

components)

b)

A copy of ASME Section XI Code Relief Requests and associated NRC safety

evaluations applicable to the examinations identified above.

c)

A list of nondestructive examination reports (ultrasonic, radiography, magnetic

particle, dye penetrant, Visual VT-1, VT-2, and VT-3), which have identified

relevant conditions on Code Class 1 & 2 systems since the beginning of the last

refueling outage. This should include the previousSection XI pressure test(s)

conducted during start up and any evaluations associated with the results of the

pressure tests. Also, include in the list the nondestructive examination reports

with relevant conditions in the reactor pressure vessel head penetration nozzles

that have been accepted for continued service. The list of nondestructive

examination reports should include a brief description of the structures, systems,

or components where the relevant condition was identified.

d)

A list with a brief description (e.g., system, material, pipe size, weld number, and

nondestructive examinations performed) of the welds in Code Class 1 and 2

systems which have been fabricated due to component repair/replacement

activities since the beginning of the last refueling outage, or are planned to be

fabricated this refueling outage.

e)

If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to

be examined and the extent of the planned examination. Please also provide

reference numbers for applicable procedures that will be used to conduct these

examinations.

f)

Copy of any 10 CFR Part 21 reports applicable to your structures, systems, or

components within the scope of Section XI of the ASME Code that have been

identified since the beginning of the last refueling outage.

g)

A list of any temporary noncode repairs in service (e.g., pinhole leaks).

h)

Please provide copies of the most recent self-assessments for the inservice

inspection, welding, and Alloy 600 programs.

A.2

Reactor Pressure Vessel Head

a)

Provide the detailed scope of the planned nondestructive examinations of the

reactor vessel head which identifies the types of nondestructive examination

methods to be used on each specific part of the vessel head to fulfill

commitments made in response to NRC Bulletin 2002-02 and

NRC Order EA-03-009. Also, include examination scope expansion criteria and

- 3 -

Enclosure

planned expansion sample sizes if relevant conditions are identified. (If

applicable)

b)

A list of the standards and/or requirements that will be used to evaluate

indications identified during nondestructive examination of the reactor vessel

head (e.g., the specific industry or procedural standards which will be used to

evaluate potential leakage and/or flaw indications).

A.3

Boric Acid Corrosion Control Program

a)

Copy of the procedures that govern the scope, equipment and implementation of

the inspections required to identify boric acid leakage and the procedures for

boric acid leakage/corrosion evaluation.

b)

Please provide a list of leaks (including Code class of the components) that have

been identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the unit was shutdown, please provide

documentation of containment walkdown inspections performed as part of the

boric acid corrosion control program.

c)

Please provide a copy of the most recent self-assessment performed for the

boric acid corrosion control program.

A.4

Steam Generator Tube Inspections

a)

A detailed schedule of:

i)

Steam generator tube inspection, data analyses, and repair activities for

the upcoming outage (If occurring)

ii)

Steam generator secondary side inspection activities for the upcoming

outage. (If occurring)

b)

Please provide a copy of your steam generator inservice inspection program and

plan. Please include a copy of the operational assessment from last outage and

a copy of the following documents as they become available:

i)

Degradation assessment

ii)

Condition monitoring assessment

c)

If you are planning on modifying your Technical Specifications such that they are

consistent with Technical Specification Task Force Traveler TSTF-449, Steam

Generator Tube Integrity, please provide copies of your correspondence with the

NRC regarding deviations from the standard technical specifications.

d)

Copy of steam generator history documentation given to vendors performing

eddy current testing of the steam generators during the upcoming outage.

- 4 -

Enclosure

e)

Copy of steam generator eddy current data analyst guidelines and site validated

eddy current technique specification sheets. Additionally, please provide a copy

of EPRI Appendix H, Examination Technique Specification Sheets, qualification

records.

f)

Identify and quantify any steam generator tube leakage experienced during the

previous operating cycle. Also provide documentation identifying which steam

generator was leaking and corrective actions completed or planned for this

condition (If applicable).

g)

Provide past history of the condition and issues pertaining to the secondary side

of the steam generators (including items such as loose parts, fouling, top of tube

sheet condition, crud removal amounts, etc.)

h)

Provide copies of your most recent self assessments of the steam generator

monitoring, loose parts monitoring, and secondary side water chemistry control

programs.

i)

Indicate where the primary, secondary, and resolution analyses are scheduled to

take place.

j)

Provide a summary of the scope of the steam generator tube examinations,

including examination methods such as Bobbin, Rotating Pancake, or Plus Point,

and the percentage of tubes to be examined. Do not provide these documents

separately if already included in other information requested.

A.5

Materials Reliability Program: Primary System Piping Butt Weld Inspection and

Evaluation Guideline (MRP-139) Activities

a)

A list, with verification, that the baseline inspections of all applicable dissimilar

metal butt welds have been completed by December 31, 2010.

b)

Verification that baseline inspection of hot leg and cold leg temperature dissimilar

metal butt welds have been included in the inspection program and that the

schedules for the baseline inspections are consistent with the baseline schedules

in MRP-139.

c)

A list and schedule (examination dates) of all dissimilar metal butt weld

examinations planned for the upcoming refueling outage. If none are scheduled,

then data from previous examinations should be available for review.

d)

A list and schedule for any welding to be performed on dissimilar metal butt

welds in the upcoming outage. If no welding will be performed then records of

previous welding on dissimilar metal butt welds and postweld nondestructive

examination documentation.

- 5 -

Enclosure

e)

A list and schedule of any stress improvement activities planned for the

upcoming refueling outage. If none are scheduled then have qualification reports

for any stress improvements previously performed.

f)

Documentation and description of how the baseline and inservice inspection

specifications in MRP-139 are satisfied at your facility.

g)

A list of weld locations controlled by MRP-139 which includes the MRP-139 weld

category, pre-mitigation volumetric examination date, type of mitigation or stress

improvement, post mitigation volumetric examination date, and plans for future

MRP-139 required examinations.

A.6

Additional Information Related to all Inservice Inspection Activities

a)

A list with a brief description of inservice inspection, boric acid corrosion control

program, and steam generator tube inspection related issues (e.g., condition

reports) entered into your corrective action program since the beginning of the

last refueling outage (for Unit 2). For example, a list based upon data base

searches using key words related to piping or steam generator tube degradation

such as: inservice inspection, ASME Code,Section XI, NDE, cracks, wear,

thinning, leakage, rust, corrosion, boric acid, or errors in piping/steam generator

tube examinations.

b)

Please provide names and phone numbers for the following program leads:

Inservice inspection (examination, planning)

Containment exams

Reactor pressure vessel head exams

Snubbers and supports

Repair and replacement program

Licensing

Site welding engineer

Boric acid corrosion control program

Steam generator inspection activities (site lead and vendor contact)

B.

Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 12,

2011):

B.1

Inservice Inspection / Welding Programs and Schedule Information

a)

Updated schedules for inservice inspection/nondestructive examination activities,

including steam generator tube inspections, planned welding activities, and

schedule showing contingency repair plans, if available.

b)

For ASME Code Class 1 and 2 welds selected by the inspector from the lists

provided from section A of this enclosure, please provide copies of the following

documentation for each subject weld:

- 6 -

Enclosure

i)

Weld data sheet (traveler)

ii)

Weld configuration and system location

iii)

Applicable Code Edition and Addenda for weldment

iv)

Applicable Code Edition and Addenda for welding procedures

v)

Applicable weld procedures used to fabricate the welds

vi)

Copies of procedure qualification records supporting the weld procedures

from B.1.b.v

vii)

Copies of mechanical test reports identified in the procedure qualification

records above

viii)

Copies of the nonconformance reports for the selected welds (If

applicable)

ix)

Radiographs of the selected welds and access to equipment to allow

viewing radiographs (If radiographic testing was performed)

x)

Copies of the preservice examination records for the selected welds

xi)

Copies of welder performance qualifications records applicable to the

selected welds, including documentation that welder maintained

proficiency in the applicable welding processes specified in the weld

procedures (at least 6 months prior to the date of subject work)

xii)

Copies of nondestructive examination personnel qualifications (Visual

inspection, penetrant testing, ultrasonic testing, radiographic testing), as

applicable

c)

For the inservice inspection related corrective action issues selected by the

inspectors from section A of this enclosure, provide a copy of the corrective

actions and supporting documentation.

d)

For the nondestructive examination reports with relevant conditions on Code

Class 1 and 2 systems selected by the inspectors from Section A above, provide

a copy of the examination records, examiner qualification records, and

associated corrective action documents.

e)

A copy of (or ready access to) most current revision of the inservice inspection

program manual and plan for the current Interval.

f)

For the nondestructive examinations selected by the inspectors from section A of

this enclosure, provide a copy of the nondestructive examination procedures

used to perform the examinations (including calibration and flaw

- 7 -

Enclosure

characterization/sizing procedures). For ultrasonic examination procedures

qualified in accordance with ASME Section XI, Appendix VIII, provide

documentation supporting the procedure qualification (e.g., the EPRI

performance demonstration qualification summary sheets). Also, include

qualification documentation of the specific equipment to be used (e.g., ultrasonic

unit, cables, and transducers including serial numbers) and nondestructive

examination personnel qualification records.

B.2

Reactor Pressure Vessel Head

a)

Provide the nondestructive personnel qualification records for the examiners who

will perform examinations of the reactor pressure vessel head.

b)

Provide drawings showing the following: (If a visual examination is planned for

the upcoming refueling outage)

i)

Reactor pressure vessel head and control rod drive mechanism nozzle

configurations

ii)

Reactor pressure vessel head insulation configuration

Note: The drawings listed above should include fabrication drawings for

the nozzle attachment welds as applicable.

c)

Copy of nondestructive examination reports from the last reactor pressure vessel

head examination.

d)

Copy of evaluation or calculation demonstrating that the scope of the visual

examination of the upper head will meet the 95 percent minimum coverage

required by NRC Order EA-03-009 (If a visual examination is planned for the

upcoming refueling outage).

e)

Provide a copy of the procedures that will be used to identify the source of any

boric acid deposits identified on the reactor pressure vessel head. If no explicit

procedures exist which govern this activity, provide a description of the process

to be followed including personnel responsibilities and expectations.

f)

Provide a copy of the updated calculation of effective degradation years for the

reactor pressure vessel head susceptibility ranking.

g)

Provide copy of the vendor qualification report(s) that demonstrates the detection

capability of the nondestructive examination equipment used for the reactor

pressure vessel head examinations. Also, identify any changes in equipment

configurations used for the reactor pressure vessel head examinations which

differ from that used in the vendor qualification report(s).

- 8 -

Enclosure

B.3

Boric Acid Corrosion Control Program

a)

Please provide boric acid walkdown inspection results, an updated list of boric

acid leaks identified so far this outage, associated corrective action

documentation, and overall status of planned boric acid inspections.

b)

Please provide any engineering evaluations completed for boric acid leaks

identified since the end of the last refueling outage. Please include a status of

corrective actions to repair and/or clean these boric acid leaks. Please identify

specifically which known leaks, if any, have remained in service or will remain in

service as active leaks.

B.4

Steam Generator Tube Inspections

a)

Copies of the Examination Technique Specification Sheets and associated

justification for any revisions.

b)

Copy of the guidance to be followed if a loose part or foreign material is identified

in the steam generators.

c)

Please provide a copy of the eddy current testing procedures used to perform the

steam generator tube inspections (specifically calibration and flaw

characterization/sizing procedures, etc.). Also include documentation for the

specific equipment to be used.

d)

Please provide copies of your responses to NRC and industry operating

experience communications such as Generic Letters, Information Notices, etc.

(as applicable to steam generator tube inspections) Do not provide these

documents separately if already included in other information requested such as

the degradation assessment.

e)

List of corrective action documents generated by the vendor and/or site with

respect to steam generator inspection activities.

B.5

Codes and Standards

a)

Ready access to (i.e., copies provided to the inspector(s) for use during the

inspection at the onsite inspection location, or room number and location where

available):

i)

Applicable Editions of the ASME Code (Sections V, IX, and XI) for the

inservice inspection program and the repair/replacement program.

ii)

EPRI and industry standards referenced in the procedures used to

perform the steam generator tube eddy current examination.

- 9 -

Enclosure

Inspector Contact Information:

Shiattin Makor

Megan Williams

Reactor Inspector

Reactor Inspector

817-276-6507

817-860-8076

shiattin.makor@nrc.gov

megan.williams@nrc.gov

Mailing Address:

US NRC Region IV

Attn: Shiattin Makor

612 E. Lamar Blvd, Suite 400

Arlington, TX 76011