ML12173A481: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 July 29, 2012 Mr. Thomas Saporito Saprodani Associates 177 US Hwy 1N, Unit 212 Tequesta, Florida 33469
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 July 29, 2012 Mr. Thomas Saporito Saprodani Associates 177 US Hwy 1N, Unit 212 Tequesta, Florida 33469 Dear Mr. Saporito: In your letter to the Executive Director for Operations (EDO) of the Nuclear Regulatory Commission (NRC), dated March 1,2012, pursuant to Title 10 of the Code ofFederal Regulations (10 CFR) Section 2.206 of the NRC's regulations, you made the following request for enforcement related action: "Petitioner respectfully requests that the NRC: (1) take escalated enforcement action against the above-captioned licensee(s) and suspend, or revoke the NRC license(s) granted to the licensee for operation of the licensees' Palisades Nuclear Plant in the USA; (2) that the NRC issue a notice of violation with a proposed civil penalty against the licensee in the total amount of $1,000,000.00 (One-Million) dollars; and (3) that the NRC issue a Confirmatory Order requiring the licensee (to take certain and specific actions) and to bring the Palisades Nuclear Plant to a "cold-shutdown" mode of operation until such time as: The licensee completes an lIindependent" Safety Culture Assessment (SCA) to more fully understand and correct the "root-cause" of multiple violations of NRC safety regulations and requirements at the Palisades Nuclear Plant2; and The licensee completes a comprehensive training program of all station maintenance personnel (including supervision) to ensure the all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes a comprehensive training program of all station operations personnel (including supervision) to ensure that all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes an lIindependent" safety-assessment thorough [through] a 3rd party contractor to review all Palisades Nuclear Plant operation and maintenance procedures to ascertain whether the procedures require IIrisk assessment" by licensed operations personnel prior to execution; and The licensee completes IIdestructive" testing and analysis to determine: (1) the extent of embrittlement of the Palisades Nuclear Plant reactor vessel; and (2) whether the nuclear reactor vessel remains in full compliance with NRC safety regulations and requirements under 10 C.F.R. §50; and under other NRC authority." 2 See, NRC February 14. 2012 -Final Significance Determination of Yellow and White Findings with Assessment Follow up and Notice of Violation NRC Inspection Report Nos. 05000255/2011019 and 05000255/2011020 Palisades Nuclear Plant."
 
T. Saporito As the basis for this request, you referenced the NRC Inspection Report 05000255/2011019 and 05000255/2011020 for Palisades Nuclear Plant (PNP). You various plant events such as direct current (DC) bus event which occurred on September 2011, and the failure of Service Water pump couplings which occurred in 2007. You that the NRC's Notice of Violation issued on February 14, 2012, does not adequately serve protect public health and safety in these circumstances where, according to your petition, exists a pervasive and problematic Safety Conscience Work Environment (SCWE) at the Your petition further states that during a recent NRC hosted public meeting, the NRC andlor acknowledged that the reactor vessel at the PNP was one of the most brittle reactor vessels in the On March 12, 2012, the petition manager contacted you via e-mail to describe the process under Section 2.206 of Title 10 of the Code of Federal Regulations and also confirmation for processing your request under 2.206 process. You were also provided opportunity to address the Petition Review Board On March 15, 2012, you provided the petition manager an acknowledgement via e-mail also requested the teleconference details to enable you to address the On March 16, 2012, the PRB met internally to discuss the request for immediate action. PRB denied the petition request for immediate action on the basis that there was no safety concern to the plant, or to the health and safety of the public. You did not provide additional information beyond reference to these events which have been the subject previous NRC inspection activities for which a resolution has been achieved. In general all requested actions in the petition do not have sufficient basis for the NRC to take the enforcement. Therefore, the request to require the escalated enforcement action to PNP and the requested civil penalty were On March 20, 2012, the petition manager contacted you via e-mail to inform you about the decision on your immediate action request. The petition manager also confirmed the date of teleconference to address the PRB by phone and provided the necessary details. On April 2012, you addressed the PRB regarding the Palisades issues listed in your petition. Prior to teleconference, you provided five additional exhibits (Agencywide Documents Access Management System (ADAMS) Accession No. ML 120930709) for consideration supplemental information to the The transcript for this teleconference is publicly available (ADAMS Accession ML 120970603). During the teleconference, you provided your concerns with regard to Reactor Oversight Process (ROP) process and also requested additional actions which described in the table in Enclosure 1. The PRB reviewed your petition, including the and supplements, and found that each of the events described in the petition was identified in various NRC inspection reports for which a resolution had already been This list is provided in Enclosure On May 3, 2012, the PRB met internally and recommended rejecting the petition. The to reject the petition was based on the following T. Saporito -3 The petitioner does not provide any additional information beyond reference to events which have been the subject of the previous NRC inspection activities (see Enclosure 2) for which a resolution has been achieved. In addition, the petitioner does not provide any additional basis for assessing a violation and civil penalty. Additionally, the issue of embrittlement of the PNP reactor vessel has also been reviewed by the NRC staff. On December 7, 2011, the NRC issued an evaluation (ADAMS Accession No. ML 112870050) concluding that the pressurized thermal shock (PTS) screening criteria will not be reached until April 2017. The licensee has options available to address the PTS issue beyond April 2017. Thus, the NRC considers these issues resolved; the petitioner has not provided any additional basis to support his requested actions. In general all the requested actions in the petition do not have sufficient basis for the NRC to take the escalated enforcement because the NRC is already aware of, and has resolved, the issues identified. Therefore, your request to take escalated enforcement action to shutdown PNP and the requested civil penalty is denied. On May 17, 2012, the petition manager informed you via e-mail regarding the initial recommendation of the PRB to reject the petition, and also offered you a second opportunity to address the PRB. On May 17, 2012, you requested written explanation describing in "great detail" about the exact language and the specific reasons for the PRB's initial recommendation. You also requested to address the PRB "in person", with attendance by the full NRC Commission at this meeting. On May 24, 2012, the petition manager provided you the summary of the basis for rejection of the petition and also provided you with the possible date for the second opportunity to address the PRB in person at the NRC headquarters. On May 25, 2012, you provided your availability for a meeting on July 19,2012, which was later confirmed by the petition manager. On June 2, 2012, however, you provided us with your decision to decline a second meeting with the PRB on July 19, 2012. On June 6, 2012, the petition manager acknowledged your withdrawal of this request. The PRB's final determination is to reject your petition for review under the 10 CFR 2.206 process because it does not meet the criteria for review. The table in Enclosure 1 provides the details for rejecting this petition. There are some issues that are outside the 10 CFR 2.206 process, and other issues identified in your petition that have already been the subject of NRC review, for which resolution has been achieved as stated in NRC MD 8.11, Review Process for 10 CFR 2.206 petitions.
==Dear Mr. Saporito:==
T. Saporito -Thank you for bringing these issues to the attention of the NRC. Sincerely, Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 cc: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports Summary of Issues and Petition Review Board Disposition Specific Issue Reference PRB 1. Escalated Petition The PRB rejected this request, since all the issues raised in enforcement action Page 3/8 support of the requested action have been the subject against NRC staff review and evaluation. Therefore it meets Nuclear Plant criteria for rejection as discussed in Management to suspend (MD) 8.11. ! revoke the NRC , license granted to the licensee operation of PNP 2. NRC to issue a Petition The PRB rejected this request, since all the issues raised in notice of violation Page 3/8 support of the requested action have been the subject with a proposed NRC staff review and evaluation. Therefore it meets the
In your letter to the Executive Director for Operations (EDO) of the Nuclear Regulatory Commission (NRC), dated March 1,2012, pursuant to Title 10 of the Code ofFederal Regulations (10 CFR) Section 2.206 of the NRC's regulations, you made the following request for enforcement related action: "Petitioner respectfully requests that the NRC: (1) take escalated enforcement action against the above-captioned licensee(s) and suspend, or revoke the NRC license(s) granted to the licensee for operation of the licensees' Palisades Nuclear Plant in the USA; (2) that the NRC issue a notice of violation with a proposed civil penalty against the licensee in the total amount of $1,000,000.00 (One-Million) dollars; and (3) that the NRC issue a Confirmatory Order requiring the licensee (to take certain and specific actions) and to bring the Palisades Nuclear Plant to a "cold-shutdown" mode of operation until such time as: The licensee completes an lIindependent" Safety Culture Assessment (SCA) to more fully understand and correct the "root-cause" of multiple violations of NRC safety regulations and requirements at the Palisades Nuclear Plant2; and The licensee completes a comprehensive training program of all station maintenance personnel (including supervision) to ensure the all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes a comprehensive training program of all station operations personnel (including supervision) to ensure that all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes an lIindependent" safety-assessment thorough [through] a 3rd party contractor to review all Palisades Nuclear Plant operation and maintenance procedures to ascertain whether the procedures require IIrisk assessment" by licensed operations personnel prior to execution; and The licensee completes IIdestructive" testing and analysis to determine: (1) the extent of embrittlement of the Palisades Nuclear Plant reactor vessel; and (2) whether the nuclear reactor vessel remains in full compliance with NRC safety regulations and requirements under 10 C.F.R. §50; and under other NRC authority." 2 See, NRC February 14. 2012 -Final Significance Determination of Yellow and White Findings with Assessment Follow up and Notice of Violation NRC Inspection Report Nos. 05000255/2011019 and 05000255/2011020 Palisades Nuclear Plant." As the basis for this request, you referenced the NRC Inspection Report 05000255/2011019 and 05000255/2011020 for Palisades Nuclear Plant (PNP). You various plant events such as direct current (DC) bus event which occurred on September 2011, and the failure of Service Water pump couplings which occurred in 2007. You that the NRC's Notice of Violation issued on February 14, 2012, does not adequately serve protect public health and safety in these circumstances where, according to your petition, exists a pervasive and problematic Safety Conscience Work Environment (SCWE) at the Your petition further states that during a recent NRC hosted public meeting, the NRC andlor acknowledged that the reactor vessel at the PNP was one of the most brittle reactor vessels in the On March 12, 2012, the petition manager contacted you via e-mail to describe the process under Section 2.206 of Title 10 of the Code of Federal Regulations and also confirmation for processing your request under 2.206 process. You were also provided opportunity to address the Petition Review Board On March 15, 2012, you provided the petition manager an acknowledgement via e-mail also requested the teleconference details to enable you to address the On March 16, 2012, the PRB met internally to discuss the request for immediate action. PRB denied the petition request for immediate action on the basis that there was no safety concern to the plant, or to the health and safety of the public. You did not provide additional information beyond reference to these events which have been the subject previous NRC inspection activities for which a resolution has been achieved. In general all requested actions in the petition do not have sufficient basis for the NRC to take the enforcement. Therefore, the request to require the escalated enforcement action to PNP and the requested civil penalty were On March 20, 2012, the petition manager contacted you via e-mail to inform you about the decision on your immediate action request. The petition manager also confirmed the date of teleconference to address the PRB by phone and provided the necessary details. On April 2012, you addressed the PRB regarding the Palisades issues listed in your petition. Prior to teleconference, you provided five additional exhibits (Agencywide Documents Access Management System (ADAMS) Accession No. ML 120930709) for consideration supplemental information to the The transcript for this teleconference is publicly available (ADAMS Accession ML 120970603). During the teleconference, you provided your concerns with regard to Reactor Oversight Process (ROP) process and also requested additional actions which described in the table in Enclosure 1. The PRB reviewed your petition, including the and supplements, and found that each of the events described in the petition was identified in various NRC inspection reports for which a resolution had already been This list is provided in Enclosure On May 3, 2012, the PRB met internally and recommended rejecting the petition. The to reject the petition was based on the following The petitioner does not provide any additional information beyond reference to events which have been the subject of the previous NRC inspection activities (see Enclosure 2) for which a resolution has been achieved. In addition, the petitioner does not provide any additional basis for assessing a violation and civil penalty. Additionally, the issue of embrittlement of the PNP reactor vessel has also been reviewed by the NRC staff. On December 7, 2011, the NRC issued an evaluation (ADAMS Accession No. ML 112870050) concluding that the pressurized thermal shock (PTS) screening criteria will not be reached until April 2017. The licensee has options available to address the PTS issue beyond April 2017. Thus, the NRC considers these issues resolved; the petitioner has not provided any additional basis to support his requested actions. In general all the requested actions in the petition do not have sufficient basis for the NRC to take the escalated enforcement because the NRC is already aware of, and has resolved, the issues identified. Therefore, your request to take escalated enforcement action to shutdown PNP and the requested civil penalty is denied. On May 17, 2012, the petition manager informed you via e-mail regarding the initial recommendation of the PRB to reject the petition, and also offered you a second opportunity to address the PRB. On May 17, 2012, you requested written explanation describing in "great detail" about the exact language and the specific reasons for the PRB's initial recommendation. You also requested to address the PRB "in person", with attendance by the full NRC Commission at this meeting. On May 24, 2012, the petition manager provided you the summary of the basis for rejection of the petition and also provided you with the possible date for the second opportunity to address the PRB in person at the NRC headquarters. On May 25, 2012, you provided your availability for a meeting on July 19,2012, which was later confirmed by the petition manager. On June 2, 2012, however, you provided us with your decision to decline a second meeting with the PRB on July 19, 2012. On June 6, 2012, the petition manager acknowledged your withdrawal of this request. The PRB's final determination is to reject your petition for review under the 10 CFR 2.206 process because it does not meet the criteria for review. The table in Enclosure 1 provides the details for rejecting this petition. There are some issues that are outside the 10 CFR 2.206 process, and other issues identified in your petition that have already been the subject of NRC review, for which resolution has been achieved as stated in NRC MD 8.11, Review Process for 10 CFR 2.206 petitions. Thank you for bringing these issues to the attention of the NRC.
 
Sincerely,Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 cc: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports Summary of Issues and Petition Review Board Disposition Specific Issue Reference PRB 1. Escalated Petition The PRB rejected this request, since all the issues raised in enforcement action Page 3/8 support of the requested action have been the subject against NRC staff review and evaluation. Therefore it meets Nuclear Plant criteria for rejection as discussed in Management to suspend (MD) 8.11. ! revoke the NRC , license granted to the licensee operation of PNP 2. NRC to issue a Petition The PRB rejected this request, since all the issues raised in notice of violation Page 3/8 support of the requested action have been the subject with a proposed NRC staff review and evaluation. Therefore it meets the
* penalty against the . Transcript-criteria for rejection as discussed in MD 8 licensee in the 4/2/12 Page Million amount of 3. NRC to issue a Petition The PRB rejected this request, since all the issues raised in Confirmatory Order Page 3/8 support of the requested action have been the subject requiring NRC staff review and evaluation. Therefore it meets licensee to criteria for rejection as discussed in MD specific actions bring PNP down to mode of until a number requested specified in take The PRB rejected this request, since all the issues raised in complete an 4. The licensee to Petition support of the requested action have been the subject Independent Page 3/8 NRC staff review and evaluation. Therefore it meets Culture criteria for rejection as discussed in MD 8.11. On January 11, 2012, at the regulatory conference for the DC breaker event the licensee stated that a third party safety culture assessment was initiated. A 95002 Supplemental inspection will consider any safety culture contribution to this event. The PRB rejected this request, since all the issues raised in complete a 5. The licensee to Petition support of the requested action have been the subject Page 3/8 NRC staff review and evaluation (see enclosure training program
* penalty against the . Transcript-criteria for rejection as discussed in MD 8 licensee in the 4/2/12 Page Million amount of 3. NRC to issue a Petition The PRB rejected this request, since all the issues raised in Confirmatory Order Page 3/8 support of the requested action have been the subject requiring NRC staff review and evaluation. Therefore it meets licensee to criteria for rejection as discussed in MD specific actions bring PNP down to mode of until a number requested specified in take The PRB rejected this request, since all the issues raised in complete an 4. The licensee to Petition support of the requested action have been the subject Independent Page 3/8 NRC staff review and evaluation. Therefore it meets Culture criteria for rejection as discussed in MD 8.11. On January 11, 2012, at the regulatory conference for the DC breaker event the licensee stated that a third party safety culture assessment was initiated. A 95002 Supplemental inspection will consider any safety culture contribution to this event. The PRB rejected this request, since all the issues raised in complete a 5. The licensee to Petition support of the requested action have been the subject Page 3/8 NRC staff review and evaluation (see enclosure training program
* Therefore it meets the criteria for rejection as discussed all station MD Enclosure 1  
* Therefore it meets the criteria for rejection as discussed all station MD Enclosure 1
-Specific Issue
-Specific Issue
* Reference I PRB personnel. 6. The licensee to Petition The PRB rejected this request, since all the issues raised in complete a Page 3/8
* Reference I PRB personnel. 6. The licensee to Petition The PRB rejected this request, since all the issues raised in complete a Page 3/8
Line 32: Line 29:
* NRC staff review and evaluation (see enclosure Therefore it meets the criteria for rejection as discussed in MD 8.11. 8. The licensee to ! Petition The PRB rejected this request for not meeting the criterion complete Page 3/8 in IVID 8.11. The facts provided are not sufficient to support "destructive" testing the statement that the sustained embrittlement is not and analysis of
* NRC staff review and evaluation (see enclosure Therefore it meets the criteria for rejection as discussed in MD 8.11. 8. The licensee to ! Petition The PRB rejected this request for not meeting the criterion complete Page 3/8 in IVID 8.11. The facts provided are not sufficient to support "destructive" testing the statement that the sustained embrittlement is not and analysis of
* compliance with NRC regulations of 10 CFR, Part reactor 9. The petitioner is Petition The PRB rejected this request because it is not a request concerned that the Page 5/8 for enforcement action against the licensee. Therefore, it NRC's Notice of does not meet the first criteria for reviewing petitions under Violation issued on 10 CFR February 14th, does not serve to public health safety at Palisades
* compliance with NRC regulations of 10 CFR, Part reactor 9. The petitioner is Petition The PRB rejected this request because it is not a request concerned that the Page 5/8 for enforcement action against the licensee. Therefore, it NRC's Notice of does not meet the first criteria for reviewing petitions under Violation issued on 10 CFR February 14th, does not serve to public health safety at Palisades
* Plant. 10. The petitioner's The PRB rejected this request because it is not a request concerns were that Transcript 4/2/12 for enforcement action against the licensee. Therefore, it his teleconference does not meet the first criteria for reviewing petitions under with PRB was not Page 15 & 10 CFR noticed and NRC actions do 16 The PRB notes that you were advised via e-mail on April 2, protect public health 2012, that page 10 of MD 8.11, "Review Process for and CFR 2.206 Petitions," states: "If the petitioner chooses to address PRB by telephone, it is not considered a meeting and no public notice is necessary." 11. The petitioner's Transcript -I The PRB rejected this request because it is not a request concern is with 4/2/12 -* for enforcement action against the licensee. Therefore, it ..does not meet the first criteria for reviewing petitions under Reactor Oversight I Pages 17 & 10 CFR 2.206. However, the PRB referred this to the Process (ROP) 43 I which he believes to Office of the Ins ector General OIG. I  
* Plant. 10. The petitioner's The PRB rejected this request because it is not a request concerns were that Transcript 4/2/12 for enforcement action against the licensee. Therefore, it his teleconference does not meet the first criteria for reviewing petitions under with PRB was not Page 15 & 10 CFR noticed and NRC actions do 16 The PRB notes that you were advised via e-mail on April 2, protect public health 2012, that page 10 of MD 8.11, "Review Process for and CFR 2.206 Petitions," states: "If the petitioner chooses to address PRB by telephone, it is not considered a meeting and no public notice is necessary." 11. The petitioner's Transcript -I The PRB rejected this request because it is not a request concern is with 4/2/12 -* for enforcement action against the licensee. Therefore, it ..does not meet the first criteria for reviewing petitions under Reactor Oversight I Pages 17 & 10 CFR 2.206. However, the PRB referred this to the Process (ROP) 43 I which he believes to Office of the Ins ector General OIG. I
-Specific Issue Reference PRB Disposition Raised be a reactive process, rather than a proactive process and that it is because of failure of NRC's regulatory framework for ROP that resulted at least in part to the serious nuclear safety violations at the Palisades Nuclear Plant. 12. The petitioner Transcript The PRB rejected this request because it is not a request would like the PRB 4/2/12 for enforcement action against the licensee. Therefore, it and IG to make a Page 21 does not meet the first criteria for reviewing petitions under special note of Mr. 10 CFR 2.206. However, the PRB referred this to the Mcintyre's Office of the Inspector General. comments referenced in the transcript. 13. The petitioner Transcript The PRB rejected this request because it is not a request made the statement 4/2/12 for enforcement action against the licensee. Therefore, it that regulators and Page 26 does not meet the first criteria for reviewing petitions under reactor operators 10 CFR 2.206. However, the PRB referred this to the have loosened or Office of the Inspector General. bent the rules. The petitioner further states, 'They're just trying to get more and more out of these plants." 14. The petitioner Transcript The PRB rejected this request because the Reactor requests that the 4/2/12 Oversight Process provides for licensee performance NRC must review Page 40 assessment on a continuing basis through mid-cycle and the entirety of the end-of-cycle assessments and an Action Matrix of licensee's history of responses from the NRC. An assessment of safety culture violations over the is provided through crosscutting issues defined in Chapter years, significant 0310 of the NRC Inspection Manual. In addition, past and serious performance is a consideration in determining traditional violations of NRC escalated enforcement actions. regulations and requirements during  
-Specific Issue Reference PRB Disposition Raised be a reactive process, rather than a proactive process and that it is because of failure of NRC's regulatory framework for ROP that resulted at least in part to the serious nuclear safety violations at the Palisades Nuclear Plant. 12. The petitioner Transcript The PRB rejected this request because it is not a request would like the PRB 4/2/12 for enforcement action against the licensee. Therefore, it and IG to make a Page 21 does not meet the first criteria for reviewing petitions under special note of Mr. 10 CFR 2.206. However, the PRB referred this to the Mcintyre's Office of the Inspector General. comments referenced in the transcript. 13. The petitioner Transcript The PRB rejected this request because it is not a request made the statement 4/2/12 for enforcement action against the licensee. Therefore, it that regulators and Page 26 does not meet the first criteria for reviewing petitions under reactor operators 10 CFR 2.206. However, the PRB referred this to the have loosened or Office of the Inspector General. bent the rules. The petitioner further states, 'They're just trying to get more and more out of these plants." 14. The petitioner Transcript The PRB rejected this request because the Reactor requests that the 4/2/12 Oversight Process provides for licensee performance NRC must review Page 40 assessment on a continuing basis through mid-cycle and the entirety of the end-of-cycle assessments and an Action Matrix of licensee's history of responses from the NRC. An assessment of safety culture violations over the is provided through crosscutting issues defined in Chapter years, significant 0310 of the NRC Inspection Manual. In addition, past and serious performance is a consideration in determining traditional violations of NRC escalated enforcement actions. regulations and requirements during
-4 Specific Issue Reference PRB licensed operations . at the Palisades
-4 Specific Issue Reference PRB licensed operations . at the Palisades
* Nuclear Plant. 15. The petitioner is The PRB rejected this request because it is not a request not satisfied with the Transcript 4/2/12 for enforcement action against the licensee. Therefore, it enforcement of Page 41 does not meet the first criteria for reviewing petitions under fines. He feels that 10 CFR in comparison other Palisades was given the i monetary fines. 16. The petitioner is Transcript The PRB rejected this request because the petitioner does requesting profiling 4/2/12 not provide sufficient facts that constitute bases for of each Page 42 action as required by the criteria under 10 CFR 17. The petitioner is The PRB rejected this request because the also stressing Transcript request is not a process established by regulation NRC should 4/2/12 Page 47 would lead to an enforcement action against the licensee. outside of the box in Therefore, it does not meet the criteria for reviewing light of petitions under 10 CFR Fukushima List of Inspection Reports In the teleconference with the PRB the petitioner cited various plant events (see transcript April 2, 2012 (Agencywide Documents Access and Management System (ADAMS) No. ML Following is the list of inspection reports associated with the On Page 30 of the transcript, reference is made to the order issued to Entergy Operations, Inc. for the operator leaving the controls. The document has inspection number January 25, EA-11-214 (Accession No. ML
* Nuclear Plant. 15. The petitioner is The PRB rejected this request because it is not a request not satisfied with the Transcript 4/2/12 for enforcement action against the licensee. Therefore, it enforcement of Page 41 does not meet the first criteria for reviewing petitions under fines. He feels that 10 CFR in comparison other Palisades was given the i monetary fines. 16. The petitioner is Transcript The PRB rejected this request because the petitioner does requesting profiling 4/2/12 not provide sufficient facts that constitute bases for of each Page 42 action as required by the criteria under 10 CFR 17. The petitioner is The PRB rejected this request because the also stressing Transcript request is not a process established by regulation NRC should 4/2/12 Page 47 would lead to an enforcement action against the licensee. outside of the box in Therefore, it does not meet the criteria for reviewing light of petitions under 10 CFR Fukushima List of Inspection Reports In the teleconference with the PRB the petitioner cited various plant events (see transcript April 2, 2012 (Agencywide Documents Access and Management System (ADAMS) No. ML Following is the list of inspection reports associated with the On Page 30 of the transcript, reference is made to the order issued to Entergy Operations, Inc. for the operator leaving the controls. The document has inspection number January 25, EA-11-214 (Accession No. ML SUBJECT: CONFIRMATORY ORDER (EFFECTIVE (NRC INSPECTION REPORT NO. 05000255/2011015 AND NRC OFFICE INVESTIGATIONS REPORT NO. PALISADES NUCLEAR On pages 30-31 of the transcript, reference is made to the auxiliary feedwater pump finding documented in inspection report January EA-11-227 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF WHITE FINDING ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 31 of the transcript, reference is made to the spent fuel pool WHITE issued in inspection report January 20, EA-09-269 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE NOTIFICATION OF FOLLOW-UP ASSESSMENT; AND NOTICE VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 32 of the transcript, reference is made to the radiological exposure WHITE finding inspection report numbered January 30, EA-08-322 (Accession No. SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING NOTICE OF VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR Enclosure 2
 
-2 On pages 33-34 of the transcript, reference is made to the DC breaker YELLOW finding inspection report numbered February 14, EA-11-243 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-36 of the transcript, reference is made to the service water (SW) pump coupling WHITE finding in inspection report numbered 05000255/2011019 issued February 14, EA-11-243 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-38 of the transcript, reference is made to the significance determination conclusions for both the SW pump P-7C coupling WHITE finding and the DC breaker finding in inspection reports numbered 050002011019 and 2011020 On pages 39 of the transcript, reference is made to the DC breaker YELLOW finding in inspection report numbered 050002011020 timeline or the special inspection team report of event in inspection report November 29, EA-11-243 (Accession No. SUB..IECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011014 PRELIMINARY YELLOW October SUBJECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011012 (Accession No. ML And, the preliminary SW coupling finding was issued in the following November 29, EA-11-241 (Accession No. SUBJECT: PALISADES NUCLEAR PLANT, NRC INSPECTION REPORT PRELIMINARY WHITE T. Saporito Thank you for bringing these issues to the attention of the NRC. Sincerely, IRAI Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 CC: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports DISTRIBUTION: G20120149/EDATS: OEDO-2012-0127 PUBLIC LPL3-1 R/F RidsNrrDorlLpl3-1 Resource RidsNrrPMPalisades Resource RidsNrrDorl Resource RidsNrrOd Resource RidsNrrLABTully Resource RidsNrrMailCenter Resource RidsOiMailCenter Resource RidsEdoMailCenter RidsOeMailCenter Resource RidsRgn3MailCenter Resource RidsOgcRp Resource RidsOcaMailCenter Resource JJandovitz, R3 RidsOpaMaii Resource MBanic, NRR MLemoncelli, OGC AZoulis, NRR DAiley, NRR KRoche, NRR SSheng, NRR DMuller, NRR VGoel. NRR MKeefe, NRR RidsNrrAcrsAcnwMailCTR RLerch, R3 JGiessner, R3 Pack ML12181A2 5 ncommg: ML12065A 1430 Response: ML12173A481 vaemaIIage: 4
SUBJECT: CONFIRMATORY ORDER (EFFECTIVE (NRC INSPECTION REPORT NO. 05000255/2011015 AND NRC OFFICE INVESTIGATIONS REPORT NO. PALISADES NUCLEAR On pages 30-31 of the transcript, reference is made to the auxiliary feedwater pump finding documented in inspection report January EA-11-227 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF WHITE FINDING ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 31 of the transcript, reference is made to the spent fuel pool WHITE issued in inspection report January 20, EA-09-269 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE NOTIFICATION OF FOLLOW-UP ASSESSMENT; AND NOTICE VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 32 of the transcript, reference is made to the radiological exposure WHITE finding inspection report numbered January 30, EA-08-322 (Accession No. SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING NOTICE OF VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR Enclosure 2  
* i OFFICE LPL3-1/PM LPL3-1/LA DElEEEB/BC DRAlAPLNBC DE/EVIB/BC DE/EPNB/BC(A) DRAlAHPB/BC NAME MChawla BTully JAndersen SWeerakkody' SRosenberg ICFairbanks for DAiley UShoop DATE 6/25/12 6/25/12 6/25/12 6/27112 6/28/12 6/28/12 OFFICE OIRSIIOLB/BC OIRSIIPAB/BC OPR/PM RGNIII OGC *NLv l/BC(A) NAME JMcHaie IDAlIsopp RFranovich IRFrahm for MBanic RLerch* MLemoncelii IFrankl AHowe DATE 6/29/12 6/28/12 6/29/12 6/25/12 7/11/12 6/29/12 7/26/12 OFFICIAL RECORD COPY
-2 On pages 33-34 of the transcript, reference is made to the DC breaker YELLOW finding inspection report numbered February 14, EA-11-243 (Accession No. ML
}}
 
SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-36 of the transcript, reference is made to the service water (SW) pump coupling WHITE finding in inspection report numbered 05000255/2011019 issued February 14, EA-11-243 (Accession No. ML
 
SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-38 of the transcript, reference is made to the significance determination conclusions for both the SW pump P-7C coupling WHITE finding and the DC breaker finding in inspection reports numbered 050002011019 and 2011020 On pages 39 of the transcript, reference is made to the DC breaker YELLOW finding in inspection report numbered 050002011020 timeline or the special inspection team report of event in inspection report November 29, EA-11-243 (Accession No. SUB..IECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011014 PRELIMINARY YELLOW October SUBJECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011012 (Accession No. ML And, the preliminary SW coupling finding was issued in the following November 29, EA-11-241 (Accession No. SUBJECT: PALISADES NUCLEAR PLANT, NRC INSPECTION REPORT PRELIMINARY WHITE Thank you for bringing these issues to the attention of the NRC.
 
Sincerely,IRAI Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 CC: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports DISTRIBUTION: G20120149/EDATS: OEDO-2012-0127 PUBLIC LPL3-1 R/F RidsNrrDorlLpl3-1 Resource RidsNrrPMPalisades Resource RidsNrrDorl Resource RidsNrrOd Resource RidsNrrLABTully Resource RidsNrrMailCenter Resource RidsOiMailCenter Resource RidsEdoMailCenter RidsOeMailCenter Resource RidsRgn3MailCenter Resource RidsOgcRp Resource RidsOcaMailCenter Resource JJandovitz, R3 RidsOpaMaii Resource MBanic, NRR MLemoncelli, OGC AZoulis, NRR DAiley, NRR KRoche, NRR SSheng, NRR DMuller, NRR VGoel. NRR MKeefe, NRR RidsNrrAcrsAcnwMailCTR RLerch, R3 JGiessner, R3 Pack ML12181A2 5 ncommg: ML12065A 1430 Response: ML12173A481 vaemaIIage: 4
* i OFFICE LPL3-1/PM LPL3-1/LA DElEEEB/BC DRAlAPLNBC DE/EVIB/BC DE/EPNB/BC(A) DRAlAHPB/BC NAME MChawla BTully JAndersen SWeerakkody' SRosenberg ICFairbanks for DAiley UShoop DATE 6/25/12 6/25/12 6/25/12 6/27112 6/28/12 6/28/12 OFFICE OIRSIIOLB/BC OIRSIIPAB/BC OPR/PM RGNIII OGC *NLv l/BC(A) NAME JMcHaie IDAlIsopp RFranovich IRFrahm for MBanic RLerch* MLemoncelii IFrankl AHowe DATE 6/29/12 6/28/12 6/29/12 6/25/12 7/11/12 6/29/12 7/26/12 OFFICIAL RECORD COPY}}

Revision as of 14:31, 28 March 2018

G20120149/EDATS: OEDO-2012-0127 - Response to Thomas Saporito Ltr. & 2.206 Petition & Email 2.206 - Palisades Nuclear Power Plant
ML12173A481
Person / Time
Site: Palisades Entergy icon.png
Issue date: 07/29/2012
From: Howe A G
Division of Operating Reactor Licensing
To: Saporito T
Saprodani Associates
Chawla M L
Shared Package
ML12181A245 List:
References
TAC ME8112, G20120149, OEDO-2012-0127
Download: ML12173A481 (12)


Text

UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 July 29, 2012 Mr. Thomas Saporito Saprodani Associates 177 US Hwy 1N, Unit 212 Tequesta, Florida 33469 Dear Mr. Saporito: In your letter to the Executive Director for Operations (EDO) of the Nuclear Regulatory Commission (NRC), dated March 1,2012, pursuant to Title 10 of the Code ofFederal Regulations (10 CFR) Section 2.206 of the NRC's regulations, you made the following request for enforcement related action: "Petitioner respectfully requests that the NRC: (1) take escalated enforcement action against the above-captioned licensee(s) and suspend, or revoke the NRC license(s) granted to the licensee for operation of the licensees' Palisades Nuclear Plant in the USA; (2) that the NRC issue a notice of violation with a proposed civil penalty against the licensee in the total amount of $1,000,000.00 (One-Million) dollars; and (3) that the NRC issue a Confirmatory Order requiring the licensee (to take certain and specific actions) and to bring the Palisades Nuclear Plant to a "cold-shutdown" mode of operation until such time as: The licensee completes an lIindependent" Safety Culture Assessment (SCA) to more fully understand and correct the "root-cause" of multiple violations of NRC safety regulations and requirements at the Palisades Nuclear Plant2; and The licensee completes a comprehensive training program of all station maintenance personnel (including supervision) to ensure the all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes a comprehensive training program of all station operations personnel (including supervision) to ensure that all licensed activities at the Palisades Nuclear Plant comply with the NRC safety regulations and requirements; and The licensee completes an lIindependent" safety-assessment thorough [through] a 3rd party contractor to review all Palisades Nuclear Plant operation and maintenance procedures to ascertain whether the procedures require IIrisk assessment" by licensed operations personnel prior to execution; and The licensee completes IIdestructive" testing and analysis to determine: (1) the extent of embrittlement of the Palisades Nuclear Plant reactor vessel; and (2) whether the nuclear reactor vessel remains in full compliance with NRC safety regulations and requirements under 10 C.F.R. §50; and under other NRC authority." 2 See, NRC February 14. 2012 -Final Significance Determination of Yellow and White Findings with Assessment Follow up and Notice of Violation NRC Inspection Report Nos. 05000255/2011019 and 05000255/2011020 Palisades Nuclear Plant."

T. Saporito As the basis for this request, you referenced the NRC Inspection Report 05000255/2011019 and 05000255/2011020 for Palisades Nuclear Plant (PNP). You various plant events such as direct current (DC) bus event which occurred on September 2011, and the failure of Service Water pump couplings which occurred in 2007. You that the NRC's Notice of Violation issued on February 14, 2012, does not adequately serve protect public health and safety in these circumstances where, according to your petition, exists a pervasive and problematic Safety Conscience Work Environment (SCWE) at the Your petition further states that during a recent NRC hosted public meeting, the NRC andlor acknowledged that the reactor vessel at the PNP was one of the most brittle reactor vessels in the On March 12, 2012, the petition manager contacted you via e-mail to describe the process under Section 2.206 of Title 10 of the Code of Federal Regulations and also confirmation for processing your request under 2.206 process. You were also provided opportunity to address the Petition Review Board On March 15, 2012, you provided the petition manager an acknowledgement via e-mail also requested the teleconference details to enable you to address the On March 16, 2012, the PRB met internally to discuss the request for immediate action. PRB denied the petition request for immediate action on the basis that there was no safety concern to the plant, or to the health and safety of the public. You did not provide additional information beyond reference to these events which have been the subject previous NRC inspection activities for which a resolution has been achieved. In general all requested actions in the petition do not have sufficient basis for the NRC to take the enforcement. Therefore, the request to require the escalated enforcement action to PNP and the requested civil penalty were On March 20, 2012, the petition manager contacted you via e-mail to inform you about the decision on your immediate action request. The petition manager also confirmed the date of teleconference to address the PRB by phone and provided the necessary details. On April 2012, you addressed the PRB regarding the Palisades issues listed in your petition. Prior to teleconference, you provided five additional exhibits (Agencywide Documents Access Management System (ADAMS) Accession No. ML 120930709) for consideration supplemental information to the The transcript for this teleconference is publicly available (ADAMS Accession ML 120970603). During the teleconference, you provided your concerns with regard to Reactor Oversight Process (ROP) process and also requested additional actions which described in the table in Enclosure 1. The PRB reviewed your petition, including the and supplements, and found that each of the events described in the petition was identified in various NRC inspection reports for which a resolution had already been This list is provided in Enclosure On May 3, 2012, the PRB met internally and recommended rejecting the petition. The to reject the petition was based on the following T. Saporito -3 The petitioner does not provide any additional information beyond reference to events which have been the subject of the previous NRC inspection activities (see Enclosure 2) for which a resolution has been achieved. In addition, the petitioner does not provide any additional basis for assessing a violation and civil penalty. Additionally, the issue of embrittlement of the PNP reactor vessel has also been reviewed by the NRC staff. On December 7, 2011, the NRC issued an evaluation (ADAMS Accession No. ML 112870050) concluding that the pressurized thermal shock (PTS) screening criteria will not be reached until April 2017. The licensee has options available to address the PTS issue beyond April 2017. Thus, the NRC considers these issues resolved; the petitioner has not provided any additional basis to support his requested actions. In general all the requested actions in the petition do not have sufficient basis for the NRC to take the escalated enforcement because the NRC is already aware of, and has resolved, the issues identified. Therefore, your request to take escalated enforcement action to shutdown PNP and the requested civil penalty is denied. On May 17, 2012, the petition manager informed you via e-mail regarding the initial recommendation of the PRB to reject the petition, and also offered you a second opportunity to address the PRB. On May 17, 2012, you requested written explanation describing in "great detail" about the exact language and the specific reasons for the PRB's initial recommendation. You also requested to address the PRB "in person", with attendance by the full NRC Commission at this meeting. On May 24, 2012, the petition manager provided you the summary of the basis for rejection of the petition and also provided you with the possible date for the second opportunity to address the PRB in person at the NRC headquarters. On May 25, 2012, you provided your availability for a meeting on July 19,2012, which was later confirmed by the petition manager. On June 2, 2012, however, you provided us with your decision to decline a second meeting with the PRB on July 19, 2012. On June 6, 2012, the petition manager acknowledged your withdrawal of this request. The PRB's final determination is to reject your petition for review under the 10 CFR 2.206 process because it does not meet the criteria for review. The table in Enclosure 1 provides the details for rejecting this petition. There are some issues that are outside the 10 CFR 2.206 process, and other issues identified in your petition that have already been the subject of NRC review, for which resolution has been achieved as stated in NRC MD 8.11, Review Process for 10 CFR 2.206 petitions.

T. Saporito -Thank you for bringing these issues to the attention of the NRC. Sincerely, Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 cc: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports Summary of Issues and Petition Review Board Disposition Specific Issue Reference PRB 1. Escalated Petition The PRB rejected this request, since all the issues raised in enforcement action Page 3/8 support of the requested action have been the subject against NRC staff review and evaluation. Therefore it meets Nuclear Plant criteria for rejection as discussed in Management to suspend (MD) 8.11. ! revoke the NRC , license granted to the licensee operation of PNP 2. NRC to issue a Petition The PRB rejected this request, since all the issues raised in notice of violation Page 3/8 support of the requested action have been the subject with a proposed NRC staff review and evaluation. Therefore it meets the

  • penalty against the . Transcript-criteria for rejection as discussed in MD 8 licensee in the 4/2/12 Page Million amount of 3. NRC to issue a Petition The PRB rejected this request, since all the issues raised in Confirmatory Order Page 3/8 support of the requested action have been the subject requiring NRC staff review and evaluation. Therefore it meets licensee to criteria for rejection as discussed in MD specific actions bring PNP down to mode of until a number requested specified in take The PRB rejected this request, since all the issues raised in complete an 4. The licensee to Petition support of the requested action have been the subject Independent Page 3/8 NRC staff review and evaluation. Therefore it meets Culture criteria for rejection as discussed in MD 8.11. On January 11, 2012, at the regulatory conference for the DC breaker event the licensee stated that a third party safety culture assessment was initiated. A 95002 Supplemental inspection will consider any safety culture contribution to this event. The PRB rejected this request, since all the issues raised in complete a 5. The licensee to Petition support of the requested action have been the subject Page 3/8 NRC staff review and evaluation (see enclosure training program
  • Therefore it meets the criteria for rejection as discussed all station MD Enclosure 1

-Specific Issue

  • Reference I PRB personnel. 6. The licensee to Petition The PRB rejected this request, since all the issues raised in complete a Page 3/8
  • support of the requested action have been the subject NRC staff review and evaluation (see enclosure 2). training program of Therefore it meets the criteria for rejection as discussed in all station operations
  • I MD 8.11. personnel. 7. The licensee to Petition The PRB rejected this request, since all the issues raised in complete an Page 3/8 support of the requested action have been the subject independent
  • NRC staff review and evaluation (see enclosure Therefore it meets the criteria for rejection as discussed in MD 8.11. 8. The licensee to ! Petition The PRB rejected this request for not meeting the criterion complete Page 3/8 in IVID 8.11. The facts provided are not sufficient to support "destructive" testing the statement that the sustained embrittlement is not and analysis of
  • compliance with NRC regulations of 10 CFR, Part reactor 9. The petitioner is Petition The PRB rejected this request because it is not a request concerned that the Page 5/8 for enforcement action against the licensee. Therefore, it NRC's Notice of does not meet the first criteria for reviewing petitions under Violation issued on 10 CFR February 14th, does not serve to public health safety at Palisades
  • Plant. 10. The petitioner's The PRB rejected this request because it is not a request concerns were that Transcript 4/2/12 for enforcement action against the licensee. Therefore, it his teleconference does not meet the first criteria for reviewing petitions under with PRB was not Page 15 & 10 CFR noticed and NRC actions do 16 The PRB notes that you were advised via e-mail on April 2, protect public health 2012, that page 10 of MD 8.11, "Review Process for and CFR 2.206 Petitions," states: "If the petitioner chooses to address PRB by telephone, it is not considered a meeting and no public notice is necessary." 11. The petitioner's Transcript -I The PRB rejected this request because it is not a request concern is with 4/2/12 -* for enforcement action against the licensee. Therefore, it ..does not meet the first criteria for reviewing petitions under Reactor Oversight I Pages 17 & 10 CFR 2.206. However, the PRB referred this to the Process (ROP) 43 I which he believes to Office of the Ins ector General OIG. I

-Specific Issue Reference PRB Disposition Raised be a reactive process, rather than a proactive process and that it is because of failure of NRC's regulatory framework for ROP that resulted at least in part to the serious nuclear safety violations at the Palisades Nuclear Plant. 12. The petitioner Transcript The PRB rejected this request because it is not a request would like the PRB 4/2/12 for enforcement action against the licensee. Therefore, it and IG to make a Page 21 does not meet the first criteria for reviewing petitions under special note of Mr. 10 CFR 2.206. However, the PRB referred this to the Mcintyre's Office of the Inspector General. comments referenced in the transcript. 13. The petitioner Transcript The PRB rejected this request because it is not a request made the statement 4/2/12 for enforcement action against the licensee. Therefore, it that regulators and Page 26 does not meet the first criteria for reviewing petitions under reactor operators 10 CFR 2.206. However, the PRB referred this to the have loosened or Office of the Inspector General. bent the rules. The petitioner further states, 'They're just trying to get more and more out of these plants." 14. The petitioner Transcript The PRB rejected this request because the Reactor requests that the 4/2/12 Oversight Process provides for licensee performance NRC must review Page 40 assessment on a continuing basis through mid-cycle and the entirety of the end-of-cycle assessments and an Action Matrix of licensee's history of responses from the NRC. An assessment of safety culture violations over the is provided through crosscutting issues defined in Chapter years, significant 0310 of the NRC Inspection Manual. In addition, past and serious performance is a consideration in determining traditional violations of NRC escalated enforcement actions. regulations and requirements during

-4 Specific Issue Reference PRB licensed operations . at the Palisades

  • Nuclear Plant. 15. The petitioner is The PRB rejected this request because it is not a request not satisfied with the Transcript 4/2/12 for enforcement action against the licensee. Therefore, it enforcement of Page 41 does not meet the first criteria for reviewing petitions under fines. He feels that 10 CFR in comparison other Palisades was given the i monetary fines. 16. The petitioner is Transcript The PRB rejected this request because the petitioner does requesting profiling 4/2/12 not provide sufficient facts that constitute bases for of each Page 42 action as required by the criteria under 10 CFR 17. The petitioner is The PRB rejected this request because the also stressing Transcript request is not a process established by regulation NRC should 4/2/12 Page 47 would lead to an enforcement action against the licensee. outside of the box in Therefore, it does not meet the criteria for reviewing light of petitions under 10 CFR Fukushima List of Inspection Reports In the teleconference with the PRB the petitioner cited various plant events (see transcript April 2, 2012 (Agencywide Documents Access and Management System (ADAMS) No. ML Following is the list of inspection reports associated with the On Page 30 of the transcript, reference is made to the order issued to Entergy Operations, Inc. for the operator leaving the controls. The document has inspection number January 25, EA-11-214 (Accession No. ML SUBJECT: CONFIRMATORY ORDER (EFFECTIVE (NRC INSPECTION REPORT NO. 05000255/2011015 AND NRC OFFICE INVESTIGATIONS REPORT NO. PALISADES NUCLEAR On pages 30-31 of the transcript, reference is made to the auxiliary feedwater pump finding documented in inspection report January EA-11-227 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF WHITE FINDING ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 31 of the transcript, reference is made to the spent fuel pool WHITE issued in inspection report January 20, EA-09-269 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE NOTIFICATION OF FOLLOW-UP ASSESSMENT; AND NOTICE VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR On pages 32 of the transcript, reference is made to the radiological exposure WHITE finding inspection report numbered January 30, EA-08-322 (Accession No. SUBJECT: FINAL SIGNIFICANCE DETERMINATION FOR A WHITE FINDING NOTICE OF VIOLATION; NRC INSPECTION REPORT NO. PALISADES NUCLEAR Enclosure 2

-2 On pages 33-34 of the transcript, reference is made to the DC breaker YELLOW finding inspection report numbered February 14, EA-11-243 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-36 of the transcript, reference is made to the service water (SW) pump coupling WHITE finding in inspection report numbered 05000255/2011019 issued February 14, EA-11-243 (Accession No. ML SUBJECT: FINAL SIGNIFICANCE DETERMINATION OF YELLOW AND WHITE WITH ASSESSMENT FOLLOWUP AND NOTICE OF NRC INSPECTION REPORT NOS. 05000255/2011019 AND PALISADES NUCLEAR On pages 35-38 of the transcript, reference is made to the significance determination conclusions for both the SW pump P-7C coupling WHITE finding and the DC breaker finding in inspection reports numbered 050002011019 and 2011020 On pages 39 of the transcript, reference is made to the DC breaker YELLOW finding in inspection report numbered 050002011020 timeline or the special inspection team report of event in inspection report November 29, EA-11-243 (Accession No. SUB..IECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011014 PRELIMINARY YELLOW October SUBJECT: PALISADES NUCLEAR PLANT -NRC SPECIAL INSPECTION TEAM REPORT 05000255/2011012 (Accession No. ML And, the preliminary SW coupling finding was issued in the following November 29, EA-11-241 (Accession No. SUBJECT: PALISADES NUCLEAR PLANT, NRC INSPECTION REPORT PRELIMINARY WHITE T. Saporito Thank you for bringing these issues to the attention of the NRC. Sincerely, IRAI Allen Howe, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-255 CC: Distribution via Listserv Enclosure 1: Summary of Issues and PRB Disposition Enclosure 2: List of Inspection Reports DISTRIBUTION: G20120149/EDATS: OEDO-2012-0127 PUBLIC LPL3-1 R/F RidsNrrDorlLpl3-1 Resource RidsNrrPMPalisades Resource RidsNrrDorl Resource RidsNrrOd Resource RidsNrrLABTully Resource RidsNrrMailCenter Resource RidsOiMailCenter Resource RidsEdoMailCenter RidsOeMailCenter Resource RidsRgn3MailCenter Resource RidsOgcRp Resource RidsOcaMailCenter Resource JJandovitz, R3 RidsOpaMaii Resource MBanic, NRR MLemoncelli, OGC AZoulis, NRR DAiley, NRR KRoche, NRR SSheng, NRR DMuller, NRR VGoel. NRR MKeefe, NRR RidsNrrAcrsAcnwMailCTR RLerch, R3 JGiessner, R3 Pack ML12181A2 5 ncommg: ML12065A 1430 Response: ML12173A481 vaemaIIage: 4

  • i OFFICE LPL3-1/PM LPL3-1/LA DElEEEB/BC DRAlAPLNBC DE/EVIB/BC DE/EPNB/BC(A) DRAlAHPB/BC NAME MChawla BTully JAndersen SWeerakkody' SRosenberg ICFairbanks for DAiley UShoop DATE 6/25/12 6/25/12 6/25/12 6/27112 6/28/12 6/28/12 OFFICE OIRSIIOLB/BC OIRSIIPAB/BC OPR/PM RGNIII OGC *NLv l/BC(A) NAME JMcHaie IDAlIsopp RFranovich IRFrahm for MBanic RLerch* MLemoncelii IFrankl AHowe DATE 6/29/12 6/28/12 6/29/12 6/25/12 7/11/12 6/29/12 7/26/12 OFFICIAL RECORD COPY