ML20199F136: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 19: Line 19:
=Text=
=Text=
{{#Wiki_filter:. _ _ _ _ _ _ _ _
{{#Wiki_filter:. _ _ _ _ _ _ _ _
                                                                                                                          _ _ _ _ _ _ _ _ _ .
_ _ _ _ _ _ _ _ _ .
                      ,     <
<
                                        U.S. NUCLEAR REGULATORY COMMISSION
,
                                                        REGION lli
U.S. NUCLEAR REGULATORY COMMISSION
                              Docket Nos.:         50 266, 50 301
REGION lli
                              Licenses No.:               DPR 24, DPR 27
Docket Nos.:
                              Report No:           50-266/97021(DRP): 50 301/97021(DRP)
50 266, 50 301
                              Licensee:             Wisconsin Electric Power Company
Licenses No.:
                              Facility:             Point Beach Nuclear Plant, Units 1 & 2
DPR 24, DPR 27
                              Location:             6612 Nuclear Road
Report No:
                                                    Two Rivers, WI 54241 9516
50-266/97021(DRP): 50 301/97021(DRP)
                              Dates:                       October 21 through November 30,1997
Licensee:
                              Inspectors:         F, Brown, Senior Resident inspector
Wisconsin Electric Power Company
                                                    A. McMurtray, Senior Resident inspector
Facility:
                                                    P. Louden, Resident Inspector
Point Beach Nuclear Plant, Units 1 & 2
                              Approved by:         J. W. McCormick Barger, Chief
Location:
                                                    Reactor Projects Branch 7
6612 Nuclear Road
        _                         ._
Two Rivers, WI 54241 9516
                                                '
Dates:
                9902030069 971222
October 21 through November 30,1997
                PDR ADOCK 05000266
Inspectors:
                0                   PDR
F, Brown, Senior Resident inspector
                                                                                                                        .
A. McMurtray, Senior Resident inspector
, . . .  ..
P. Louden, Resident Inspector
            - -
Approved by:
                        . .
J. W. McCormick Barger, Chief
                                          .
Reactor Projects Branch 7
                                                  .
_
                                                        .
._
                                                                _ _ _ _ _ . - - _ _ - - _ _ - . . - _ . - - - - -
'
9902030069 971222
PDR
ADOCK 05000266
0
PDR
.
, . . .
-
-
.
.
.
.
.
_ _ _ _ _ . - - _ _ - - _ _ - . . - _ . - - - - -
..


        .
.
                                      EXECUTIVE SUMMARY
EXECUTIVE SUMMARY
                            Point Beach Nuclear Plant, Units 1 and 2
Point Beach Nuclear Plant, Units 1 and 2
            NRC Inspection Report No. 50 266/97021(DRP); 50-301/97021(DRP)
NRC Inspection Report No. 50 266/97021(DRP); 50-301/97021(DRP)
This inspection included aspects of licensee operations, engineering, maintenance, and
This inspection included aspects of licensee operations, engineering, maintenance, and
plant support. The report covt,rs a 6 week inspection period by the resident inspectors.
plant support. The report covt,rs a 6 week inspection period by the resident inspectors.
Operations
Operations
*      Good command and control, deliberate conduct of operations, and good procedure
Good command and control, deliberate conduct of operations, and good procedure
        adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.
*
        (Section 01.1)
adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.
*      The facility was operated in a safe manner with a strong safety focus and generally
(Section 01.1)
        conservative operational decisions. Two notable examples were the decision to
The facility was operated in a safe manner with a strong safety focus and generally
        promptly shut down Unit 2 when reactor protection instrumentation test problems
*
        could not be resolved within the allowed time and the decision to delay the startup of
conservative operational decisions. Two notable examples were the decision to
        Unit 1 while a nuclear instrument detector was repaired. (Section 01.2)
promptly shut down Unit 2 when reactor protection instrumentation test problems
*      Prior to unit restart, the inspectors determined that Unit 1 containment cleanliness
could not be resolved within the allowed time and the decision to delay the startup of
        was sufficient to prevent immediate safety concerns; however, the inspectors
Unit 1 while a nuclear instrument detector was repaired. (Section 01.2)
        identified several items, including loose electrical tape, which should not have been
Prior to unit restart, the inspectors determined that Unit 1 containment cleanliness
        present. (Section 02.1)
*
*      The licensee had taken adequate measures to ensure those safety systems
was sufficient to prevent immediate safety concerns; however, the inspectors
        susceptible to freezing during the winter months were protected. Also, the licensee
identified several items, including loose electrical tape, which should not have been
        had taken acceptable actions in addressing concerns with the facade freeze
present. (Section 02.1)
        protection system discussed in a previous inspection report. (Section 02.2)            4
The licensee had taken adequate measures to ensure those safety systems
*
*
        The licensee identified and corrected three examples of the use of inappropriate
susceptible to freezing during the winter months were protected. Also, the licensee
        procedures. The need for numerous other procedure changes was identified by
had taken acceptable actions in addressing concerns with the facade freeze
        operators prior to the use of inappropriate procedures. Despite these problems with
protection system discussed in a previous inspection report. (Section 02.2)
        procedure development and review, the inspectors considered the use of procedures
4
        in Operations to be good. This strong performance was based, in part, on
The licensee identified and corrected three examples of the use of inappropriate
        Operations Department initiatives to ensure that all required procedures were
*
        performed as written, to ensure that activities requiring procedures were performed
procedures. The need for numerous other procedure changes was identified by
        using procedures rather than work plans, and to provide mentors who reinforced the
operators prior to the use of inappropriate procedures. Despite these problems with
        need for procedural control of activities affecting quality. (Section 03.1)
procedure development and review, the inspectors considered the use of procedures
*      Most component cooling water (CCW) syntem normal, abnormal and emergency
in Operations to be good. This strong performance was based, in part, on
        operating procedures were considered appropriate, but the inspectors identified a
Operations Department initiatives to ensure that all required procedures were
        weakness with the failure of the emergency operating procedure to provide positive
performed as written, to ensure that activities requiring procedures were performed
        isolation of nonsafety related CCW flow paths during the containment sump
using procedures rather than work plans, and to provide mentors who reinforced the
        recirculation phase of accident mitigation. This procedure weakness was considered
need for procedural control of activities affecting quality. (Section 03.1)
        one aspect of a iest control violation. (Section 03.2)
Most component cooling water (CCW) syntem normal, abnormal and emergency
*
*
        Operator knowledge of the CCW system and its operation was good Reactor
operating procedures were considered appropriate, but the inspectors identified a
                                                  2
weakness with the failure of the emergency operating procedure to provide positive
                                                                ___
isolation of nonsafety related CCW flow paths during the containment sump
recirculation phase of accident mitigation. This procedure weakness was considered
one aspect of a iest control violation. (Section 03.2)
Operator knowledge of the CCW system and its operation was good Reactor
*
2
_ _ _


                                                                                        _         _-_-
_
          .       .
_ - _ -
        operators were familiar with the CCW system status and the cause for CCW system
.
        annunciators. (Sections 04 & 05)
.
  *      The quality assurance organization's identification and documentation of findings
operators were familiar with the CCW system status and the cause for CCW system
        improved significantly as the result of self critical program level arsessments
annunciators. (Sections 04 & 05)
        performed by the licensee. A self assessment performed by Quality Assurance
The quality assurance organization's identification and documentation of findings
        during this report period noted improvement in some areas but identified the need for
*
        improvement in other areas. The inspectors considered the improvements and the
improved significantly as the result of self critical program level arsessments
        thorought.ess of the current self assessment to be positives. New performance
performed by the licensee. A self assessment performed by Quality Assurance
        indicators for corrective action backlogs were implemented, but prioritization of
during this report period noted improvement in some areas but identified the need for
        condition reports within each organization's backlog was of concern to plant
improvement in other areas. The inspectors considered the improvements and the
        management and the inspectors. (Section 07.1, applicable to all functional areas)
thorought.ess of the current self assessment to be positives. New performance
  *      The licensee committed to develop an Annual Plan which prioritized high-level
indicators for corrective action backlogs were implemented, but prioritization of
        improvement initiatives and commitments to the NRC. This will provide a means for
condition reports within each organization's backlog was of concern to plant
        licensee management to track the status of the improvement initiatives. (Section X2,
management and the inspectors. (Section 07.1, applicable to all functional areas)
        applicable to all functional areas)
The licensee committed to develop an Annual Plan which prioritized high-level
  Maintenance
*
  *
improvement initiatives and commitments to the NRC. This will provide a means for
          No problems were noted during observations of maintenance and surveillance
licensee management to track the status of the improvement initiatives. (Section X2,
          activities involving the Unit 1 feedwater isolation feature and the auxiliary feedwater,
applicable to all functional areas)
          safety injection, and residual heat removal systems. (Section M1.1)
Maintenance
  *      An inadequately controlled modification performed in December 1996 defeated the
No problems were noted during observations of maintenance and surveillance
          Unit 1 containment upper hatch interlock system. This caused a Technical
*
          Specification violation when the required compensatory actions were not
activities involving the Unit 1 feedwater isolation feature and the auxiliary feedwater,
          implemented. No instances were identified where containment integrity had been
safety injection, and residual heat removal systems. (Section M1.1)
          degraded during the interlock system inoperability. (Section M2.1)
An inadequately controlled modification performed in December 1996 defeated the
  *
*
          Maintenance supervision effectively responded to problems with maintenance
Unit 1 containment upper hatch interlock system. This caused a Technical
          procedures for the CCW pump and motor repairs, inadequacies in the work scoping
Specification violation when the required compensatory actions were not
          process and insufficient lead time following procedure development con'ributed to
implemented. No instances were identified where containment integrity had been
          the procedure problems. (Section M3.1)
degraded during the interlock system inoperability. (Section M2.1)
  Enaineerina
Maintenance supervision effectively responded to problems with maintenance
  *      The inspectors independently identified that CCW system testing had not
*
          demonstrated the system's ability to provide its safety-related function when
procedures for the CCW pump and motor repairs, inadequacies in the work scoping
          instrument inaccuracies and potential accident condition system lineups were
process and insufficient lead time following procedure development con'ributed to
          considered. The inspectors also determined that four licensee operability
the procedure problems. (Section M3.1)
          determinations for these problems generated between December 1996 and
Enaineerina
          November 1997, were inadequate. The licensee developed an adequate operability
The inspectors independently identified that CCW system testing had not
          determination after the inspectors brought this issue to the attention of plant
*
          management. Two violations were identified. (Section E1.1)
demonstrated the system's ability to provide its safety-related function when
    *
instrument inaccuracies and potential accident condition system lineups were
          A system engineer identified the potential for an unreviewed safety question if a test
considered. The inspectors also determined that four licensee operability
          of spare ventilation equipment, committed to in a Licensee Event Report, was
determinations for these problems generated between December 1996 and
November 1997, were inadequate. The licensee developed an adequate operability
determination after the inspectors brought this issue to the attention of plant
management. Two violations were identified. (Section E1.1)
A system engineer identified the potential for an unreviewed safety question if a test
*
of spare ventilation equipment, committed to in a Licensee Event Report, was
performed at power. This identification was the result of a comprehensive and
-
-
          performed at power. This identification was the result of a comprehensive and                .
.
                                                  3
3


                  ..      .                                      .
,
,
                -
..
          .
.
        thorough review of the proposed test by the system engineer. (Section E2.1)
.
  Plant Support
-
  -
.
        The radiological housekeeping within the P mary Auxiliary Building was good.
thorough review of the proposed test by the system engineer. (Section E2.1)
        (Section R1)
Plant Support
                                                          4
The radiological housekeeping within the P mary Auxiliary Building was good.
                                            --__-_____- .
-
(Section R1)
4
--__-_____- .


                                                                                            . _ _ _ _
. _ _ _ _
          .
-
                  -
.
                                          8tport Details
8tport Details
  Summarv of Plant Status
Summarv of Plant Status
  Unit 2 was at full power and Unit 1 was in an extended outage at the start of the inspection
Unit 2 was at full power and Unit 1 was in an extended outage at the start of the inspection
  perled. Tw: unit operation was precluded due to previously identified concems with the
perled. Tw: unit operation was precluded due to previously identified concems with the
  auxiliary feedwater system. Unit 2 was shutdown on November 15,1997, after the licensee
auxiliary feedwater system. Unit 2 was shutdown on November 15,1997, after the licensee
  identified that complete testing of reactor protection system instrumentation and control
identified that complete testing of reactor protection system instrumentation and control
  circuitry had not been completed as required by T/Ss. Unit i startup was underway at the
circuitry had not been completed as required by T/Ss. Unit i startup was underway at the
  end of the Inspection period.
end of the Inspection period.
  Inspection Focus
Inspection Focus
  During this inspection period, the inspectors integrated a vertical slice review of the
During this inspection period, the inspectors integrated a vertical slice review of the
  component cooling water (CCW) system into the routine inspection of the Operations,
component cooling water (CCW) system into the routine inspection of the Operations,
  Engineering, and Maintenance functional areas,
Engineering, and Maintenance functional areas,
                                            l. Operations
l. Operations
  01     Conduct of Operations
01
  01.1 Shutdown and Startuo Activities
Conduct of Operations
    a.     Insoection Scope (Inspection Procedure (IP) 71707)
01.1 Shutdown and Startuo Activities
          The inspectors observed the T/S-required shutdown of Unit 2 on November 15,
a.
          1997, and the startup of Unit 1 which began November 21,1997, and was
Insoection Scope (Inspection Procedure (IP) 71707)
          completed November 30,1997.
The inspectors observed the T/S-required shutdown of Unit 2 on November 15,
    b.     Observations and Findinas
1997, and the startup of Unit 1 which began November 21,1997, and was
                                                                                                      i
completed November 30,1997.
          Shutdown of Unit 2
b.
          During a review of NRC Generic Lette- N 01," Testing of Safety Related Logic
Observations and Findinas
i
Shutdown of Unit 2
During a review of NRC Generic Lette- N 01," Testing of Safety Related Logic
Circuits," licensee engineering staff k wiled that multiple permissive logic circuitry
<
<
          Circuits," licensee engineering staff k wiled that multiple permissive logic circuitry
had not been tested in accordance v -
          had not been tested in accordance v - T/S requirements. Technical Specification
T/S requirements. Technical Specification
          Table 15.4.11 Item 45 identifies these permissives and the required f4quency of
Table 15.4.11 Item 45 identifies these permissives and the required f4quency of
          testing (every refueling outage). The engineering review identified that these
testing (every refueling outage). The engineering review identified that these
          combination logic tests had not been performed and a Condition Report (CR) 97-
combination logic tests had not been performed and a Condition Report (CR) 97-
            3786, dated November 14,1997, was written.
3786, dated November 14,1997, was written.
          A 24 hour delay was allowed by T/Ss to accomplish the missed surveillance, but the
A 24 hour delay was allowed by T/Ss to accomplish the missed surveillance, but the
            licensee determined that an acceptable procedure likely could not be written,
licensee determined that an acceptable procedure likely could not be written,
            approved, and implemented within the 24-hour time limit Consequently, the
approved, and implemented within the 24-hour time limit Consequently, the
            Ucensee decided at 11:30 a.m. on November 15 to shut down the unit.
Ucensee decided at 11:30 a.m. on November 15 to shut down the unit.
            Once the decision was made to shut down, the T/S action statement of Table 15.3.5-
Once the decision was made to shut down, the T/S action statement of Table 15.3.5-
                                                  5
5


                                                      _
_
                                                              - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _
      .
.
      2 went into effect, requiring the unit to be in Hot Shutdown within 8 hours. The
2 went into effect, requiring the unit to be in Hot Shutdown within 8 hours. The
      licensee subsequently provided an event notification to the NRC Operations Office at
licensee subsequently provided an event notification to the NRC Operations Office at
      1:25 p.m. in accordance with 10 CFR 50.72(b)(1)(1)(A) and (b)(2)(iii)(A).
1:25 p.m. in accordance with 10 CFR 50.72(b)(1)(1)(A) and (b)(2)(iii)(A).
      The inspectors observed the Manager's Supervisory Staff (onsite review committee)
The inspectors observed the Manager's Supervisory Staff (onsite review committee)
      meetings which led to the decision to shut down Unit 2, and noted that senior plant
meetings which led to the decision to shut down Unit 2, and noted that senior plant
      management consistently queried plant staff to ensure that they were not pressing
management consistently queried plant staff to ensure that they were not pressing
      too hard for a desired result and being too production focused. The inspectors
too hard for a desired result and being too production focused. The inspectors
      concluded that the decision to shutdown Unit 2 was conservative and appropriate for
concluded that the decision to shutdown Unit 2 was conservative and appropriate for
      the situation.
the situation.
      The inspecturs observed control room activities during the shutdown of the Unit 2
The inspecturs observed control room activities during the shutdown of the Unit 2
      reactor. The shutdown was methodically conducted, and control room command
reactor. The shutdown was methodically conducted, and control room command
      and control was adequate. Ono delay in the direct shutting down of the unit
and control was adequate. Ono delay in the direct shutting down of the unit
      occurred during the testing of the Unit 2 main steam isolation valves (MSIVs).
occurred during the testing of the Unit 2 main steam isolation valves (MSIVs).
      Operations elected to perform the non required test to gather information for
Operations elected to perform the non required test to gather information for
      engineering trending. During the shutdown, just prior to starting the test, a control
engineering trending. During the shutdown, just prior to starting the test, a control
      (reactor) operator noted that an initial condition for the test was that the reactor be
(reactor) operator noted that an initial condition for the test was that the reactor be
      between 2 percent and 5 percent power. The reactor at the time was at about 1.5
between 2 percent and 5 percent power. The reactor at the time was at about 1.5
      percent. Operations department supervision decided to increase reactor power to
percent. Operations department supervision decided to increase reactor power to
      within the band indicated in the procedure and continue with the test. Other minor
within the band indicated in the procedure and continue with the test. Other minor
      delays occurred during the testing of the 'A' MSIV. The result of these test
delays occurred during the testing of the 'A' MSIV. The result of these test
      decisions led to the reactor reacning hot shutdown status at 7:00 p.m. on November
decisions led to the reactor reacning hot shutdown status at 7:00 p.m. on November
      15,1997,30 minutes prior to the required limit and 1 hour later th:n had the testing
15,1997,30 minutes prior to the required limit and 1 hour later th:n had the testing
      not been conducted.
not been conducted.
                                                                                                                            I
I
      Startuo of Unit 1
Startuo of Unit 1
      The inspectors performed extensive control room observations during the startup of
The inspectors performed extensive control room observations during the startup of
      Unit 1. Good use of procedures and good command and control were noted. No
Unit 1. Good use of procedures and good command and control were noted. No
      negative observations were identified.
negative observations were identified.
c.   Conclusions
c.
      Good command and control, deliberate conduct of operations, and good procedure
Conclusions
      adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.
Good command and control, deliberate conduct of operations, and good procedure
adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.
01.2 Safety Focus in Operational Decision Makina
01.2 Safety Focus in Operational Decision Makina
a.   Inspection Scope
a.
      The inspectors monitored operation of the facility to assess whether an appropriate
Inspection Scope
      safety focus was maintained.
The inspectors monitored operation of the facility to assess whether an appropriate
b.   Observations and Findinai
safety focus was maintained.
      The inspectors observed an appropriate safety focus in the operation of the facility,
b.
      most notably in the decision to promptly shut down Unit 2 when it was determined
Observations and Findinai
                                                6
The inspectors observed an appropriate safety focus in the operation of the facility,
most notably in the decision to promptly shut down Unit 2 when it was determined
6


I               ,
I
                      .
.
              that the instrumentation test problems discussed in Section 01.1 could not be
,
              resolved, within the allowed time, to plant management's satisfaction. The deelslon
that the instrumentation test problems discussed in Section 01.1 could not be
              to delay startup while an intermediate range nuclear instrumentation detector was
resolved, within the allowed time, to plant management's satisfaction. The deelslon
              repaired was another example of conservative decision making, in that the T/3
to delay startup while an intermediate range nuclear instrumentation detector was
              allowed startup with only one operable detector.
repaired was another example of conservative decision making, in that the T/3
              Four examples of operational decisions which were not consistent with the normally
allowed startup with only one operable detector.
              strong safety focus were noted by the inspectors. None of these decisions had a
Four examples of operational decisions which were not consistent with the normally
              direct impact on the safe operation of the facility. Multiple equipment failures or
strong safety focus were noted by the inspectors. None of these decisions had a
              human errors would have been required while these decisions were in effect for
direct impact on the safe operation of the facility. Multiple equipment failures or
              there to have been an impact on the safe operation of the facility,
human errors would have been required while these decisions were in effect for
              The first decision was to perform the MSIV maintenance diagnostic test during a T/S
there to have been an impact on the safe operation of the facility,
              required shutdown, which resulted in the unit remaining critical approximately an
The first decision was to perform the MSIV maintenance diagnostic test during a T/S
              hour longer than necessary (as discussed in Section 01.1). Following this
required shutdown, which resulted in the unit remaining critical approximately an
              shutdown, the operations manager directed that a new procedure be written to
hour longer than necessary (as discussed in Section 01.1). Following this
              ensure that T/S required shutdowns were not delayed by the performance of optional
shutdown, the operations manager directed that a new procedure be written to
              testing.
ensure that T/S required shutdowns were not delayed by the performance of optional
              The second decision involved restart of Unit 1 with an inoperable upper containment
testing.
              personnel hatch interlock. While allowed by the T/Ss, this decision resulted in
The second decision involved restart of Unit 1 with an inoperable upper containment
              reliance on manual action rather than automatic action to prevent defeat of the
personnel hatch interlock. While allowed by the T/Ss, this decision resulted in
              personnel hatch should use of the hatch be required during an emergency. A new
reliance on manual action rather than automatic action to prevent defeat of the
              procedure was written to help ensure proper operation of the hatch.
personnel hatch should use of the hatch be required during an emergency. A new
              The third decision involved performing repairs to Unit 1 control room annunciators.
procedure was written to help ensure proper operation of the hatch.
              Shortly before pressurizing and heating up the plant, plant staff identified that an
The third decision involved performing repairs to Unit 1 control room annunciators.
              outage of annunciator panel 10-03 would be required to repair a degraded resistor.
Shortly before pressurizing and heating up the plant, plant staff identified that an
                                                                                  _
outage of annunciator panel 10-03 would be required to repair a degraded resistor.
              The outage removed 122 annunciator windows from service. The required repair
The outage removed 122 annunciator windows from service. The required repair
              could have been performed prior to exiting cold shutdown conditions, but it was nnt.
_
              The licensee established appropriate administrative controls for the annunciator
could have been performed prior to exiting cold shutdown conditions, but it was nnt.
              outage. The inspectors observed the outage, which lasted approximately 1% hours,-
The licensee established appropriate administrative controls for the annunciator
              and did not note any performance problems.
outage. The inspectors observed the outage, which lasted approximately 1% hours,-
              The fourth decision involved relying on an analysis to demonstrate Unit 1 CCW
and did not note any performance problems.
              system operability rather than performing a test to confirm proper system alignment
The fourth decision involved relying on an analysis to demonstrate Unit 1 CCW
              and operation. This issue is discussed in more detail in E1.1.
system operability rather than performing a test to confirm proper system alignment
          b.   Conclusions
and operation. This issue is discussed in more detail in E1.1.
              The facility was operated in a safe mannei with a strong safety focus and generally
b.
                conservative operational decisions.
Conclusions
        02     Operational Status of Facilities and Equipment
The facility was operated in a safe mannei with a strong safety focus and generally
  --
conservative operational decisions.
        -02M Unit 1 Containment Walkdown
02
                                                      7--
Operational Status of Facilities and Equipment
    ..
--
                                      ..   ..   .
-02M Unit 1 Containment Walkdown
                                                                                    _ _ - _ _
7--
..
..
..
.
_ _ - _ _


. - _ _ _ _ _ _ _ _ - _ _ - _ _ _ - _ _ _ _ _ - _ _                                 ________   -__-_____- _ _-_ ___________ _________- ___-- - - - _ _ -_-
. - _ _ _ _ _ _ _ _ - _ _ - _ _ _ - _ _ _ _ _ - _ _
                                                                  <
________
                                                            .
-__-_____- _ _-_ ___________ _________- ___-- - - - _ _
                                                    a.   Inspection Scope
-_-
                                                          The inspectors performed a walkdown of the Unit 1 containment. This walkdown
<
                                                          was performed after licensee management's containment walkdown but prior to final
.
                                                          containment closeout.
a.
                                                    b.   Observations and Findinat
Inspection Scope
                                                          The inspectors verified that equipment stored in containment was appropriately
The inspectors performed a walkdown of the Unit 1 containment. This walkdown
                                                          secured. The general cleanliness of the containment was considered to be
was performed after licensee management's containment walkdown but prior to final
                                                          acceptable in that no immediate or direct challenges to safety related systems or
containment closeout.
                                                          components were observed; however, the inspectors found and removed several
b.
                                                          pieces of loose tape, a broken stay tie, an aerosol can cap, a radiological posting, a
Observations and Findinat
                                                          bottle of leak detection fluid, and some other miscellaneous trash. The total volume
The inspectors verified that equipment stored in containment was appropriately
                                                          and surface area of the removed items was insignificant compared to the available
secured. The general cleanliness of the containment was considered to be
                                                          surface area of the emergency core cooling system sump recirculation strainers.
acceptable in that no immediate or direct challenges to safety related systems or
                                                          The inspectors also noted two pieces of modular reflective insulation unsecured
components were observed; however, the inspectors found and removed several
                                                          within the *B" reactor coolant pump (RCP) cubicle, a spare valve protector for a
pieces of loose tape, a broken stay tie, an aerosol can cap, a radiological posting, a
                                                          portable nitrogen bottle, and about twenty pieces of electrical tape dangling from
bottle of leak detection fluid, and some other miscellaneous trash. The total volume
                                                          electrica: conductors on the containment polar crane. The inspectors informed the
and surface area of the removed items was insignificant compared to the available
                                                          licensee of these observations, and the observed items were subsequently removea
surface area of the emergency core cooling system sump recirculation strainers.
                                                          from the containment by licensee staff .nrior to final containment closeoui. The
The inspectors also noted two pieces of modular reflective insulation unsecured
                                                          electrical tape removed from the polar crane was characterized as being quite old
within the *B" reactor coolant pump (RCP) cubicle, a spare valve protector for a
                                                          and degraded.
portable nitrogen bottle, and about twenty pieces of electrical tape dangling from
                                                    c.   Conclusistni
electrica: conductors on the containment polar crane. The inspectors informed the
                                                          The inspectors determined that Unit 1 containment cleanliness was sufficient to
licensee of these observations, and the observed items were subsequently removea
                                                          prevent immediate 6afety concems; however, the inspectors identified several items,
from the containment by licensee staff .nrior to final containment closeoui. The
                                                          including loose electrical tape, which should not have been present.
electrical tape removed from the polar crane was characterized as being quite old
                                                    02.2 Cold Weather Preparations
and degraded.
                                                    a.   insoection Scoco flP 71714)
c.
                                                          The inspectors reviewed the implementation of the licensee's cold weather
Conclusistni
                                                          preparations and freeze protection program for safety-related systems.
The inspectors determined that Unit 1 containment cleanliness was sufficient to
                                                    b.   Observations ansi Findinos
prevent immediate 6afety concems; however, the inspectors identified several items,
                                                                          _
including loose electrical tape, which should not have been present.
                                                          The inspectors reviewed the licensee's completed surveillances for cold weather
02.2 Cold Weather Preparations
                                                          preparations and performed independent verification checks of selected cold weather
a.
                                                          protection equipment. No problems were identified.
insoection Scoco flP 71714)
                                                          During a previous inspection ' Inspection Report No. 50-266/97003(DRP);
The inspectors reviewed the implementation of the licensee's cold weather
                                                          50 301/97003(DRP)), the inspectors identified concerns with the material condition of
preparations and freeze protection program for safety-related systems.
                                                          the facade freeze protection system and with work orders not receiving the
b.
                                                          appropriate priority to ensure completion before the onset of cold weather. An
Observations ansi Findinos
                                                                                                                                    8
_
The inspectors reviewed the licensee's completed surveillances for cold weather
preparations and performed independent verification checks of selected cold weather
protection equipment. No problems were identified.
During a previous inspection ' Inspection Report No. 50-266/97003(DRP);
50 301/97003(DRP)), the inspectors identified concerns with the material condition of
the facade freeze protection system and with work orders not receiving the
appropriate priority to ensure completion before the onset of cold weather. An
8


                                      .
                    .
                additional concern involved the uncontrolled use of heat lamps in the facades to
                alleviate freeze protection circuitry problems in heat traced lines.
                The inspectors reviewed the licensee's response to these concerns and noted that a
                facade freeze protection improvement initiative was started in June of 1997. The
                maintenance backlog reduction group was given the task to address the freeze
                protection circuitry problems. The major problem involved the functional quality of
                the existing heat tracing coils. To address this problem, new heat tracing wiring and
                leads were installed on much of the facade piping. At the conclusion of the
                inspection period, about 90 percent of the new heat tracing had been installed in the
                facade systems requiring heat tracing. The remaining 10 percent was scheduled to
                  be completed within the next few weeks. The inspectors concluded that the licensee
                  had made acceptable efforts to restore the facade freeze protection system to a
                  reliable functioning status.
                  During this inspection, no heat lamps were in place within the facades and
                  operations department management implemented the use of the station's temporary
                  information tag or temporary modification programs as the formal means to track
    heat lamp usage.                      Also during this inspection period, an NRC Maintenance Rule
                                          Inspection Team identified the failure to consider the facade freeze
                                          protection system to be within the scope of the Maintenance Rule (see
                                          Inspection Report No. 50 266/97025(DRS); 50 301/97025(DRS)).
      c.          Conclusions
                  The licensee had ta'Kon adequate measure to ensure that safety systems susceptible
                  to freezing were protected during the wir ter months. Actions taken to address
                  previous concerns with facade freeze protection system were also acceptable.
    03              Operations Procedures and Documentation
    03.1 Use of Procedures in the Operations Department
      a.          Ln.ipection
                        n              Scoce
                    The inspectors monitoled the facility's control and use of proceduret to ensure
                    compliance with NRC regulations and the T/Ss, and to ensure that activities affecting
                    quality were appropriately planned and executed.
      b.            Observations and Findinas_
                    The inspectors observed good use of procedures by operators in the control room
                    and in the plant. Procedures which could not be performed as written were
                    corrected prior to performance of work: however, the large number of required
                      procedure changes was indicative of the poor past practices regarding procedure
                      development and use.
                      Proactive lmorovements in Ooerations Procedures and Usagg
                                      _                                                                        _
                                                                    9
.
.
  .
.
    .
additional concern involved the uncontrolled use of heat lamps in the facades to
          _ _ _ _ _ - _ _ _ _ _ _ _ _
alleviate freeze protection circuitry problems in heat traced lines.
The inspectors reviewed the licensee's response to these concerns and noted that a
facade freeze protection improvement initiative was started in June of 1997. The
maintenance backlog reduction group was given the task to address the freeze
protection circuitry problems. The major problem involved the functional quality of
the existing heat tracing coils. To address this problem, new heat tracing wiring and
leads were installed on much of the facade piping. At the conclusion of the
inspection period, about 90 percent of the new heat tracing had been installed in the
facade systems requiring heat tracing. The remaining 10 percent was scheduled to
be completed within the next few weeks. The inspectors concluded that the licensee
had made acceptable efforts to restore the facade freeze protection system to a
reliable functioning status.
During this inspection, no heat lamps were in place within the facades and
operations department management implemented the use of the station's temporary
information tag or temporary modification programs as the formal means to track
heat lamp usage.
Also during this inspection period, an NRC Maintenance Rule
Inspection Team identified the failure to consider the facade freeze
protection system to be within the scope of the Maintenance Rule (see
Inspection Report No. 50 266/97025(DRS); 50 301/97025(DRS)).
c.
Conclusions
The licensee had ta'Kon adequate measure to ensure that safety systems susceptible
to freezing were protected during the wir ter months. Actions taken to address
previous concerns with facade freeze protection system were also acceptable.
03
Operations Procedures and Documentation
03.1 Use of Procedures in the Operations Department
Ln.ipection Scoce
a.
n
The inspectors monitoled the facility's control and use of proceduret to ensure
compliance with NRC regulations and the T/Ss, and to ensure that activities affecting
quality were appropriately planned and executed.
b.
Observations and Findinas_
The inspectors observed good use of procedures by operators in the control room
and in the plant. Procedures which could not be performed as written were
corrected prior to performance of work: however, the large number of required
procedure changes was indicative of the poor past practices regarding procedure
development and use.
Proactive lmorovements in Ooerations Procedures and Usagg
_
_
9
.
.
.
_ _ _ _ _ - _ _ _ _ _ _ _ _


  . _ . - . - -             -   __-.-- - - -             .         _.-     .--.             __ _
. _ .
                .
- . - -
                        .
-
                The inspectors discussed the improved procedure usage with tne operations
__-.-- - - -
                manager who informed the inspectors of two initiatives within the operations
.
                department. The inspectors considered these initiatives to be significant. The first
_.-
                initiative involved the reclassification of all operations procedures as ' Continuous
.--.
                Use." This classification dealt with a reported mind set among operators that non.
__
                continuous use procedures did not need to be performed as written. The inspectors
_
                discussed this mind set with the Regulatory Services and Licensing Manager, who
.
                acknowledged that the failure to perform any required procedure as written, unless
.
                authorized by 10 CFR 50.54(x), was inconsistent with NRC requirements ar.d the
The inspectors discussed the improved procedure usage with tne operations
                licensee's Nuclear Power Business Unit, Procedure 1.1.2, *Procedurs Use and
manager who informed the inspectors of two initiatives within the operations
                Adherence." The second initiative involved the conversion of all repetitive use
department. The inspectors considered these initiatives to be significant. The first
                operations work plans to procedures. This initiative reduced the possibility that a
initiative involved the reclassification of all operations procedures as ' Continuous
                work plan would be used to perform activities that the T/Ss required in be
Use." This classification dealt with a reported mind set among operators that non.
                procedurally controlled. The inspectors will monitor the effectiveness of these
continuous use procedures did not need to be performed as written. The inspectors
                operations department initiatives and the use of procedures by other departments
discussed this mind set with the Regulatory Services and Licensing Manager, who
                under the previously opened inspection follow up item (IFI) 50 266/97020-02(DRP);
acknowledged that the failure to perform any required procedure as written, unless
                50 301/97020-02(DRP).
authorized by 10 CFR 50.54(x), was inconsistent with NRC requirements ar.d the
                The inspectors also observed positive examples of another operations department
licensee's Nuclear Power Business Unit, Procedure 1.1.2, *Procedurs Use and
                significant initiative. The experienced contractors mentoring operators in the control
Adherence." The second initiative involved the conversion of all repetitive use
                room were observed to coach plant staff to ensure that activities affecting quality,
operations work plans to procedures. This initiative reduced the possibility that a
                such as troubleshooting a failed control rod drive logic card, were planned and
work plan would be used to perform activities that the T/Ss required in be
                controlled using approved procedures.
procedurally controlled. The inspectors will monitor the effectiveness of these
,              inadeauste Procedure Reviews
operations department initiatives and the use of procedures by other departments
                An operator initiated CR 97 3877 on November 17,1997, to document an
under the previously opened inspection follow up item (IFI) 50 266/97020-02(DRP);
                inadequacy in Surveillance Procedure TS 30," Low Head Safety injection Check
50 301/97020-02(DRP).
                Valve Leakage Test (Cold Shutdown)," Revision 16. Specifically, the procedure
The inspectors also observed positive examples of another operations department
                directed that containment isolation valves be opened, while containment integrity was
significant initiative. The experienced contractors mentoring operators in the control
                in effect, without establishing the appropriate compensatory control of having a
room were observed to coach plant staff to ensure that activities affecting quality,
                dedicated operator stationed at the valve. Another operator initiated CR 97-3870 on
such as troubleshooting a failed control rod drive logic card, were planned and
                November 23,1997, to document an inadequacy with In service Test (IT) 300,
controlled using approved procedures.
                *Feedwater Leakage Check Test Line Valve," Revision 10. This procedure also
inadeauste Procedure Reviews
                directed that a containment isolation valve be opened without specifying the use of a
,
                dedicated operator. On both of these occasions, the involved operators identified the
An operator initiated CR 97 3877 on November 17,1997, to document an
                procedure errors after the valves were opened but before T/S containment integrity
inadequacy in Surveillance Procedure TS 30," Low Head Safety injection Check
                requirements were violated. Work was stopped, the containment isolation valves
Valve Leakage Test (Cold Shutdown)," Revision 16. Specifically, the procedure
                were shut, and the procedures were corrected.
directed that containment isolation valves be opened, while containment integrity was
                The low temperature overpressure protection (LTOP) system actuated on October
in effect, without establishing the appropriate compensatory control of having a
                23,1997, when operators started the Unit 1 "A" RCP using Operating Procedure
dedicated operator stationed at the valve. Another operator initiated CR 97-3870 on
                (OP) 4A, * Filling and Venting Reactor Coolent System,' Revision 44, and OP 48,
November 23,1997, to document an inadequacy with In service Test (IT) 300,
                " Reactor Coolant Pump Operation," Revision 33. This RCP start was unusual in that
*Feedwater Leakage Check Test Line Valve," Revision 10. This procedure also
                it was part of a fill-and vent evolution but the primary system was solid with little
directed that a containment isolation valve be opened without specifying the use of a
                entrained gas. The operating crew anticipated rapid pressure swings when the
dedicated operator. On both of these occasions, the involved operators identified the
                                                            10
procedure errors after the valves were opened but before T/S containment integrity
                                                                                                      _ - - _ .
requirements were violated. Work was stopped, the containment isolation valves
                                                                        . -      .
were shut, and the procedures were corrected.
The low temperature overpressure protection (LTOP) system actuated on October
23,1997, when operators started the Unit 1 "A" RCP using Operating Procedure
(OP) 4A, * Filling and Venting Reactor Coolent System,' Revision 44, and OP 48,
" Reactor Coolant Pump Operation," Revision 33. This RCP start was unusual in that
it was part of a fill-and vent evolution but the primary system was solid with little
entrained gas. The operating crew anticipated rapid pressure swings when the
10
. -
.
_ - - _ .


    _._
_._
              .
.
                      .
.
L
L
)             pump was started, so the control operator made large and rapid changes to the
)
              chcmical and volume control system (CVCS) letdown and charging controls.
pump was started, so the control operator made large and rapid changes to the
              Because of the lack of entrained gas in the primary system, the system induced
chcmical and volume control system (CVCS) letdown and charging controls.
              pressure transient was insignificant. The manipulation of the CVCS controls resulted
Because of the lack of entrained gas in the primary system, the system induced
              in en overfilling transient which was terminated by the operator's actions and the
pressure transient was insignificant. The manipulation of the CVCS controls resulted
              LTOP a:tuation. The October 23,1997, LTOP event was the second time that a
in en overfilling transient which was terminated by the operator's actions and the
              RCP had been started during fill and venting of a solid, de-gassed primary system.
LTOP a:tuation. The October 23,1997, LTOP event was the second time that a
RCP had been started during fill and venting of a solid, de-gassed primary system.
.
A subsecor't review of data from the first time evolution, in September 1997,
'
'
.            A subsecor't review of data from the first time evolution, in September 1997,
indicateu that an LTOP actJallon had nearly occurred on that occaslon. Procedure
              indicateu that an LTOP actJallon had nearly occurred on that occaslon. Procedure
OP 4B I;ad been changed on August 2,1997, to cover sta . . 4 RCPs in the
              OP 4B I;ad been changed on August 2,1997, to cover stav. . 4 RCPs in the
v
              condtions cescribed above, but this change had not established controls or
condtions cescribed above, but this change had not established controls or
              cor.Wed cautions for the operato,s to prevent the LTOP actuation. Planned
cor.Wed cautions for the operato,s to prevent the LTOP actuation. Planned
              corre.;tive action 6 for the latest event includes additional crew training and revision of
corre.;tive action 6 for the latest event includes additional crew training and revision of
              the procedures.
the procedures.
              The inspectors concluded that the inadequate procedures described above were not
The inspectors concluded that the inadequate procedures described above were not
              indicative of a repetitive problem because of the large number of new procedures
indicative of a repetitive problem because of the large number of new procedures
              and revised procedures which were implemented during this inspection period. The
and revised procedures which were implemented during this inspection period. The
              licensee identified and corrected, non-repetitive inadequacies in IT 300, TS 30, and
licensee identified and corrected, non-repetitive inadequacies in IT 300, TS 30, and
              OP 48 are considered to be examples of a non-citeo violation
OP 48 are considered to be examples of a non-citeo violation
              (NCV 5F266/97021-01(DRP); 50 301/9702101(DRP)). In recent insoection periods,
(NCV 5F266/97021-01(DRP); 50 301/9702101(DRP)). In recent insoection periods,
  ,
the insp;,ctors had noted that operators were being relied upon to catch procedure
              the insp;,ctors had noted that operators were being relied upon to catch procedure
,
              errors which should have been corrected during procedure preparation and review.
errors which should have been corrected during procedure preparation and review.
              The events described above indicate the risk associated with continued reliance on
The events described above indicate the risk associated with continued reliance on
              operators to catch procedure problems. The effectiveness of the initiatives to
operators to catch procedure problems. The effectiveness of the initiatives to
              improve procedures and procedure reviews so that less burden is placed on
improve procedures and procedure reviews so that less burden is placed on
              opMators will be monitored under the previously opened IFl 50 266/97020-02(DRP);
opMators will be monitored under the previously opened IFl 50 266/97020-02(DRP);
              50-301/97020 02(DRP),
50-301/97020 02(DRP),
        c.   Conclusions
c.
              The licensee identified and corrected three examples of the use of inappropriate
Conclusions
              procedures. The need for numerous other procedure changes was identified by
The licensee identified and corrected three examples of the use of inappropriate
              operators prior to the use of the procedures. Despite these problems with procedure
procedures. The need for numerous other procedure changes was identified by
              development and review, the inspectors considered the use of procedures in
operators prior to the use of the procedures. Despite these problems with procedure
              operations to be good. This strong performance was based, in part, on operations
development and review, the inspectors considered the use of procedures in
              department initiatives to clarify that all required procedures were to be performed as
operations to be good. This strong performance was based, in part, on operations
              written, to ensure that activities requiring procedures were performed using
department initiatives to clarify that all required procedures were to be performed as
              procedures rather than work plans, and to provide mentors who reinforced the need
written, to ensure that activities requiring procedures were performed using
              for procedural control of activities affecting quality.
procedures rather than work plans, and to provide mentors who reinforced the need
        03.2 Comoonent Coolina Water Procedures
for procedural control of activities affecting quality.
        a,   bsDection ScoDe
03.2 Comoonent Coolina Water Procedures
                The inspectors reviewed normal, abnormal, and emergency operating procedures
a,
                for the CCW system.
bsDection ScoDe
                                                          11
The inspectors reviewed normal, abnormal, and emergency operating procedures
                                                                      --_
for the CCW system.
11
--_


                                      .   . _ .   -           .     . - .       __     -     _
.
        .
. _ .
                .
-
    b. Observations and Findinos
.
      The inspectors reviewed OP 6A, * Operation of Component Cooling System,"
. - .
        Revision 21, and Check List 6A, * Component Cooling, Unit 1,* Revision 22, and did
__
      not identify any signincant issues. The inspectors also reviewed Abnormal Operating
-
        Procedure (AOP) 98, Unit 1,' Component Cooling System Malfunction," Revision 9,
_
  /
.
      and only identified one potential concern. Specifically, Step 6 directed that the CCW
.
      surge tank vent valve, CC.17, be opened if the CCW surge tank level was trending
b.
      lower. Valve CC.17 must be closed (closed system outside of containment) to
Observations and Findinos
      maintain containment integrity because there are not two containment isolation
The inspectors reviewed OP 6A, * Operation of Component Cooling System,"
      valves in the CCW system. The inspectors were concerned that operators
Revision 21, and Check List 6A, * Component Cooling, Unit 1,* Revision 22, and did
      implementing AOP 9B could overlook the impact of opening CC.17 under the stress
not identify any signincant issues. The inspectors also reviewed Abnormal Operating
      of responding to a CCW system failure. The inspectors detennined that this issue
Procedure (AOP) 98, Unit 1,' Component Cooling System Malfunction," Revision 9,
      did not make AOP 9B inadequate, but discussed the concern with the procedure and
/
      tho basic system configuration limitations which affected the procedure, with licensee
and only identified one potential concern. Specifically, Step 6 directed that the CCW
      tranagement.
surge tank vent valve, CC.17, be opened if the CCW surge tank level was trending
        The inspectors reviewed Emergency Operating Procedure (EOP) 0.0, *Redlagnosis,"
lower. Valve CC.17 must be closed (closed system outside of containment) to
      Revision 5, and EOP 1.3, " Transfer to Containment Sump Recirculation," Revision
maintain containment integrity because there are not two containment isolation
        15 to determine whether the CCW system was adequately described and controlled.
valves in the CCW system. The inspectors were concerned that operators
      The inspectors did not identify any concerns with EOP 0.0. However, the inspectors
implementing AOP 9B could overlook the impact of opening CC.17 under the stress
      identified that Step 9, * Establish Desired Component Cooling Lineup," of EOP 1.3 did
of responding to a CCW system failure. The inspectors detennined that this issue
      not establish the same system lineup described in the operability determination (OD)
did not make AOP 9B inadequate, but discussed the concern with the procedure and
      for CR 96-416 (see Section E1.1). Specifically, the inspectors identified that the
tho basic system configuration limitations which affected the procedure, with licensee
      CVCS seal water heat exchanger and the waste gas compressors were not isolated
tranagement.
      by EOP 1.3 but were not considered as flow paths in the OD. The site system
The inspectors reviewed Emergency Operating Procedure (EOP) 0.0, *Redlagnosis,"
      engineers wrote CR 97 3754 and an associated OD to document and address this
Revision 5, and EOP 1.3, " Transfer to Containment Sump Recirculation," Revision
      inspector-identified issue (Section E1.1). The inspectors also identified that EOP
15 to determine whether the CCW system was adequately described and controlled.
      1.3, Step 9e, directed that CCW flow to the CVCS non-regenerative heat exchanger
The inspectors did not identify any concerns with EOP 0.0. However, the inspectors
      be isolated by closing valve 1(2)CC 130 using its pneumatic actuator controller
identified that Step 9, * Establish Desired Component Cooling Lineup," of EOP 1.3 did
      1(2)HC 130. The inspectors noted that 1(2)CC-130 was a fall-open butterfly valve
not establish the same system lineup described in the operability determination (OD)
      and that its pneumatic actuPor was nonsafety related. The inspectors also noted
for CR 96-416 (see Section E1.1). Specifically, the inspectors identified that the
      that there was no direct control board indication of the position status of 1(2)CC-130
CVCS seal water heat exchanger and the waste gas compressors were not isolated
      or direct indication of CCW flow through the CVCS non regenerative heat exchanger.
by EOP 1.3 but were not considered as flow paths in the OD. The site system
      The only available indication for an operator to use in determining whether use of the
engineers wrote CR 97 3754 and an associated OD to document and address this
      pneumatic actuator had achieved the desired results was the CCW system total flow
inspector-identified issue (Section E1.1). The inspectors also identified that EOP
      indicator. The inspectors noted that no quantitative value for flow change as a result
1.3, Step 9e, directed that CCW flow to the CVCS non-regenerative heat exchanger
      of successful closure of 1(2)CC 130 under accident conditions was available to the
be isolated by closing valve 1(2)CC 130 using its pneumatic actuator controller
      operators, and flow changes in the CCW system from completion of Steps 9c
1(2)HC 130. The inspectors noted that 1(2)CC-130 was a fall-open butterfly valve
      (placing a residual heat removal (RHR) heat exchanger in service), 9d (isolating
and that its pneumatic actuPor was nonsafety related. The inspectors also noted
      CCW loads in containment), and paraiset performance by an auxiliary building
that there was no direct control board indication of the position status of 1(2)CC-130
      operator of iso!ating a boric acid evaporator (Attachment A of EOP 1.3) could mask
or direct indication of CCW flow through the CVCS non regenerative heat exchanger.
      the effect of Step 9e. Additionally, if the nonsafety related actuator were to fall open
The only available indication for an operator to use in determining whether use of the
      after completion of Step 9e, there would be no direct indication of CCW system flow
pneumatic actuator had achieved the desired results was the CCW system total flow
      diversion from safety related loads.
indicator. The inspectors noted that no quantitative value for flow change as a result
      The inspectors reviewed the CCW system test procedures and ODs, and concluded
of successful closure of 1(2)CC 130 under accident conditions was available to the
      that the effect of CCW flow diversion through the non regenerative heat exchangers
operators, and flow changes in the CCW system from completion of Steps 9c
                                                12
(placing a residual heat removal (RHR) heat exchanger in service), 9d (isolating
CCW loads in containment), and paraiset performance by an auxiliary building
operator of iso!ating a boric acid evaporator (Attachment A of EOP 1.3) could mask
the effect of Step 9e. Additionally, if the nonsafety related actuator were to fall open
after completion of Step 9e, there would be no direct indication of CCW system flow
diversion from safety related loads.
The inspectors reviewed the CCW system test procedures and ODs, and concluded
that the effect of CCW flow diversion through the non regenerative heat exchangers
12
i
i
.
.


        ,
.
                  .
,
        was not evaluated or bounded, and had the potential to directly affect the mitigation
was not evaluated or bounded, and had the potential to directly affect the mitigation
        of a design basis loss of coolant accident. The non regenerative heat exchanger
of a design basis loss of coolant accident. The non regenerative heat exchanger
        Isolation valve,1(2)CC 7408, was used during performance of CCW system tests to
Isolation valve,1(2)CC 7408, was used during performance of CCW system tests to
        serve the function covered by EOP 13, Step 9e. The weaknesses in controlling _
serve the function covered by EOP 13, Step 9e. The weaknesses in controlling _
        CCW system configuration during accident conditions was a contributing aspect of
CCW system configuration during accident conditions was a contributing aspect of
        the test control inadequacies described in Section E1.1.
the test control inadequacies described in Section E1.1.
  c.   Csnelusions
c.
        Most CCW system normal, abnormal and emergency operating procedures were
Csnelusions
        considered appropriate,- but the inspectors identified weaknesses associated with the
Most CCW system normal, abnormal and emergency operating procedures were
        failure of the EOP to provide for positive isolation of nonsafety related CCW flow
considered appropriate,- but the inspectors identified weaknesses associated with the
        paths during the containment sump recirculation phase of accident mitigation.
failure of the EOP to provide for positive isolation of nonsafety related CCW flow
  04     Operator Knowledge and Performance
paths during the containment sump recirculation phase of accident mitigation.
        The inspectors interviewed several licensed and non licensed operators regarding
04
        the function, design, component makeup, and system interrelationships of the CCW
Operator Knowledge and Performance
        system. All opemtors interviewed displayed a solid fundamental understanding of
The inspectors interviewed several licensed and non licensed operators regarding
        the system and its overall purposes. Control room operators were familiar with the
the function, design, component makeup, and system interrelationships of the CCW
        cause of alllit CCW system annunciators and accurately explained all system
system. All opemtors interviewed displayed a solid fundamental understanding of
          Indications discussed with the inspectors.
the system and its overall purposes. Control room operators were familiar with the
  05     Operator Training and Qualifications
cause of alllit CCW system annunciators and accurately explained all system
        The inspectors reviewed Training Handbook 10,9," Primary Systems Descriptions:
Indications discussed with the inspectors.
        Component Cooling System," Revision 4, and found it to be informative and
05
          accurate. Some of the non licensed operators stated during interviews with the
Operator Training and Qualifications
          inspectors that
The inspectors reviewed Training Handbook 10,9," Primary Systems Descriptions:
          improvements could be made regarding the depth of training they receive on system
Component Cooling System," Revision 4, and found it to be informative and
          interrelationships following initial operator qualifications.
accurate. Some of the non licensed operators stated during interviews with the
  07     Quality Assurance in Operations
inspectors that
  07.1 Imorovements In the Licensee Quality Assurance Function (IP 40500)
improvements could be made regarding the depth of training they receive on system
  a.     Insoection Scope
interrelationships following initial operator qualifications.
          The inspectors performed reviews of some licensee Quality Assurance (QA)
07
          organization uudits, assessments, and CRs to determine the effectiveness of the QA
Quality Assurance in Operations
          function,
07.1 Imorovements In the Licensee Quality Assurance Function (IP 40500)
  b.     Obseivations and Findinas
a.
          The licensee conducted three program-level assessments of the Point Beach QA
Insoection Scope
          organization and function during the last 18 months. The most recent was
The inspectors performed reviews of some licensee Quality Assurance (QA)
          completed in April 1997, and two of the three assessments were conducted by
organization uudits, assessments, and CRs to determine the effectiveness of the QA
          outside contractors. The assessments were critical of the organizational and
function,
b.
Obseivations and Findinas
The licensee conducted three program-level assessments of the Point Beach QA
organization and function during the last 18 months. The most recent was
completed in April 1997, and two of the three assessments were conducted by
outside contractors. The assessments were critical of the organizational and
_
_
                                                    13
13
                                              .
.
                                                      .   .
.
                                                                        . . .
.
.
.
.


_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ .
_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ .
                                                    4
4
                                                  functional performance, and consequently major organizational, personnel, and
functional performance, and consequently major organizational, personnel, and
                                                  staffing changes were implemented. The inspectors noted significant improvement
staffing changes were implemented. The inspectors noted significant improvement
                                                  in the number and quality of QA findings following these changes. The most
in the number and quality of QA findings following these changes. The most
                                                  important QA findings were classified as QA Program Significant issues, and were
important QA findings were classified as QA Program Significant issues, and were
                                                  tracked as separate high level priorities within the licensee work and improvement
tracked as separate high level priorities within the licensee work and improvement
                                                  prioritization process.
prioritization process.
                                                  In addition, the QA orgnizetion performed a self assessment, S A 9719, dated
In addition, the QA orgnizetion performed a self assessment, S A 9719, dated
                                                  November 20,1997, of their performance in implementing corrective actions from the
November 20,1997, of their performance in implementing corrective actions from the
                                                  program level assessments. This self assessment involved the participation of two
program level assessments. This self assessment involved the participation of two
                                                  CA managers from other nuclear power plants. The self assessment acknowledged
CA managers from other nuclear power plants. The self assessment acknowledged
                                                  the improvements noted by the inspectors, and also identified opportunities for
the improvements noted by the inspectors, and also identified opportunities for
                                                  continued improvement, including better training and qualification of OA staff, more
continued improvement, including better training and qualification of OA staff, more
                                                  consistent initiation of CRs, and more time for preparation for performance of audits.
consistent initiation of CRs, and more time for preparation for performance of audits.
                                                  One additional issue in "1e self assessment was that the QA Program Significant
One additional issue in "1e self assessment was that the QA Program Significant
                                                  Issues list was one of ma,iy priority lists in the prioritization process, and that this
Issues list was one of ma,iy priority lists in the prioritization process, and that this
                                                  fact led to uncertainty on the part of line managers as to relative significance (see
fact led to uncertainty on the part of line managers as to relative significance (see
                                                  also Section X2 for discussion of work prioritization issues).
also Section X2 for discussion of work prioritization issues).
                                                  Another positive action observed during this report period was the development of
Another positive action observed during this report period was the development of
                                                  performance indicators for corrective action backlogs in the line organizations. This
performance indicators for corrective action backlogs in the line organizations. This
                                                  action was undertaken to help focus management attention on the CR process. One
action was undertaken to help focus management attention on the CR process. One
                                                  issue that was of concern to the inspectors was the lack of a programmatic process
issue that was of concern to the inspectors was the lack of a programmatic process
                                                  for assigning work priorities within the CR backlog. Plant management had directed
for assigning work priorities within the CR backlog. Plant management had directed
                                                  individual line managers to ensure that CRs were worked in the order of safety
individual line managers to ensure that CRs were worked in the order of safety
                                                  significance, but no process existed to evaluate performance in this stea,
significance, but no process existed to evaluate performance in this stea,
                                            c.   Conclusions
c.
                                                  Performance of the QA organization's identification and documentation of findings
Conclusions
                                                  improved significantly as the '. ssult of self critical, program-level assessments
Performance of the QA organization's identification and documentation of findings
                                                  performed by the licensee. A self assessment performed by QA during this report
improved significantly as the '. ssult of self critical, program-level assessments
                                                  period noted improvement but identified additional areas for improvement. The
performed by the licensee. A self assessment performed by QA during this report
                                                  inspectors considered the improvements and the thoroughness of the current self.
period noted improvement but identified additional areas for improvement. The
                                                  assessment to be positives.
inspectors considered the improvements and the thoroughness of the current self.
                                                  New performance indicators for corrective action backlogs were implemented, but
assessment to be positives.
                                                  prioritization of CRs within each organization's backlog was of concern to plant
New performance indicators for corrective action backlogs were implemented, but
                                                  management.
prioritization of CRs within each organization's backlog was of concern to plant
                                            08     Miscellaneous Operations issues
management.
                                            08.1 [Qlgsed) IFl 50 266/97003-01(DRP): 50 301/97003-01(DRP): Miscellaneous
08
                                                  concerns regarding the facade freeze protection system. The inspectors' follow-up
Miscellaneous Operations issues
                                                  review of these matters is discussed in Section O2.2 of this report. The inspectors'
08.1 [Qlgsed) IFl 50 266/97003-01(DRP): 50 301/97003-01(DRP): Miscellaneous
                                                  original concerns were determined to be adequately addressed.
concerns regarding the facade freeze protection system. The inspectors' follow-up
                                                                                            14
review of these matters is discussed in Section O2.2 of this report. The inspectors'
original concerns were determined to be adequately addressed.
14


                                      _                                    _ - _ _ _ _ _ _ _ _ _ _ - _ - _ .
.
.
                  -
_
        .
_ - _ _ _ _ _ _ _ _ _ _ - _ - _ .
  OS.2 (Closed) Ucensee [ *nt Report (LER) 50 266/95005-00: Manual Reactor Trip
-
        During Startup Physics Testing. On April 15,1995, control rod F-12 dropped into the
.
        Unit 1 core during low power physics testing. Unit 1 was critical below the point of
OS.2 (Closed) Ucensee [ *nt Report (LER) 50 266/95005-00: Manual Reactor Trip
        adding heat at the time. During troubleshooting on April 16,1995, a second control
During Startup Physics Testing. On April 15,1995, control rod F-12 dropped into the
        rod, E 11, dropped part way into the core when the control operator withdrew rods in
Unit 1 core during low power physics testing. Unit 1 was critical below the point of
        control bank A. When the second rod entered the core, the reactor went subcritical.
adding heat at the time. During troubleshooting on April 16,1995, a second control
        The duty shift superAor ordered the reactor manually tripped.
rod, E 11, dropped part way into the core when the control operator withdrew rods in
        The licensee dete. ad that rod E 11 dropped because fuses pulled to facilitate
control bank A. When the second rod entered the core, the reactor went subcritical.
        troubleshooting actN, des on rod F 12 were common to movable gripper coils of both
The duty shift superAor ordered the reactor manually tripped.
        rods. After the manual reactor trip, troubleshooting activities on the F 12 rod
The licensee dete.
        determined that the rod had dropped due to the failure of its stationary gripper coll.
ad that rod E 11 dropped because fuses pulled to facilitate
        The licensee initiated CR 95 255 for this event and performed Root Cause
troubleshooting actN, des on rod F 12 were common to movable gripper coils of both
        Evaluation 9510 since human performance factors contributed to the partial drop of
rods. After the manual reactor trip, troubleshooting activities on the F 12 rod
        E 11. The root cause evaluation determined that there was a miscommunication
determined that the rod had dropped due to the failure of its stationary gripper coll.
        between the instrument and control engineer coordinating F 12 troubleshooting
The licensee initiated CR 95 255 for this event and performed Root Cause
        activities and the reactor engineer and control operator for Unit 1. The root cause
Evaluation 9510 since human performance factors contributed to the partial drop of
        evaluation also determined that inadequate shift tumover and pre job briefs
E 11. The root cause evaluation determined that there was a miscommunication
        contributed to this event.
between the instrument and control engineer coordinating F 12 troubleshooting
        The licensee replaced the failed stationary gripper coil stack and successfully tested
activities and the reactor engineer and control operator for Unit 1. The root cause
        it prior to the subsequent restart of Unit 1. The licensee had an off site laboratory
evaluation also determined that inadequate shift tumover and pre job briefs
        analyze the failure mechanism of the failed stack. The laboratory determined that
contributed to this event.
        the primary contributor to the coil failure was high temperv     ' hat resulted from the
The licensee replaced the failed stationary gripper coil stack and successfully tested
        failure of a control rod drive motor shroud fan damper.1       censee repaired the
it prior to the subsequent restart of Unit 1. The licensee had an off site laboratory
        damper and shroud temperatures remained normal during Unit 1 operation.
analyze the failure mechanism of the failed stack. The laboratory determined that
        Secondary contributors to the coil failure were aging and moisture / boric acid
the primary contributor to the coil failure was high temperv
        intrusion. The licensee subsequently inspected the stationary gripper coil stacks for
' hat resulted from the
          Unit 1 and Unit 2. No problems were identified.
failure of a control rod drive motor shroud fan damper.1
        The inspectors reviewed the root cause evaluation, the CR, the laboratory report,
censee repaired the
          and F 12 troubleshooting, and coil stack replacement work plans. The inspectors
damper and shroud temperatures remained normal during Unit 1 operation.
          had no concerns with any of these activities. The inspectors also noted that recent
Secondary contributors to the coil failure were aging and moisture / boric acid
          improvements in communications during reactivity maneuvers, shift tumovers, and
intrusion. The licensee subsequently inspected the stationary gripper coil stacks for
          pre job briefs should prevent this event from occurring again. The inspectors had no
Unit 1 and Unit 2. No problems were identified.
          additional concerns with this issue.
The inspectors reviewed the root cause evaluation, the CR, the laboratory report,
                                          II. Maintenance
and F 12 troubleshooting, and coil stack replacement work plans. The inspectors
  M1     Conduct of Maintenance
had no concerns with any of these activities. The inspectors also noted that recent
  M1.1 Te9s and Surveillances
improvements in communications during reactivity maneuvers, shift tumovers, and
          NRC Inspection Procedures 62707 & 61726 were used in the inspection of plant
pre job briefs should prevent this event from occurring again. The inspectors had no
                                                  15
additional concerns with this issue.
II. Maintenance
M1
Conduct of Maintenance
M1.1 Te9s and Surveillances
NRC Inspection Procedures 62707 & 61726 were used in the inspection of plant
15


          4       *
*
          maintenance and surveillance activities, The inspectors observed and reviewed
4
          selected ponions of the following tests:
maintenance and surveillance activities, The inspectors observed and reviewed
          *      In service Test Procedure 10A," Test of dectrically Driven Auxiliary Feed
selected ponions of the following tests:
                  Pumps and Valves With Flow to Unit 1 Steam Generators (Quarterly)?
In service Test Procedure 10A," Test of dectrically Driven Auxiliary Feed
                  Revision 1, conducted on November 26,1997.
*
          *      TS Test 45 "Feedwater Isolation Test From a Safety injection Signal Unit 1,"
Pumps and Valves With Flow to Unit 1 Steam Generators (Quarterly)?
                  Revision 0, conducted on November 14,1997.
Revision 1, conducted on November 26,1997.
          *      In service Test Procedure 530A,' Leakage Reduction and Preventive
TS Test 45 "Feedwater Isolation Test From a Safety injection Signal Unit 1,"
                  Maintenance Program Test of the Train A High Head Safety injection and
*
                  Residual Heat Removal Systems Unit 1," Revision 2, conducted on November
Revision 0, conducted on November 14,1997.
                  26,1997.
In service Test Procedure 530A,' Leakage Reduction and Preventive
        The work performed under these activities was professional and thorough.
*
        Technicians were experienced and knowledgeable of their assigned tasks. The work
Maintenance Program Test of the Train A High Head Safety injection and
        packages were present at the job site and actively used by the technicians for all
Residual Heat Removal Systems Unit 1," Revision 2, conducted on November
        work observed. System engineers were frequently observed monitoring job
26,1997.
        progress.
The work performed under these activities was professional and thorough.
  M2     Maintenance and Material Condition of Facilities and Equipment
Technicians were experienced and knowledgeable of their assigned tasks. The work
  M2.1 . Containment Hatch Interlock inocerability
packages were present at the job site and actively used by the technicians for all
  a.   insoection Scope (IPs 62707 & 37551)
work observed. System engineers were frequently observed monitoring job
        The inspectors reviewed the circumstances surrounding the licensee's identification
progress.
        that a gear was missing from the Unit 1 containment upper personnel hatch interlock
M2
        mechanism. The inspectors also reviewed the results of the licensee's root cause
Maintenance and Material Condition of Facilities and Equipment
        investigation into the matter,
M2.1 . Containment Hatch Interlock inocerability
  b,   Observatipns and Findinas
a.
insoection Scope (IPs 62707 & 37551)
The inspectors reviewed the circumstances surrounding the licensee's identification
that a gear was missing from the Unit 1 containment upper personnel hatch interlock
mechanism. The inspectors also reviewed the results of the licensee's root cause
investigation into the matter,
b,
Observatipns and Findinas
'
'
        Maintenance workers identified that a gear was missing from the Unit 1 containment
Maintenance workers identified that a gear was missing from the Unit 1 containment
        upper hatch interlock mechanism while preparing to perform operational checks on
upper hatch interlock mechanism while preparing to perform operational checks on
        the hetch. Condition Report 97-3574 was written to address the defect and to note
the hetch. Condition Report 97-3574 was written to address the defect and to note
        that the absence of the gear inight defeat the interlock system. Licensee
that the absence of the gear inight defeat the interlock system. Licensee
        management requested a root cause evaluation of the missing gear.
management requested a root cause evaluation of the missing gear.
,
,
        Licensee engineering staff verified through field tests that, with the gear missing, the
Licensee engineering staff verified through field tests that, with the gear missing, the
        interlock system could be defeated if the normd lever manipulations for opening the
interlock system could be defeated if the normd lever manipulations for opening the
        hatch doors were not followed. This condition was documented in CR 97-3756.
hatch doors were not followed. This condition was documented in CR 97-3756.
        The licensee's root cause evaluation determined that the gear was removed on
The licensee's root cause evaluation determined that the gear was removed on
        December 28,1996, following an unsuccessful containment hatch leakage test. The
December 28,1996, following an unsuccessful containment hatch leakage test. The
        failure of the test was attributed to a bent remote operator shaft which was causing
failure of the test was attributed to a bent remote operator shaft which was causing
        damage to the quad ring seal. Removing the hatch interlock gear was intended to
damage to the quad ring seal. Removing the hatch interlock gear was intended to
                                                  16
16
l
l
l
l
I
I
l
l
                                    -   - -----     . - - -     ,
- -- -- - .--
.
-
-
- -----
. - - -
,


  _ _ _ _ _                                                     _-_       _ - _ - _ - _ _ _ - - - - - - - - _ .
_ _ _ _
                    '
_
            .
_-_
            eliminate stresses on the seal ring caused by the bent shaft. Removal of the gear
_ - _ - _ - _ _ _ - - - - - - - - _ .
            was not recognized as being a temporary modification to the hatch interlock system;
'
            therefore, the design control process was not used and the proper reviews and
.
            approval of the gear removal were not obtained. The gear was removed under work
eliminate stresses on the seal ring caused by the bent shaft. Removal of the gear
            order 9614237. A station log entry referenced that the hatch was operable based on
was not recognized as being a temporary modification to the hatch interlock system;
            a successful hatch leakage test performed following the removal of the gear. No
therefore, the design control process was not used and the proper reviews and
            post maintenance testing of the hatch interleck was performed.
approval of the gear removal were not obtained. The gear was removed under work
            Unit 1 was at power between December 28,1990, and February 18,1997, with the
order 9614237. A station log entry referenced that the hatch was operable based on
            Unit 1 containment hatch interlock system inoperable. The failure to perform the
a successful hatch leakage test performed following the removal of the gear. No
            required compensatory actions was a Violation (VIO 50-266/97021-02(DRP);
post maintenance testing of the hatch interleck was performed.
            50 301/97021-02(DRP)) of T/S 15.3.6.A.1.d.2. No instances were noted that
Unit 1 was at power between December 28,1990, and February 18,1997, with the
            indicated that the containment ilitegrity for Unit 1 was degraded during this period,
Unit 1 containment hatch interlock system inoperable. The failure to perform the
  c.       Conclusions
required compensatory actions was a Violation (VIO 50-266/97021-02(DRP);
            The licensee inadvertently defeated the Unit 1 containment upper hatch interlock
50 301/97021-02(DRP)) of T/S 15.3.6.A.1.d.2. No instances were noted that
            system by removing a gear from the system without utilizing the appropriate design
indicated that the containment ilitegrity for Unit 1 was degraded during this period,
            control processes for work on safety related components. One T/S violation was
c.
            identified.
Conclusions
  M2.2 Comoonent Cooling _ Water System Walkdowns and Material Con @gn
The licensee inadvertently defeated the Unit 1 containment upper hatch interlock
            The inspectors conducted walkdowns 'the CCW system and saw no obvious
system by removing a gear from the system without utilizing the appropriate design
            material condition problems. The inspectors also reviewed CRs for the CCW
control processes for work on safety related components. One T/S violation was
              system. Many of the CR's identified isolated problems or deficiencies. However,
identified.
            one issue which was noted in several CRs was the unreliability of pressure
M2.2 Comoonent Cooling _ Water System Walkdowns and Material Con @gn
            controllers and level transmitters in the system. The instruments had been
The inspectors conducted walkdowns 'the CCW system and saw no obvious
              frequently found out of tolerance end presented calibration repeatability difficulties.
material condition problems. The inspectors also reviewed CRs for the CCW
            Another issue involved a several year old problem with fluctuations in the CCW
system. Many of the CR's identified isolated problems or deficiencies. However,
,            surge tank level. There were several apnarent contributors to this level fluctuation,
one issue which was noted in several CRs was the unreliability of pressure
              but definitive corrective actions had not been taken. The inspectors concluded that
controllers and level transmitters in the system. The instruments had been
              there was no safety consequence associated with the surge tank level fluctuations.
frequently found out of tolerance end presented calibration repeatability difficulties.
  M2.3 Primarv Auxiliary Buildina (PAB) Boric Acid L.eaks
Another issue involved a several year old problem with fluctuations in the CCW
              During tours of the PAB and the Unit 1 containment, the inspectors observed boric
surge tank level. There were several apnarent contributors to this level fluctuation,
              acid build-up and numerous work order tags on several pieces of safety-related
,
              equipment. Boric acid build-up was present on the mechanical seals for the safety
but definitive corrective actions had not been taken. The inspectors concluded that
              injection (SI) and RHR pumps and body-to-bonnet joints and packing for charging,
there was no safety consequence associated with the surge tank level fluctuations.
              SI, and RHR valves. There were more work order tags and boric acid build up than
M2.3 Primarv Auxiliary Buildina (PAB) Boric Acid L.eaks
              the inspectors had observed during previous tours of the PAB, but the inspectors
During tours of the PAB and the Unit 1 containment, the inspectors observed boric
              had no operability concerns. All observations were discussed with plant
acid build-up and numerous work order tags on several pieces of safety-related
              management.
equipment. Boric acid build-up was present on the mechanical seals for the safety
                                                    17
injection (SI) and RHR pumps and body-to-bonnet joints and packing for charging,
SI, and RHR valves. There were more work order tags and boric acid build up than
the inspectors had observed during previous tours of the PAB, but the inspectors
had no operability concerns. All observations were discussed with plant
management.
17


                                                                                              - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ .
.. ..
.. .. .        .          ..          .
.
              .
.
                        *
..
        M3    Maintenance Procedures and Documentation
.
        M3.1 CCW Pumo Modification
- _ _ _ _ _ _ _ _ _ _ _ _ _ - _ .
        a.   Inspection Scope (IP 62707)
*
              The inspectors reviewed the replacement of the Unit 1 CCW system *B" pump motor
.
              and the overhaul of the pump impeller,
M3
        b.   Observations and Findinas
Maintenance Procedures and Documentation
              The licensee pit.nned to replace the motor for the Unit 1 CCW *B* pump (due tc high
M3.1 CCW Pumo Modification
              vibrations) with the spare pump motor maintained onsite to meet 10 CFR 50,
a.
              Appendix R requirements. Pump impeller overhauls were also planned to be
Inspection Scope (IP 62707)
              performed during the motor replacement.
The inspectors reviewed the replacement of the Unit 1 CCW system *B" pump motor
              After a couple of days of work, the job vlas stopped following requests by the job
and the overhaul of the pump impeller,
              leaders because the procedures being used were cumbersome to implement and
b.
              hard to follow. At one point prior to the work being stopped, maintenance workers
Observations and Findinas
              were referencing three procedures at one time. Maintenance management stopped
The licensee pit.nned to replace the motor for the Unit 1 CCW *B* pump (due tc high
              the work and immediately met with workers to more fully understand the problems
vibrations) with the spare pump motor maintained onsite to meet 10 CFR 50,
              and establish a strategy to address the concerns prior to work recommencing.
Appendix R requirements. Pump impeller overhauls were also planned to be
              The inspectors discussed the circumstances with maintenance personnel and
performed during the motor replacement.
              supervision and determined that the causes for the procedural problems leading to
After a couple of days of work, the job vlas stopped following requests by the job
              the work stoppage included inadequate management guidance regarding the scope
leaders because the procedures being used were cumbersome to implement and
              of the work, and failure to provide enough lead time following procedural
hard to follow. At one point prior to the work being stopped, maintenance workers
              development to allow for a thorough procedure review and walkdown.
were referencing three procedures at one time. Maintenance management stopped
                                                                                                                                ,
the work and immediately met with workers to more fully understand the problems
              Once the work was restarted, it was conducted smoothly and in a timely manner.
and establish a strategy to address the concerns prior to work recommencing.
              The inspectors noted that workers involved with the repairs exerdsed good craft
The inspectors discussed the circumstances with maintenance personnel and
              skills, housekeeping in the work area was tidy, and appropriate tools were used
supervision and determined that the causes for the procedural problems leading to
              during the repairs. However, there were inconsistencies in the manner by which
the work stoppage included inadequate management guidance regarding the scope
              foreign material exclusion areas were established and controlled during the work
of the work, and failure to provide enough lead time following procedural
              suggesting that the intent of the program and/or station procedures were not clearly
development to allow for a thorough procedure review and walkdown.
              understood by the workforce.
,
        c.   Conclusions
Once the work was restarted, it was conducted smoothly and in a timely manner.
              The inspectors concluded that maintenance supervision effectively responded to
The inspectors noted that workers involved with the repairs exerdsed good craft
              problems encountered by workers during the CCW pump and motor repairs.
skills, housekeeping in the work area was tidy, and appropriate tools were used
              Inadequacies in work scoping and insufficient lead time following procedure
during the repairs. However, there were inconsistencies in the manner by which
              devebpment caused the problems.
foreign material exclusion areas were established and controlled during the work
                                                                                                                                  >
suggesting that the intent of the program and/or station procedures were not clearly
                                                      18
understood by the workforce.
c.
Conclusions
The inspectors concluded that maintenance supervision effectively responded to
problems encountered by workers during the CCW pump and motor repairs.
Inadequacies in work scoping and insufficient lead time following procedure
devebpment caused the problems.
>
18


_ ___ _______ __- __________________ ___ - ______ _ -____ - _ ________                                                                 ______ _ __ _______ _ _ -_ _ _
_ ___ _______ __- __________________ ___ - ______ _ -____ - _ ________
                                                                      *
______ _ __ _______ _ _ -_ _ _
                                                                .
*
                                                                                                lll Enn neerina
.
E1                                                         Conduct of Engineering
lll Enn neerina
E1.1                                                       CCW System Testina Inadecuacies
E1
                  a.                                       Inspection Scope UP 3755.)
Conduct of Engineering
                                                            The inspectors reviewed the CCW system test and surveillance procedures to
E1.1
                                                            ensure that the system was tested in a manner which ensured that design basis
CCW System Testina Inadecuacies
                                                            requirements would be met under postulated accident conditions and configurations.
a.
                  b.                                       Qblervations and Findinas
Inspection Scope UP 3755.)
                                                            The inspectors found that identifying design bases requirements for the CCW system
The inspectors reviewed the CCW system test and surveillance procedures to
                                                            was difficult. The T/Ss did not contain any quantitative requirements for the system.
ensure that the system was tested in a manner which ensured that design basis
                                                            The Final Safety Analysis Report (FSAR) provided adequate discussion of some
requirements would be met under postulated accident conditions and configurations.
                                                            design bases information such as containment integrity considerations, but did not
b.
                                                            list required flow rates for all safety related loads and did not reference critical
Qblervations and Findinas
                                                            operational controls such as the need to throttic the CCW system outlet valves from
The inspectors found that identifying design bases requirements for the CCW system
                                                            the RHR heat exchangers to prevent pump run out. The FSAR also provided only
was difficult. The T/Ss did not contain any quantitative requirements for the system.
                                                            one taference to design basis documents for the CCW system. The inspectors
The Final Safety Analysis Report (FSAR) provided adequate discussion of some
                                                            reviewed two recent 10 CFR 50.59 r /aluations: Safety Evaluation 97-183 and Safety
design bases information such as containment integrity considerations, but did not
                                                            Screening 97-1259-01. Neither e'.alu0 tion referenced CCW system current licensing
list required flow rates for all safety related loads and did not reference critical
                                                            basis requirements other than the T/Ss and FSAR. The inspectors did not identify
operational controls such as the need to throttic the CCW system outlet valves from
                                                            any inadequacies in the two evaluations; however, the potential existed to miss
the RHR heat exchangers to prevent pump run out. The FSAR also provided only
                                                            important considerations when modifying the system or system procedures.
one taference to design basis documents for the CCW system. The inspectors
                                                            The CCW system had only a single containment isolation valve on the return lines
reviewed two recent 10 CFR 50.59 r /aluations: Safety Evaluation 97-183 and Safety
                                                            from containment. To compensate for this, the system outside containment was
Screening 97-1259-01. Neither e'.alu0 tion referenced CCW system current licensing
                                                            maintained as closed to the environment. This provided redundancy for the
basis requirements other than the T/Ss and FSAR. The inspectors did not identify
                                                            contait. ment isolatinn function. The inspectors noted that some of the valves relied
any inadequacies in the two evaluations; however, the potential existed to miss
                                                            upon for keeping the system closed outside of containment were known to have
important considerations when modifying the system or system procedures.
                                                            small amounts of seat leakage, but the valves were not included in the periodic valve
The CCW system had only a single containment isolation valve on the return lines
                                                            leak check program, the leak rates were not quantified, and a bounding analysis of
from containment. To compensate for this, the system outside containment was
                                                            acceptable leak rates was not developed. The licensee informed the inspectors that
maintained as closed to the environment. This provided redundancy for the
                                                            this condition had been reviewed and found acceptable within the current licensing
contait. ment isolatinn function. The inspectors noted that some of the valves relied
                                                            basis (CLB). The inspectors will review the acceptability of classifying a system as
upon for keeping the system closed outside of containment were known to have
                                                            closed without performing boundary valve leak checks as an IFl (50-266/97021-
small amounts of seat leakage, but the valves were not included in the periodic valve
                                                            03(DRP); 50 301/9702103(DRP)).
leak check program, the leak rates were not quantified, and a bounding analysis of
                                                            The inspectors reviewed IT 12, " Component Cooling Water Pumps and Valves
acceptable leak rates was not developed. The licensee informed the inspectors that
                                                            (Quarterly)," Revision 12, to determine whether the ability of the CCW system to
this condition had been reviewed and found acceptable within the current licensing
                                                            meet its design bases requirements under accident conditions was adequate!y
basis (CLB). The inspectors will review the acceptability of classifying a system as
                                                            demonstrated. Procedure IT 12 provided testing methodology which satisfied the in
closed without performing boundary valve leak checks as an IFl (50-266/97021-
                                                            service test requirements of TS 15.4.2; however, it did not demonstrate system
03(DRP); 50 301/9702103(DRP)).
                                                            operability relative to safety-related flow and flow distribution. The system
The inspectors reviewed IT 12, " Component Cooling Water Pumps and Valves
                                                            engineering group referred the inspectors to Wisconsin Michigan Test Procedure
(Quarterly)," Revision 12, to determine whether the ability of the CCW system to
                                                                                                        19
meet its design bases requirements under accident conditions was adequate!y
demonstrated. Procedure IT 12 provided testing methodology which satisfied the in
service test requirements of TS 15.4.2; however, it did not demonstrate system
operability relative to safety-related flow and flow distribution. The system
engineering group referred the inspectors to Wisconsin Michigan Test Procedure
19


        '
'
.
.
(WMTP) 12.11,' Component Cooling System Flow Test," Revision 1, performed on
(WMTP) 12.11,' Component Cooling System Flow Test," Revision 1, performed on
Line 855: Line 982:
acceptable test results during performance of PBTP 52. An OD associated with this
acceptable test results during performance of PBTP 52. An OD associated with this
CR stated that sufficient margin existed to allow lowering the required acceptance
CR stated that sufficient margin existed to allow lowering the required acceptance
criteria. This OD wac inadequate in that action was not taken to develop revised
criteria. This OD wac inadequate in that action was not taken to develop revised
acceptance criteria or to change the CLB. On November 4,1997, the inspectors met
acceptance criteria or to change the CLB. On November 4,1997, the inspectors met
with licensee staff and provided specific concems with CCW system bst
with licensee staff and provided specific concems with CCW system bst
methodology and the OD associated with CR 96-416.
methodology and the OD associated with CR 96-416.
On November 11,1997, a licensee engineer wrote CR 97-3754 to document
On November 11,1997, a licensee engineer wrote CR 97-3754 to document
confirmation of the inspectors' finding that two nonsafety-related loads not
confirmation of the inspectors' finding that two nonsafety-related loads not
considered in the OD for CR 96-416 were left in service when following the steps of
considered in the OD for CR 96-416 were left in service when following the steps of
  EOP-1.3 (see Section O3.2). The OD for CR 97-3754 containec a corrective action
EOP-1.3 (see Section O3.2). The OD for CR 97-3754 containec a corrective action
to revise EOP-1.3, prior to Unit 1 start-up, so that the CVCS seal heat exchanger
to revise EOP-1.3, prior to Unit 1 start-up, so that the CVCS seal heat exchanger
and waste gas compressor would be isolated during containment sump recirculation.
and waste gas compressor would be isolated during containment sump recirculation.
  On November 25,1997, a system engineer wrote CR 97-3901 to document that
On November 25,1997, a system engineer wrote CR 97-3901 to document that
  EOP-1.3 had not been revised prior to Unit 1 leaving cold shutdown in the start-up
EOP-1.3 had not been revised prior to Unit 1 leaving cold shutdown in the start-up
  process. The ODs for CRS 97-3754 and 97-3901 both failed to address the lack of
process. The ODs for CRS 97-3754 and 97-3901 both failed to address the lack of
  acceptable test results. On November 25,1997, the inspectors informed the plant
acceptable test results. On November 25,1997, the inspectors informed the plant
  manager and the site vice president of their concerns with the adequacy of the
manager and the site vice president of their concerns with the adequacy of the
  existing ODs for the CCW system. A new OD was completed on November 28,
existing ODs for the CCW system. A new OD was completed on November 28,
  1997, prior to Unit 1 going critical. This OD provided reasonable assurance that the
1997, prior to Unit 1 going critical. This OD provided reasonable assurance that the
  CCW system would perform its design safety functions by taking credit for seasonally
CCW system would perform its design safety functions by taking credit for seasonally
  cool service water system temperatures. The failure to establish an adequate basis
cool service water system temperatures. The failure to establish an adequate basis
  for system operability between December 30,1996, and November 28,1997, was a
for system operability between December 30,1996, and November 28,1997, was a
  violation (50-266/97021-05(DRP); 50-301/97021-05(DRP)) of 10 CFR 50, Appendix
violation (50-266/97021-05(DRP); 50-301/97021-05(DRP)) of 10 CFR 50, Appendix
  B, Criterion XVI, " Corrective Action."
B, Criterion XVI, " Corrective Action."
                                                        20
20
                                  - - - _ _ _ _ _ _ _ _
- - - _ _ _ _ _ _ _ _


                                  _ _ _ _ _   _ _ _ _ -_ ____
_ _ _ _ _
    .
_ _ _ _ -_ ____
              -
-
                                                                                            n
n
  c. Conclusions
.
    The inspectore concluded tnat CCW system testing had not demonstrated the
c.
    system's ability to provide its safety related function when instrument inaccuracies
Conclusions
    and potential accident condition system lineups were considered. The inspectors
The inspectore concluded tnat CCW system testing had not demonstrated the
    3!so determined that four ODs for these problems had been generated between
system's ability to provide its safety related function when instrument inaccuracies
    December 1996 and November 1997, but that these ODs were not E.1 equate. The
and potential accident condition system lineups were considered. The inspectors
    licensee developed an adequate OD after the inspectors brought this issue to the
3!so determined that four ODs for these problems had been generated between
    attention of plant management.
December 1996 and November 1997, but that these ODs were not E.1 equate. The
E2.1 Positive System Enciaeer Performance
licensee developed an adequate OD after the inspectors brought this issue to the
    The licensee committed to test and maintain spare ventilation equipment in
attention of plant management.
    LER 266/97-020-00. While preparing a safety evaluation for the required test, a
E2.1
    system engineer identified that an unreviewed safety question (USQ) would exist if
Positive System Enciaeer Performance
    the test were performed with a unit at power. This issue was identified as the result
The licensee committed to test and maintain spare ventilation equipment in
    of a thorough review of references in the FSAR. The inspectors considered the
LER 266/97-020-00. While preparing a safety evaluation for the required test, a
    performance of the extensive research required to identify this potential USQ to be a
system engineer identified that an unreviewed safety question (USQ) would exist if
    positive.
the test were performed with a unit at power. This issue was identified as the result
E4   Engineering Staff Knowledge and Performance
of a thorough review of references in the FSAR. The inspectors considered the
    The inspectors found system engineers to be knowledgeable of their systems in
performance of the extensive research required to identify this potential USQ to be a
    most cases. However, during the course of the CCW system inspection, the
positive.
    inspectors requested information on the operation of valve 1(2)CC-130. During
E4
    subsequent discussion between the inspectors anO the system engineer for the CCW
Engineering Staff Knowledge and Performance
    system, the system engineer stated that valve 1(2)CC-130 was a fail-closed valve.
The inspectors found system engineers to be knowledgeable of their systems in
    The inspectors questioned this conclusion based on field observation of the valve
most cases. However, during the course of the CCW system inspection, the
      actuator arrangement. Additionally, check list 6A contained a note which stated that
inspectors requested information on the operation of valve 1(2)CC-130. During
    valve 1(2)CC-130 was gagged to prevent CCW pump run out should the valve fail.
subsequent discussion between the inspectors anO the system engineer for the CCW
      ihe difference between a fail-open and fail-closed valve was also significant
system, the system engineer stated that valve 1(2)CC-130 was a fail-closed valve.
      because of potential CCW flow diversion under accident conditions (see Section
The inspectors questioned this conclusion based on field observation of the valve
      O3.2). The system engineer later informed the inspectors that valve 1(2)CC-130
actuator arrangement. Additionally, check list 6A contained a note which stated that
      was a fail-open. The system engineer wrote a CR which indicated that the vender
valve 1(2)CC-130 was gagged to prevent CCW pump run out should the valve fail.
      information for the valve was incorrect. The inspectors considered the system
ihe difference between a fail-open and fail-closed valve was also significant
      engineer's lack of familiarity with the as-installed method of operation of the valve
because of potential CCW flow diversion under accident conditions (see Section
      actuator to be a weakness.
O3.2). The system engineer later informed the inspectors that valve 1(2)CC-130
                                            IV, Plant Support
was a fail-open. The system engineer wrote a CR which indicated that the vender
R1   Radiological Protection and Chemistry (RP&C) Controls (IP 71750)
information for the valve was incorrect. The inspectors considered the system
      During the inspection period the inspectors frequently entered the PAB to conduct
engineer's lack of familiarity with the as-installed method of operation of the valve
      housekeeping inspections and surveillances observations. Generally, radiological
actuator to be a weakness.
      housekeeping was good. However, during an inspection on November 25,1997, the
IV, Plant Support
      inspectors identified that a piece of drain tubing associated with Unit 1 Leakage
R1
      Reduction and Preventive Maintenance Program tests was dripping a small amount
Radiological Protection and Chemistry (RP&C) Controls (IP 71750)
      of reactor coolant onto the floor of the #2 pipeway within the PAB. The inspectors
During the inspection period the inspectors frequently entered the PAB to conduct
                                                                21
housekeeping inspections and surveillances observations. Generally, radiological
                . _ _ - _ _ _ _ .
housekeeping was good. However, during an inspection on November 25,1997, the
inspectors identified that a piece of drain tubing associated with Unit 1 Leakage
Reduction and Preventive Maintenance Program tests was dripping a small amount
of reactor coolant onto the floor of the #2 pipeway within the PAB. The inspectors
21
. _ _ - _ _ _ _ .


    ___                           ._ _ _ - _ - _ - _ _ _ _ _ _ _ _ _ - - - - - - - _ _ - - .
___
            .
._
          informed operations and health physics personnel of the condition and it was
_ _ - _ - _ - _ _ _ _ _ _ _ _ _ - - - - - - - _ _ - - .
          appropriately addressed,
.
informed operations and health physics personnel of the condition and it was
appropriately addressed,
i
i
                                                                                              22
22
  .
.
        .-             _ _ _ _ . _
.-
_ _ _ _ . _


                              - _ _ _ _ - _ _ _ _ - _ - _ _ _ _
- _ _ _ _ - _ _ _ _ - _ - _ _ _ _
                          -
-
                      .
.
                                                                V. Manaaement Meetinas
V. Manaaement Meetinas
          X1         Exit Meeting Summary
X1
          The inspectors presented the inspection results to members of licensee management at the
Exit Meeting Summary
          conclusion of the inspection on December 2,1997. The licensee acknowledged the findings
The inspectors presented the inspection results to members of licensee management at the
          presented.
conclusion of the inspection on December 2,1997. The licensee acknowledged the findings
          The insoectors asked the licensee whether any materials examined during the inspection
presented.
,          should be considered proprietary. No proprietary information was identified.
The insoectors asked the licensee whether any materials examined during the inspection
            X2       Management Meeting Summary
should be considered proprietary. No proprietary information was identified.
          A public meeting with the licensee was held on October 29,1997, in Manitowoc. Wisconsin.
,
            Licensee senior management provided the NRC Point Beach Oversight Panel with the
X2
            current status of improvement initiatives. Individual managers described the review and
Management Meeting Summary
            approval process for ensuring that Unit 1 was ready to be restarted. Planned improvements
A public meeting with the licensee was held on October 29,1997, in Manitowoc. Wisconsin.
            in the work planning process were also discussed in detail. The NRC was also told that an
Licensee senior management provided the NRC Point Beach Oversight Panel with the
            Operating Plan for 1998 was being developed. This plan will prioritize licensee initiatives
current status of improvement initiatives. Individual managers described the review and
            and commitments to the NRC, such as development of comprehensive current licensing
approval process for ensuring that Unit 1 was ready to be restarted. Planned improvements
            bases documents. It will also provide a means for licensee management to track the status
in the work planning process were also discussed in detail. The NRC was also told that an
            of the improvement initiatives. The NRC welcomed this initiative because the prioritization
Operating Plan for 1998 was being developed. This plan will prioritize licensee initiatives
            tools in place, the QA Program Significant issues Listing, the Level 1 Report, the Plan for
and commitments to the NRC, such as development of comprehensive current licensing
            Achievement of Operational Excellence, and the corrective action program Significant
bases documents. It will also provide a means for licensee management to track the status
            Conditions Adverse to Quality allidentified appropriate information but did not appear to be
of the improvement initiatives. The NRC welcomed this initiative because the prioritization
              integrated.
tools in place, the QA Program Significant issues Listing, the Level 1 Report, the Plan for
                                                                          23
Achievement of Operational Excellence, and the corrective action program Significant
  _ _ - _ _ - _ _ _
Conditions Adverse to Quality allidentified appropriate information but did not appear to be
integrated.
23
_ _ - _ _ - _ _ _


                                                                  . _ _ _ _
. _ _ _ _
              .. .   ='
.. .
                                PARTIAL LIST OF PERSONS CONTACTED
= '
      . Wisconsin Electric Power Comoany
PARTIAL LIST OF PERSONS CONTACTED
      S. A.- Patuiski, Site Vice President
. Wisconsin Electric Power Comoany
      A. J. Cayla, Plant Manager
S. A.- Patuiski, Site Vice President
    . R. G. Mende, Operations Manager
A. J. Cayla, Plant Manager
      W. B. Fromm, Maintenance Manager
. R. G. Mende, Operations Manager
      .J. G. Schweitzer, Site Engineering Manager
W. B. Fromm, Maintenance Manager
      P. B. Tindall, Health Physics Manager
.J. G. Schweitzer, Site Engineering Manager
                            _
P. B. Tindall, Health Physics Manager
      D. F. Johnson, Regulatory Services and Licensing Manager
D. F. Johnson, Regulatory Services and Licensing Manager
                                                                            'l
_
                                                              -
'l
                                                              __
-
                                                  24
__
24
.. .
.. .
          _
_


                                        _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -_
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -_
        .
*
              *
.
                          ' INSPECTION PROCEDURES USED
' INSPECTION PROCEDURES USED
IP 37551:     Onsite Engineering
IP 37551:
IP 40500:     Effectiveness of Licensee Controls in Identifying, Resolving, and Preventing
Onsite Engineering
              Problems
IP 40500:
IP 61726:     Surveillance Observations
Effectiveness of Licensee Controls in Identifying, Resolving, and Preventing
IP 62707:     Maintenance Observation
Problems
IP 71707:     Plant Operations
IP 61726:
IP 71714:     Cold Weather Preparations
Surveillance Observations
IP 71750:     Plant Support Activities
IP 62707:
                        ITEMS GPENED, CLOSED, AND DISCUSSED
Maintenance Observation
Opened
IP 71707:
50-266/97021-01(DRP)               _
Plant Operations
                                                                                                      _
IP 71714:
50-301/97021-01(DRP)         NCV                                           Procedural Inadequacies
Cold Weather Preparations
50-266/97021-02(DRP)
IP 71750:
50-301/97021-02(DRP)         VIO                                           Containment Hatch Interlock Inoperability
Plant Support Activities
50-266/97021-03(DRP)                                                                                                             '
ITEMS GPENED, CLOSED, AND DISCUSSED
50-301/97021-03(DRP)         IFl                                           Closed System Without Boundary Checks CCW
Opened
                                                                              System
50-266/97021-01(DRP)
50-266/97021-04(DRP)                                                                                       _
_
50-301/97021-04(DRP)_       _ VIO                                          Inadequate Testing of CCW System
_
50-266/97021-05(DRP)
50-301/97021-01(DRP)
  50-301/97021-05(DRP)       _VIO                                           Inadequate Operability Determination for CCW
NCV
                                                                              System
Procedural Inadequacies
  Closed
50-266/97021-02(DRP)
  50-266/97021-01(DRP)
50-301/97021-02(DRP)
  50-301/97021-01(DRP)         NCV                                           Procedural Inadequacies
VIO
  50-266/97003 01(DRP)
Containment Hatch Interlock Inoperability
  50-301/97003-01(DRP)         IFl                                           Concems with Facade Freeze Protection
50-266/97021-03(DRP)
-50-266/95005                         LER                                                     Manual Reactor Trip During Startup
'
                                                                                              Physics Testing
50-301/97021-03(DRP)
  Discussed
IFl
  50-266/97020-02(DRP)         IFl                                           Review of Procedure Adherence and
Closed System Without Boundary Checks CCW
                                                                                25
System
                                                                                  _ __________
50-266/97021-04(DRP)
_ VIO
Inadequate Testing of CCW System
50-301/97021-04(DRP)_
_
50-266/97021-05(DRP)
50-301/97021-05(DRP)
_VIO
Inadequate Operability Determination for CCW
System
Closed
50-266/97021-01(DRP)
50-301/97021-01(DRP)
NCV
Procedural Inadequacies
50-266/97003 01(DRP)
50-301/97003-01(DRP)
IFl
Concems with Facade Freeze Protection
-50-266/95005
LER
Manual Reactor Trip During Startup
Physics Testing
Discussed
50-266/97020-02(DRP)
IFl
Review of Procedure Adherence and
25
_ __________


                                                _______  _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _
_ _ _ _ _ _ _
      .
_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _
            *
*
                                          Effectiveness
.
50-301/97020-02(DRP)         IFl
Effectiveness
                LIST OF ACRONYMS USED IN POINT BEACH REPORTS
50-301/97020-02(DRP)
AC           Alternating Current
IFl
AFW         Auxiliary Feedwater
LIST OF ACRONYMS USED IN POINT BEACH REPORTS
AOP         Abnormal Operating Procedure
AC
ASME         American Society of Mechanical Engineers
Alternating Current
CCW         - Component Cooling Water System
AFW
CFR         - Code of Federal Regulations
Auxiliary Feedwater
CLUB         Current Licensing Basis
AOP
CR           Condition Report
Abnormal Operating Procedure
CVCS         Chemical and Volume Control System
ASME
ECCS         Emergency Core Cooling System
American Society of Mechanical Engineers
EOP           Emergency Operating Procedure
CCW
ESF           Engineered Safety Feature
- Component Cooling Water System
EP           Emergency Planning
CFR
FAR           Final Safety Analysis Report
- Code of Federal Regulations
IFl           Inspection Follow-up item
CLUB
IP             inspection Procedure
Current Licensing Basis
IPE           Individual Plant Evaluation
CR
IR             Inspection Report
Condition Report
ILRT           Integrated Leak Rate Test
CVCS
IT -           In-service Test
Chemical and Volume Control System
LCO           Limiting Condition for Operation
ECCS
LER           Licensee Event Report
Emergency Core Cooling System
LTOP           Low Temperature Overpressure Protection
EOP
MSIV           Main Steam Isolation Valve
Emergency Operating Procedure
MSS           Manager's Supervisory Staff
ESF
NCV           Non-Cited Violation -
Engineered Safety Feature
NDE           Non-Destructive Examination
EP
NRC           Nuclear Regulatory Commission
Emergency Planning
OD             Operability Determination
FAR
01             Operating Instruction
Final Safety Analysis Report
OM             Operations Manual
IFl
OOS           Out-of-Service
Inspection Follow-up item
OP             Operating Procedure
IP
ORT           Operations Refueling Test
inspection Procedure
PAB           Primary Auxiliary Building
IPE
PASS           Post-accident Sampling System
Individual Plant Evaluation
PBTP           Point Beach Test Procedure
IR
PDR           Public Document Room
Inspection Report
POD           Prompt Operability Determination
ILRT
QA             Quality Assurance
Integrated Leak Rate Test
RCP           Reactor Coolant Pump
IT -
                                              26
In-service Test
                                                                                              l
LCO
Limiting Condition for Operation
LER
Licensee Event Report
LTOP
Low Temperature Overpressure Protection
MSIV
Main Steam Isolation Valve
MSS
Manager's Supervisory Staff
NCV
Non-Cited Violation -
NDE
Non-Destructive Examination
NRC
Nuclear Regulatory Commission
OD
Operability Determination
01
Operating Instruction
OM
Operations Manual
OOS
Out-of-Service
OP
Operating Procedure
ORT
Operations Refueling Test
PAB
Primary Auxiliary Building
PASS
Post-accident Sampling System
PBTP
Point Beach Test Procedure
PDR
Public Document Room
POD
Prompt Operability Determination
QA
Quality Assurance
RCP
Reactor Coolant Pump
26
l


                                                                            _ - _ - _ - _ _ _ _ _ .
_ - _ - _ - _ _ _ _ _ .
                            *
*
                    .
.
              RCS       _ Reactor Coolant System
RCS
            - RHR             Residual Heat Removal
_ Reactor Coolant System
              RMP             Routine Maintenance Procedure
- RHR
              RP.             Radiation Protection
Residual Heat Removal
              RWST -                   Refueling Water Storage Tank
RMP
              SALP             Systematic Assessment of Licensee Performance
Routine Maintenance Procedure
              SER             Safety Evaluation Report
RP.
              SFP             Spent Fuel Pool
Radiation Protection
              SI-             Safety injection
RWST -
              SW               Service Water
Refueling Water Storage Tank
              TDAFW           Turbine Driven Auxiliary Feedwater
SALP
            -T/S         -Technical Specification-
Systematic Assessment of Licensee Performance
              TS               Technical Specification Test
SER
              URI             Unresolved item
Safety Evaluation Report
              USQ             Unreviewed Safety Question
SFP
              VIO             Violation
Spent Fuel Pool
              VNCR             Control Room Ventilation
SI-
              WMTP             Wisconsin Michigan Test Procedure
Safety injection
SW
Service Water
TDAFW
Turbine Driven Auxiliary Feedwater
-T/S
-Technical Specification-
TS
Technical Specification Test
URI
Unresolved item
USQ
Unreviewed Safety Question
VIO
Violation
VNCR
Control Room Ventilation
WMTP
Wisconsin Michigan Test Procedure
t'
t'
                                                                                                      l
l
                                                                                                    -
-
                                                                  27
27
  .
.
    .. . .   .. .   .
.. . .
                          ____                 _ _ _ _ _ _ _ _ _ _
.. .
.
____
_ _ _ _ _ _ _ _ _ _
}}
}}

Latest revision as of 07:50, 10 December 2024

Insp Repts 50-266/97-21 & 50-301/97-21 on 971021-1130. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support
ML20199F136
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 12/22/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20199F126 List:
References
50-266-97-21, 50-301-97-21, NUDOCS 9802030069
Download: ML20199F136 (27)


See also: IR 05000266/1997021

Text

. _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ .

<

,

U.S. NUCLEAR REGULATORY COMMISSION

REGION lli

Docket Nos.:

50 266, 50 301

Licenses No.:

DPR 24, DPR 27

Report No:

50-266/97021(DRP): 50 301/97021(DRP)

Licensee:

Wisconsin Electric Power Company

Facility:

Point Beach Nuclear Plant, Units 1 & 2

Location:

6612 Nuclear Road

Two Rivers, WI 54241 9516

Dates:

October 21 through November 30,1997

Inspectors:

F, Brown, Senior Resident inspector

A. McMurtray, Senior Resident inspector

P. Louden, Resident Inspector

Approved by:

J. W. McCormick Barger, Chief

Reactor Projects Branch 7

_

._

'

9902030069 971222

PDR

ADOCK 05000266

0

PDR

.

, . . .

-

-

.

.

.

.

.

_ _ _ _ _ . - - _ _ - - _ _ - . . - _ . - - - - -

..

.

EXECUTIVE SUMMARY

Point Beach Nuclear Plant, Units 1 and 2

NRC Inspection Report No. 50 266/97021(DRP); 50-301/97021(DRP)

This inspection included aspects of licensee operations, engineering, maintenance, and

plant support. The report covt,rs a 6 week inspection period by the resident inspectors.

Operations

Good command and control, deliberate conduct of operations, and good procedure

adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.

(Section 01.1)

The facility was operated in a safe manner with a strong safety focus and generally

conservative operational decisions. Two notable examples were the decision to

promptly shut down Unit 2 when reactor protection instrumentation test problems

could not be resolved within the allowed time and the decision to delay the startup of

Unit 1 while a nuclear instrument detector was repaired. (Section 01.2)

Prior to unit restart, the inspectors determined that Unit 1 containment cleanliness

was sufficient to prevent immediate safety concerns; however, the inspectors

identified several items, including loose electrical tape, which should not have been

present. (Section 02.1)

The licensee had taken adequate measures to ensure those safety systems

susceptible to freezing during the winter months were protected. Also, the licensee

had taken acceptable actions in addressing concerns with the facade freeze

protection system discussed in a previous inspection report. (Section 02.2)

4

The licensee identified and corrected three examples of the use of inappropriate

procedures. The need for numerous other procedure changes was identified by

operators prior to the use of inappropriate procedures. Despite these problems with

procedure development and review, the inspectors considered the use of procedures

in Operations to be good. This strong performance was based, in part, on

Operations Department initiatives to ensure that all required procedures were

performed as written, to ensure that activities requiring procedures were performed

using procedures rather than work plans, and to provide mentors who reinforced the

need for procedural control of activities affecting quality. (Section 03.1)

Most component cooling water (CCW) syntem normal, abnormal and emergency

operating procedures were considered appropriate, but the inspectors identified a

weakness with the failure of the emergency operating procedure to provide positive

isolation of nonsafety related CCW flow paths during the containment sump

recirculation phase of accident mitigation. This procedure weakness was considered

one aspect of a iest control violation. (Section 03.2)

Operator knowledge of the CCW system and its operation was good Reactor

2

_ _ _

_

_ - _ -

.

.

operators were familiar with the CCW system status and the cause for CCW system

annunciators. (Sections 04 & 05)

The quality assurance organization's identification and documentation of findings

improved significantly as the result of self critical program level arsessments

performed by the licensee. A self assessment performed by Quality Assurance

during this report period noted improvement in some areas but identified the need for

improvement in other areas. The inspectors considered the improvements and the

thorought.ess of the current self assessment to be positives. New performance

indicators for corrective action backlogs were implemented, but prioritization of

condition reports within each organization's backlog was of concern to plant

management and the inspectors. (Section 07.1, applicable to all functional areas)

The licensee committed to develop an Annual Plan which prioritized high-level

improvement initiatives and commitments to the NRC. This will provide a means for

licensee management to track the status of the improvement initiatives. (Section X2,

applicable to all functional areas)

Maintenance

No problems were noted during observations of maintenance and surveillance

activities involving the Unit 1 feedwater isolation feature and the auxiliary feedwater,

safety injection, and residual heat removal systems. (Section M1.1)

An inadequately controlled modification performed in December 1996 defeated the

Unit 1 containment upper hatch interlock system. This caused a Technical

Specification violation when the required compensatory actions were not

implemented. No instances were identified where containment integrity had been

degraded during the interlock system inoperability. (Section M2.1)

Maintenance supervision effectively responded to problems with maintenance

procedures for the CCW pump and motor repairs, inadequacies in the work scoping

process and insufficient lead time following procedure development con'ributed to

the procedure problems. (Section M3.1)

Enaineerina

The inspectors independently identified that CCW system testing had not

demonstrated the system's ability to provide its safety-related function when

instrument inaccuracies and potential accident condition system lineups were

considered. The inspectors also determined that four licensee operability

determinations for these problems generated between December 1996 and

November 1997, were inadequate. The licensee developed an adequate operability

determination after the inspectors brought this issue to the attention of plant

management. Two violations were identified. (Section E1.1)

A system engineer identified the potential for an unreviewed safety question if a test

of spare ventilation equipment, committed to in a Licensee Event Report, was

performed at power. This identification was the result of a comprehensive and

-

.

3

,

..

.

.

-

.

thorough review of the proposed test by the system engineer. (Section E2.1)

Plant Support

The radiological housekeeping within the P mary Auxiliary Building was good.

-

(Section R1)

4

--__-_____- .

. _ _ _ _

-

.

8tport Details

Summarv of Plant Status

Unit 2 was at full power and Unit 1 was in an extended outage at the start of the inspection

perled. Tw: unit operation was precluded due to previously identified concems with the

auxiliary feedwater system. Unit 2 was shutdown on November 15,1997, after the licensee

identified that complete testing of reactor protection system instrumentation and control

circuitry had not been completed as required by T/Ss. Unit i startup was underway at the

end of the Inspection period.

Inspection Focus

During this inspection period, the inspectors integrated a vertical slice review of the

component cooling water (CCW) system into the routine inspection of the Operations,

Engineering, and Maintenance functional areas,

l. Operations

01

Conduct of Operations

01.1 Shutdown and Startuo Activities

a.

Insoection Scope (Inspection Procedure (IP) 71707)

The inspectors observed the T/S-required shutdown of Unit 2 on November 15,

1997, and the startup of Unit 1 which began November 21,1997, and was

completed November 30,1997.

b.

Observations and Findinas

i

Shutdown of Unit 2

During a review of NRC Generic Lette- N 01," Testing of Safety Related Logic

Circuits," licensee engineering staff k wiled that multiple permissive logic circuitry

<

had not been tested in accordance v -

T/S requirements. Technical Specification

Table 15.4.11 Item 45 identifies these permissives and the required f4quency of

testing (every refueling outage). The engineering review identified that these

combination logic tests had not been performed and a Condition Report (CR) 97-

3786, dated November 14,1997, was written.

A 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> delay was allowed by T/Ss to accomplish the missed surveillance, but the

licensee determined that an acceptable procedure likely could not be written,

approved, and implemented within the 24-hour time limit Consequently, the

Ucensee decided at 11:30 a.m. on November 15 to shut down the unit.

Once the decision was made to shut down, the T/S action statement of Table 15.3.5-

5

_

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _

.

2 went into effect, requiring the unit to be in Hot Shutdown within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The

licensee subsequently provided an event notification to the NRC Operations Office at

1:25 p.m. in accordance with 10 CFR 50.72(b)(1)(1)(A) and (b)(2)(iii)(A).

The inspectors observed the Manager's Supervisory Staff (onsite review committee)

meetings which led to the decision to shut down Unit 2, and noted that senior plant

management consistently queried plant staff to ensure that they were not pressing

too hard for a desired result and being too production focused. The inspectors

concluded that the decision to shutdown Unit 2 was conservative and appropriate for

the situation.

The inspecturs observed control room activities during the shutdown of the Unit 2

reactor. The shutdown was methodically conducted, and control room command

and control was adequate. Ono delay in the direct shutting down of the unit

occurred during the testing of the Unit 2 main steam isolation valves (MSIVs).

Operations elected to perform the non required test to gather information for

engineering trending. During the shutdown, just prior to starting the test, a control

(reactor) operator noted that an initial condition for the test was that the reactor be

between 2 percent and 5 percent power. The reactor at the time was at about 1.5

percent. Operations department supervision decided to increase reactor power to

within the band indicated in the procedure and continue with the test. Other minor

delays occurred during the testing of the 'A' MSIV. The result of these test

decisions led to the reactor reacning hot shutdown status at 7:00 p.m. on November

15,1997,30 minutes prior to the required limit and 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> later th:n had the testing

not been conducted.

I

Startuo of Unit 1

The inspectors performed extensive control room observations during the startup of

Unit 1. Good use of procedures and good command and control were noted. No

negative observations were identified.

c.

Conclusions

Good command and control, deliberate conduct of operations, and good procedure

adherence were observed during the shutdown of Unit 2 and the startup of Unit 1.

01.2 Safety Focus in Operational Decision Makina

a.

Inspection Scope

The inspectors monitored operation of the facility to assess whether an appropriate

safety focus was maintained.

b.

Observations and Findinai

The inspectors observed an appropriate safety focus in the operation of the facility,

most notably in the decision to promptly shut down Unit 2 when it was determined

6

I

.

,

that the instrumentation test problems discussed in Section 01.1 could not be

resolved, within the allowed time, to plant management's satisfaction. The deelslon

to delay startup while an intermediate range nuclear instrumentation detector was

repaired was another example of conservative decision making, in that the T/3

allowed startup with only one operable detector.

Four examples of operational decisions which were not consistent with the normally

strong safety focus were noted by the inspectors. None of these decisions had a

direct impact on the safe operation of the facility. Multiple equipment failures or

human errors would have been required while these decisions were in effect for

there to have been an impact on the safe operation of the facility,

The first decision was to perform the MSIV maintenance diagnostic test during a T/S

required shutdown, which resulted in the unit remaining critical approximately an

hour longer than necessary (as discussed in Section 01.1). Following this

shutdown, the operations manager directed that a new procedure be written to

ensure that T/S required shutdowns were not delayed by the performance of optional

testing.

The second decision involved restart of Unit 1 with an inoperable upper containment

personnel hatch interlock. While allowed by the T/Ss, this decision resulted in

reliance on manual action rather than automatic action to prevent defeat of the

personnel hatch should use of the hatch be required during an emergency. A new

procedure was written to help ensure proper operation of the hatch.

The third decision involved performing repairs to Unit 1 control room annunciators.

Shortly before pressurizing and heating up the plant, plant staff identified that an

outage of annunciator panel 10-03 would be required to repair a degraded resistor.

The outage removed 122 annunciator windows from service. The required repair

_

could have been performed prior to exiting cold shutdown conditions, but it was nnt.

The licensee established appropriate administrative controls for the annunciator

outage. The inspectors observed the outage, which lasted approximately 1% hours,-

and did not note any performance problems.

The fourth decision involved relying on an analysis to demonstrate Unit 1 CCW

system operability rather than performing a test to confirm proper system alignment

and operation. This issue is discussed in more detail in E1.1.

b.

Conclusions

The facility was operated in a safe mannei with a strong safety focus and generally

conservative operational decisions.

02

Operational Status of Facilities and Equipment

--

-02M Unit 1 Containment Walkdown

7--

..

..

..

.

_ _ - _ _

. - _ _ _ _ _ _ _ _ - _ _ - _ _ _ - _ _ _ _ _ - _ _

________

-__-_____- _ _-_ ___________ _________- ___-- - - - _ _

-_-

<

.

a.

Inspection Scope

The inspectors performed a walkdown of the Unit 1 containment. This walkdown

was performed after licensee management's containment walkdown but prior to final

containment closeout.

b.

Observations and Findinat

The inspectors verified that equipment stored in containment was appropriately

secured. The general cleanliness of the containment was considered to be

acceptable in that no immediate or direct challenges to safety related systems or

components were observed; however, the inspectors found and removed several

pieces of loose tape, a broken stay tie, an aerosol can cap, a radiological posting, a

bottle of leak detection fluid, and some other miscellaneous trash. The total volume

and surface area of the removed items was insignificant compared to the available

surface area of the emergency core cooling system sump recirculation strainers.

The inspectors also noted two pieces of modular reflective insulation unsecured

within the *B" reactor coolant pump (RCP) cubicle, a spare valve protector for a

portable nitrogen bottle, and about twenty pieces of electrical tape dangling from

electrica: conductors on the containment polar crane. The inspectors informed the

licensee of these observations, and the observed items were subsequently removea

from the containment by licensee staff .nrior to final containment closeoui. The

electrical tape removed from the polar crane was characterized as being quite old

and degraded.

c.

Conclusistni

The inspectors determined that Unit 1 containment cleanliness was sufficient to

prevent immediate 6afety concems; however, the inspectors identified several items,

including loose electrical tape, which should not have been present.

02.2 Cold Weather Preparations

a.

insoection Scoco flP 71714)

The inspectors reviewed the implementation of the licensee's cold weather

preparations and freeze protection program for safety-related systems.

b.

Observations ansi Findinos

_

The inspectors reviewed the licensee's completed surveillances for cold weather

preparations and performed independent verification checks of selected cold weather

protection equipment. No problems were identified.

During a previous inspection ' Inspection Report No. 50-266/97003(DRP);

50 301/97003(DRP)), the inspectors identified concerns with the material condition of

the facade freeze protection system and with work orders not receiving the

appropriate priority to ensure completion before the onset of cold weather. An

8

.

.

additional concern involved the uncontrolled use of heat lamps in the facades to

alleviate freeze protection circuitry problems in heat traced lines.

The inspectors reviewed the licensee's response to these concerns and noted that a

facade freeze protection improvement initiative was started in June of 1997. The

maintenance backlog reduction group was given the task to address the freeze

protection circuitry problems. The major problem involved the functional quality of

the existing heat tracing coils. To address this problem, new heat tracing wiring and

leads were installed on much of the facade piping. At the conclusion of the

inspection period, about 90 percent of the new heat tracing had been installed in the

facade systems requiring heat tracing. The remaining 10 percent was scheduled to

be completed within the next few weeks. The inspectors concluded that the licensee

had made acceptable efforts to restore the facade freeze protection system to a

reliable functioning status.

During this inspection, no heat lamps were in place within the facades and

operations department management implemented the use of the station's temporary

information tag or temporary modification programs as the formal means to track

heat lamp usage.

Also during this inspection period, an NRC Maintenance Rule

Inspection Team identified the failure to consider the facade freeze

protection system to be within the scope of the Maintenance Rule (see

Inspection Report No. 50 266/97025(DRS); 50 301/97025(DRS)).

c.

Conclusions

The licensee had ta'Kon adequate measure to ensure that safety systems susceptible

to freezing were protected during the wir ter months. Actions taken to address

previous concerns with facade freeze protection system were also acceptable.

03

Operations Procedures and Documentation

03.1 Use of Procedures in the Operations Department

Ln.ipection Scoce

a.

n

The inspectors monitoled the facility's control and use of proceduret to ensure

compliance with NRC regulations and the T/Ss, and to ensure that activities affecting

quality were appropriately planned and executed.

b.

Observations and Findinas_

The inspectors observed good use of procedures by operators in the control room

and in the plant. Procedures which could not be performed as written were

corrected prior to performance of work: however, the large number of required

procedure changes was indicative of the poor past practices regarding procedure

development and use.

Proactive lmorovements in Ooerations Procedures and Usagg

_

_

9

.

.

.

_ _ _ _ _ - _ _ _ _ _ _ _ _

. _ .

- . - -

-

__-.-- - - -

.

_.-

.--.

__

_

.

.

The inspectors discussed the improved procedure usage with tne operations

manager who informed the inspectors of two initiatives within the operations

department. The inspectors considered these initiatives to be significant. The first

initiative involved the reclassification of all operations procedures as ' Continuous

Use." This classification dealt with a reported mind set among operators that non.

continuous use procedures did not need to be performed as written. The inspectors

discussed this mind set with the Regulatory Services and Licensing Manager, who

acknowledged that the failure to perform any required procedure as written, unless

authorized by 10 CFR 50.54(x), was inconsistent with NRC requirements ar.d the

licensee's Nuclear Power Business Unit, Procedure 1.1.2, *Procedurs Use and

Adherence." The second initiative involved the conversion of all repetitive use

operations work plans to procedures. This initiative reduced the possibility that a

work plan would be used to perform activities that the T/Ss required in be

procedurally controlled. The inspectors will monitor the effectiveness of these

operations department initiatives and the use of procedures by other departments

under the previously opened inspection follow up item (IFI) 50 266/97020-02(DRP);

50 301/97020-02(DRP).

The inspectors also observed positive examples of another operations department

significant initiative. The experienced contractors mentoring operators in the control

room were observed to coach plant staff to ensure that activities affecting quality,

such as troubleshooting a failed control rod drive logic card, were planned and

controlled using approved procedures.

inadeauste Procedure Reviews

,

An operator initiated CR 97 3877 on November 17,1997, to document an

inadequacy in Surveillance Procedure TS 30," Low Head Safety injection Check

Valve Leakage Test (Cold Shutdown)," Revision 16. Specifically, the procedure

directed that containment isolation valves be opened, while containment integrity was

in effect, without establishing the appropriate compensatory control of having a

dedicated operator stationed at the valve. Another operator initiated CR 97-3870 on

November 23,1997, to document an inadequacy with In service Test (IT) 300,

  • Feedwater Leakage Check Test Line Valve," Revision 10. This procedure also

directed that a containment isolation valve be opened without specifying the use of a

dedicated operator. On both of these occasions, the involved operators identified the

procedure errors after the valves were opened but before T/S containment integrity

requirements were violated. Work was stopped, the containment isolation valves

were shut, and the procedures were corrected.

The low temperature overpressure protection (LTOP) system actuated on October

23,1997, when operators started the Unit 1 "A" RCP using Operating Procedure

(OP) 4A, * Filling and Venting Reactor Coolent System,' Revision 44, and OP 48,

" Reactor Coolant Pump Operation," Revision 33. This RCP start was unusual in that

it was part of a fill-and vent evolution but the primary system was solid with little

entrained gas. The operating crew anticipated rapid pressure swings when the

10

. -

.

_ - - _ .

_._

.

.

L

)

pump was started, so the control operator made large and rapid changes to the

chcmical and volume control system (CVCS) letdown and charging controls.

Because of the lack of entrained gas in the primary system, the system induced

pressure transient was insignificant. The manipulation of the CVCS controls resulted

in en overfilling transient which was terminated by the operator's actions and the

LTOP a:tuation. The October 23,1997, LTOP event was the second time that a

RCP had been started during fill and venting of a solid, de-gassed primary system.

.

A subsecor't review of data from the first time evolution, in September 1997,

'

indicateu that an LTOP actJallon had nearly occurred on that occaslon. Procedure

OP 4B I;ad been changed on August 2,1997, to cover sta . . 4 RCPs in the

v

condtions cescribed above, but this change had not established controls or

cor.Wed cautions for the operato,s to prevent the LTOP actuation. Planned

corre.;tive action 6 for the latest event includes additional crew training and revision of

the procedures.

The inspectors concluded that the inadequate procedures described above were not

indicative of a repetitive problem because of the large number of new procedures

and revised procedures which were implemented during this inspection period. The

licensee identified and corrected, non-repetitive inadequacies in IT 300, TS 30, and

OP 48 are considered to be examples of a non-citeo violation

(NCV 5F266/97021-01(DRP); 50 301/9702101(DRP)). In recent insoection periods,

the insp;,ctors had noted that operators were being relied upon to catch procedure

,

errors which should have been corrected during procedure preparation and review.

The events described above indicate the risk associated with continued reliance on

operators to catch procedure problems. The effectiveness of the initiatives to

improve procedures and procedure reviews so that less burden is placed on

opMators will be monitored under the previously opened IFl 50 266/97020-02(DRP);

50-301/97020 02(DRP),

c.

Conclusions

The licensee identified and corrected three examples of the use of inappropriate

procedures. The need for numerous other procedure changes was identified by

operators prior to the use of the procedures. Despite these problems with procedure

development and review, the inspectors considered the use of procedures in

operations to be good. This strong performance was based, in part, on operations

department initiatives to clarify that all required procedures were to be performed as

written, to ensure that activities requiring procedures were performed using

procedures rather than work plans, and to provide mentors who reinforced the need

for procedural control of activities affecting quality.

03.2 Comoonent Coolina Water Procedures

a,

bsDection ScoDe

The inspectors reviewed normal, abnormal, and emergency operating procedures

for the CCW system.

11

--_

.

. _ .

-

.

. - .

__

-

_

.

.

b.

Observations and Findinos

The inspectors reviewed OP 6A, * Operation of Component Cooling System,"

Revision 21, and Check List 6A, * Component Cooling, Unit 1,* Revision 22, and did

not identify any signincant issues. The inspectors also reviewed Abnormal Operating

Procedure (AOP) 98, Unit 1,' Component Cooling System Malfunction," Revision 9,

/

and only identified one potential concern. Specifically, Step 6 directed that the CCW

surge tank vent valve, CC.17, be opened if the CCW surge tank level was trending

lower. Valve CC.17 must be closed (closed system outside of containment) to

maintain containment integrity because there are not two containment isolation

valves in the CCW system. The inspectors were concerned that operators

implementing AOP 9B could overlook the impact of opening CC.17 under the stress

of responding to a CCW system failure. The inspectors detennined that this issue

did not make AOP 9B inadequate, but discussed the concern with the procedure and

tho basic system configuration limitations which affected the procedure, with licensee

tranagement.

The inspectors reviewed Emergency Operating Procedure (EOP) 0.0, *Redlagnosis,"

Revision 5, and EOP 1.3, " Transfer to Containment Sump Recirculation," Revision

15 to determine whether the CCW system was adequately described and controlled.

The inspectors did not identify any concerns with EOP 0.0. However, the inspectors

identified that Step 9, * Establish Desired Component Cooling Lineup," of EOP 1.3 did

not establish the same system lineup described in the operability determination (OD)

for CR 96-416 (see Section E1.1). Specifically, the inspectors identified that the

CVCS seal water heat exchanger and the waste gas compressors were not isolated

by EOP 1.3 but were not considered as flow paths in the OD. The site system

engineers wrote CR 97 3754 and an associated OD to document and address this

inspector-identified issue (Section E1.1). The inspectors also identified that EOP

1.3, Step 9e, directed that CCW flow to the CVCS non-regenerative heat exchanger

be isolated by closing valve 1(2)CC 130 using its pneumatic actuator controller

1(2)HC 130. The inspectors noted that 1(2)CC-130 was a fall-open butterfly valve

and that its pneumatic actuPor was nonsafety related. The inspectors also noted

that there was no direct control board indication of the position status of 1(2)CC-130

or direct indication of CCW flow through the CVCS non regenerative heat exchanger.

The only available indication for an operator to use in determining whether use of the

pneumatic actuator had achieved the desired results was the CCW system total flow

indicator. The inspectors noted that no quantitative value for flow change as a result

of successful closure of 1(2)CC 130 under accident conditions was available to the

operators, and flow changes in the CCW system from completion of Steps 9c

(placing a residual heat removal (RHR) heat exchanger in service), 9d (isolating

CCW loads in containment), and paraiset performance by an auxiliary building

operator of iso!ating a boric acid evaporator (Attachment A of EOP 1.3) could mask

the effect of Step 9e. Additionally, if the nonsafety related actuator were to fall open

after completion of Step 9e, there would be no direct indication of CCW system flow

diversion from safety related loads.

The inspectors reviewed the CCW system test procedures and ODs, and concluded

that the effect of CCW flow diversion through the non regenerative heat exchangers

12

i

.

.

,

was not evaluated or bounded, and had the potential to directly affect the mitigation

of a design basis loss of coolant accident. The non regenerative heat exchanger

Isolation valve,1(2)CC 7408, was used during performance of CCW system tests to

serve the function covered by EOP 13, Step 9e. The weaknesses in controlling _

CCW system configuration during accident conditions was a contributing aspect of

the test control inadequacies described in Section E1.1.

c.

Csnelusions

Most CCW system normal, abnormal and emergency operating procedures were

considered appropriate,- but the inspectors identified weaknesses associated with the

failure of the EOP to provide for positive isolation of nonsafety related CCW flow

paths during the containment sump recirculation phase of accident mitigation.

04

Operator Knowledge and Performance

The inspectors interviewed several licensed and non licensed operators regarding

the function, design, component makeup, and system interrelationships of the CCW

system. All opemtors interviewed displayed a solid fundamental understanding of

the system and its overall purposes. Control room operators were familiar with the

cause of alllit CCW system annunciators and accurately explained all system

Indications discussed with the inspectors.

05

Operator Training and Qualifications

The inspectors reviewed Training Handbook 10,9," Primary Systems Descriptions:

Component Cooling System," Revision 4, and found it to be informative and

accurate. Some of the non licensed operators stated during interviews with the

inspectors that

improvements could be made regarding the depth of training they receive on system

interrelationships following initial operator qualifications.

07

Quality Assurance in Operations

07.1 Imorovements In the Licensee Quality Assurance Function (IP 40500)

a.

Insoection Scope

The inspectors performed reviews of some licensee Quality Assurance (QA)

organization uudits, assessments, and CRs to determine the effectiveness of the QA

function,

b.

Obseivations and Findinas

The licensee conducted three program-level assessments of the Point Beach QA

organization and function during the last 18 months. The most recent was

completed in April 1997, and two of the three assessments were conducted by

outside contractors. The assessments were critical of the organizational and

_

13

.

.

.

.

.

.

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

4

functional performance, and consequently major organizational, personnel, and

staffing changes were implemented. The inspectors noted significant improvement

in the number and quality of QA findings following these changes. The most

important QA findings were classified as QA Program Significant issues, and were

tracked as separate high level priorities within the licensee work and improvement

prioritization process.

In addition, the QA orgnizetion performed a self assessment, S A 9719, dated

November 20,1997, of their performance in implementing corrective actions from the

program level assessments. This self assessment involved the participation of two

CA managers from other nuclear power plants. The self assessment acknowledged

the improvements noted by the inspectors, and also identified opportunities for

continued improvement, including better training and qualification of OA staff, more

consistent initiation of CRs, and more time for preparation for performance of audits.

One additional issue in "1e self assessment was that the QA Program Significant

Issues list was one of ma,iy priority lists in the prioritization process, and that this

fact led to uncertainty on the part of line managers as to relative significance (see

also Section X2 for discussion of work prioritization issues).

Another positive action observed during this report period was the development of

performance indicators for corrective action backlogs in the line organizations. This

action was undertaken to help focus management attention on the CR process. One

issue that was of concern to the inspectors was the lack of a programmatic process

for assigning work priorities within the CR backlog. Plant management had directed

individual line managers to ensure that CRs were worked in the order of safety

significance, but no process existed to evaluate performance in this stea,

c.

Conclusions

Performance of the QA organization's identification and documentation of findings

improved significantly as the '. ssult of self critical, program-level assessments

performed by the licensee. A self assessment performed by QA during this report

period noted improvement but identified additional areas for improvement. The

inspectors considered the improvements and the thoroughness of the current self.

assessment to be positives.

New performance indicators for corrective action backlogs were implemented, but

prioritization of CRs within each organization's backlog was of concern to plant

management.

08

Miscellaneous Operations issues

08.1 [Qlgsed) IFl 50 266/97003-01(DRP): 50 301/97003-01(DRP): Miscellaneous

concerns regarding the facade freeze protection system. The inspectors' follow-up

review of these matters is discussed in Section O2.2 of this report. The inspectors'

original concerns were determined to be adequately addressed.

14

.

_

_ - _ _ _ _ _ _ _ _ _ _ - _ - _ .

-

.

OS.2 (Closed) Ucensee [ *nt Report (LER) 50 266/95005-00: Manual Reactor Trip

During Startup Physics Testing. On April 15,1995, control rod F-12 dropped into the

Unit 1 core during low power physics testing. Unit 1 was critical below the point of

adding heat at the time. During troubleshooting on April 16,1995, a second control

rod, E 11, dropped part way into the core when the control operator withdrew rods in

control bank A. When the second rod entered the core, the reactor went subcritical.

The duty shift superAor ordered the reactor manually tripped.

The licensee dete.

ad that rod E 11 dropped because fuses pulled to facilitate

troubleshooting actN, des on rod F 12 were common to movable gripper coils of both

rods. After the manual reactor trip, troubleshooting activities on the F 12 rod

determined that the rod had dropped due to the failure of its stationary gripper coll.

The licensee initiated CR 95 255 for this event and performed Root Cause

Evaluation 9510 since human performance factors contributed to the partial drop of

E 11. The root cause evaluation determined that there was a miscommunication

between the instrument and control engineer coordinating F 12 troubleshooting

activities and the reactor engineer and control operator for Unit 1. The root cause

evaluation also determined that inadequate shift tumover and pre job briefs

contributed to this event.

The licensee replaced the failed stationary gripper coil stack and successfully tested

it prior to the subsequent restart of Unit 1. The licensee had an off site laboratory

analyze the failure mechanism of the failed stack. The laboratory determined that

the primary contributor to the coil failure was high temperv

' hat resulted from the

failure of a control rod drive motor shroud fan damper.1

censee repaired the

damper and shroud temperatures remained normal during Unit 1 operation.

Secondary contributors to the coil failure were aging and moisture / boric acid

intrusion. The licensee subsequently inspected the stationary gripper coil stacks for

Unit 1 and Unit 2. No problems were identified.

The inspectors reviewed the root cause evaluation, the CR, the laboratory report,

and F 12 troubleshooting, and coil stack replacement work plans. The inspectors

had no concerns with any of these activities. The inspectors also noted that recent

improvements in communications during reactivity maneuvers, shift tumovers, and

pre job briefs should prevent this event from occurring again. The inspectors had no

additional concerns with this issue.

II. Maintenance

M1

Conduct of Maintenance

M1.1 Te9s and Surveillances

NRC Inspection Procedures 62707 & 61726 were used in the inspection of plant

15

4

maintenance and surveillance activities, The inspectors observed and reviewed

selected ponions of the following tests:

In service Test Procedure 10A," Test of dectrically Driven Auxiliary Feed

Pumps and Valves With Flow to Unit 1 Steam Generators (Quarterly)?

Revision 1, conducted on November 26,1997.

TS Test 45 "Feedwater Isolation Test From a Safety injection Signal Unit 1,"

Revision 0, conducted on November 14,1997.

In service Test Procedure 530A,' Leakage Reduction and Preventive

Maintenance Program Test of the Train A High Head Safety injection and

Residual Heat Removal Systems Unit 1," Revision 2, conducted on November

26,1997.

The work performed under these activities was professional and thorough.

Technicians were experienced and knowledgeable of their assigned tasks. The work

packages were present at the job site and actively used by the technicians for all

work observed. System engineers were frequently observed monitoring job

progress.

M2

Maintenance and Material Condition of Facilities and Equipment

M2.1 . Containment Hatch Interlock inocerability

a.

insoection Scope (IPs 62707 & 37551)

The inspectors reviewed the circumstances surrounding the licensee's identification

that a gear was missing from the Unit 1 containment upper personnel hatch interlock

mechanism. The inspectors also reviewed the results of the licensee's root cause

investigation into the matter,

b,

Observatipns and Findinas

'

Maintenance workers identified that a gear was missing from the Unit 1 containment

upper hatch interlock mechanism while preparing to perform operational checks on

the hetch. Condition Report 97-3574 was written to address the defect and to note

that the absence of the gear inight defeat the interlock system. Licensee

management requested a root cause evaluation of the missing gear.

,

Licensee engineering staff verified through field tests that, with the gear missing, the

interlock system could be defeated if the normd lever manipulations for opening the

hatch doors were not followed. This condition was documented in CR 97-3756.

The licensee's root cause evaluation determined that the gear was removed on

December 28,1996, following an unsuccessful containment hatch leakage test. The

failure of the test was attributed to a bent remote operator shaft which was causing

damage to the quad ring seal. Removing the hatch interlock gear was intended to

16

l

l

I

l

- -- -- - .--

.

-

-

- -----

. - - -

,

_ _ _ _

_

_-_

_ - _ - _ - _ _ _ - - - - - - - - _ .

'

.

eliminate stresses on the seal ring caused by the bent shaft. Removal of the gear

was not recognized as being a temporary modification to the hatch interlock system;

therefore, the design control process was not used and the proper reviews and

approval of the gear removal were not obtained. The gear was removed under work order 9614237. A station log entry referenced that the hatch was operable based on

a successful hatch leakage test performed following the removal of the gear. No

post maintenance testing of the hatch interleck was performed.

Unit 1 was at power between December 28,1990, and February 18,1997, with the

Unit 1 containment hatch interlock system inoperable. The failure to perform the

required compensatory actions was a Violation (VIO 50-266/97021-02(DRP);

50 301/97021-02(DRP)) of T/S 15.3.6.A.1.d.2. No instances were noted that

indicated that the containment ilitegrity for Unit 1 was degraded during this period,

c.

Conclusions

The licensee inadvertently defeated the Unit 1 containment upper hatch interlock

system by removing a gear from the system without utilizing the appropriate design

control processes for work on safety related components. One T/S violation was

identified.

M2.2 Comoonent Cooling _ Water System Walkdowns and Material Con @gn

The inspectors conducted walkdowns 'the CCW system and saw no obvious

material condition problems. The inspectors also reviewed CRs for the CCW

system. Many of the CR's identified isolated problems or deficiencies. However,

one issue which was noted in several CRs was the unreliability of pressure

controllers and level transmitters in the system. The instruments had been

frequently found out of tolerance end presented calibration repeatability difficulties.

Another issue involved a several year old problem with fluctuations in the CCW

surge tank level. There were several apnarent contributors to this level fluctuation,

,

but definitive corrective actions had not been taken. The inspectors concluded that

there was no safety consequence associated with the surge tank level fluctuations.

M2.3 Primarv Auxiliary Buildina (PAB) Boric Acid L.eaks

During tours of the PAB and the Unit 1 containment, the inspectors observed boric

acid build-up and numerous work order tags on several pieces of safety-related

equipment. Boric acid build-up was present on the mechanical seals for the safety

injection (SI) and RHR pumps and body-to-bonnet joints and packing for charging,

SI, and RHR valves. There were more work order tags and boric acid build up than

the inspectors had observed during previous tours of the PAB, but the inspectors

had no operability concerns. All observations were discussed with plant

management.

17

.. ..

.

.

..

.

- _ _ _ _ _ _ _ _ _ _ _ _ _ - _ .

.

M3

Maintenance Procedures and Documentation

M3.1 CCW Pumo Modification

a.

Inspection Scope (IP 62707)

The inspectors reviewed the replacement of the Unit 1 CCW system *B" pump motor

and the overhaul of the pump impeller,

b.

Observations and Findinas

The licensee pit.nned to replace the motor for the Unit 1 CCW *B* pump (due tc high

vibrations) with the spare pump motor maintained onsite to meet 10 CFR 50,

Appendix R requirements. Pump impeller overhauls were also planned to be

performed during the motor replacement.

After a couple of days of work, the job vlas stopped following requests by the job

leaders because the procedures being used were cumbersome to implement and

hard to follow. At one point prior to the work being stopped, maintenance workers

were referencing three procedures at one time. Maintenance management stopped

the work and immediately met with workers to more fully understand the problems

and establish a strategy to address the concerns prior to work recommencing.

The inspectors discussed the circumstances with maintenance personnel and

supervision and determined that the causes for the procedural problems leading to

the work stoppage included inadequate management guidance regarding the scope

of the work, and failure to provide enough lead time following procedural

development to allow for a thorough procedure review and walkdown.

,

Once the work was restarted, it was conducted smoothly and in a timely manner.

The inspectors noted that workers involved with the repairs exerdsed good craft

skills, housekeeping in the work area was tidy, and appropriate tools were used

during the repairs. However, there were inconsistencies in the manner by which

foreign material exclusion areas were established and controlled during the work

suggesting that the intent of the program and/or station procedures were not clearly

understood by the workforce.

c.

Conclusions

The inspectors concluded that maintenance supervision effectively responded to

problems encountered by workers during the CCW pump and motor repairs.

Inadequacies in work scoping and insufficient lead time following procedure

devebpment caused the problems.

>

18

_ ___ _______ __- __________________ ___ - ______ _ -____ - _ ________

______ _ __ _______ _ _ -_ _ _

.

lll Enn neerina

E1

Conduct of Engineering

E1.1

CCW System Testina Inadecuacies

a.

Inspection Scope UP 3755.)

The inspectors reviewed the CCW system test and surveillance procedures to

ensure that the system was tested in a manner which ensured that design basis

requirements would be met under postulated accident conditions and configurations.

b.

Qblervations and Findinas

The inspectors found that identifying design bases requirements for the CCW system

was difficult. The T/Ss did not contain any quantitative requirements for the system.

The Final Safety Analysis Report (FSAR) provided adequate discussion of some

design bases information such as containment integrity considerations, but did not

list required flow rates for all safety related loads and did not reference critical

operational controls such as the need to throttic the CCW system outlet valves from

the RHR heat exchangers to prevent pump run out. The FSAR also provided only

one taference to design basis documents for the CCW system. The inspectors

reviewed two recent 10 CFR 50.59 r /aluations: Safety Evaluation 97-183 and Safety

Screening 97-1259-01. Neither e'.alu0 tion referenced CCW system current licensing

basis requirements other than the T/Ss and FSAR. The inspectors did not identify

any inadequacies in the two evaluations; however, the potential existed to miss

important considerations when modifying the system or system procedures.

The CCW system had only a single containment isolation valve on the return lines

from containment. To compensate for this, the system outside containment was

maintained as closed to the environment. This provided redundancy for the

contait. ment isolatinn function. The inspectors noted that some of the valves relied

upon for keeping the system closed outside of containment were known to have

small amounts of seat leakage, but the valves were not included in the periodic valve

leak check program, the leak rates were not quantified, and a bounding analysis of

acceptable leak rates was not developed. The licensee informed the inspectors that

this condition had been reviewed and found acceptable within the current licensing

basis (CLB). The inspectors will review the acceptability of classifying a system as

closed without performing boundary valve leak checks as an IFl (50-266/97021-

03(DRP); 50 301/9702103(DRP)).

The inspectors reviewed IT 12, " Component Cooling Water Pumps and Valves

(Quarterly)," Revision 12, to determine whether the ability of the CCW system to

meet its design bases requirements under accident conditions was adequate!y

demonstrated. Procedure IT 12 provided testing methodology which satisfied the in

service test requirements of TS 15.4.2; however, it did not demonstrate system

operability relative to safety-related flow and flow distribution. The system

engineering group referred the inspectors to Wisconsin Michigan Test Procedure

19

'

.

(WMTP) 12.11,' Component Cooling System Flow Test," Revision 1, performed on

November 2,1989, and Point Beach Test Procedure (PBTP) 52, "Coi.vonent

Cooling Water System Flow Test - Unit 2,* Revision 0, performed on June 10,1997.

The inspectors detemuned that WMTP 12.11 did not test the CCW system in its

accident configuration and did not include provisions for considering instrument

inaccuracy in establishirg acceptance criteria. Procedure PBTP 52 also did not test

the CCW system in its accident configuration, and the specified acceptance criteria,

which included instrument inaccuracy, had not been satisfied. The licensee informed

the inspectors that there were no other applicable test procedures. The failure to

perform testing that demonstrated that the CCW system would satisfactorily perform

its safety-related function under accident conditions, was a violation

(50-266/97021-04(DRP); 50-301/97021-04(DRP)) of 10 CFR 50, Appendix B,

Criterion XI, " Test Control."

After identifying the testing problems discussed above, the inspectors reviewed the

licensee's record of CRs and ODs for the CCW system to determine whether

reasonable assurance of system operability existed. The inspectors found that CR

96-416 and an OD had been written on December 30,1996, which clarified design

basis flow requirements and relied on some of the test data from WMTP 12.11 to

demonstrate operability. This OD was inadequate in that, while relying on some test

data from WMTP 12.11, it ignored other data from WMTP 12.11 and did not consider

the impact of nonsafety-related loads which were not isolated under accident

conditions. CR 97-1863 had been written to document the tailure to obtain

acceptable test results during performance of PBTP 52. An OD associated with this

CR stated that sufficient margin existed to allow lowering the required acceptance

criteria. This OD wac inadequate in that action was not taken to develop revised

acceptance criteria or to change the CLB. On November 4,1997, the inspectors met

with licensee staff and provided specific concems with CCW system bst

methodology and the OD associated with CR 96-416.

On November 11,1997, a licensee engineer wrote CR 97-3754 to document

confirmation of the inspectors' finding that two nonsafety-related loads not

considered in the OD for CR 96-416 were left in service when following the steps of

EOP-1.3 (see Section O3.2). The OD for CR 97-3754 containec a corrective action

to revise EOP-1.3, prior to Unit 1 start-up, so that the CVCS seal heat exchanger

and waste gas compressor would be isolated during containment sump recirculation.

On November 25,1997, a system engineer wrote CR 97-3901 to document that

EOP-1.3 had not been revised prior to Unit 1 leaving cold shutdown in the start-up

process. The ODs for CRS 97-3754 and 97-3901 both failed to address the lack of

acceptable test results. On November 25,1997, the inspectors informed the plant

manager and the site vice president of their concerns with the adequacy of the

existing ODs for the CCW system. A new OD was completed on November 28,

1997, prior to Unit 1 going critical. This OD provided reasonable assurance that the

CCW system would perform its design safety functions by taking credit for seasonally

cool service water system temperatures. The failure to establish an adequate basis

for system operability between December 30,1996, and November 28,1997, was a

violation (50-266/97021-05(DRP); 50-301/97021-05(DRP)) of 10 CFR 50, Appendix

B, Criterion XVI, " Corrective Action."

20

- - - _ _ _ _ _ _ _ _

_ _ _ _ _

_ _ _ _ -_ ____

-

n

.

c.

Conclusions

The inspectore concluded tnat CCW system testing had not demonstrated the

system's ability to provide its safety related function when instrument inaccuracies

and potential accident condition system lineups were considered. The inspectors

3!so determined that four ODs for these problems had been generated between

December 1996 and November 1997, but that these ODs were not E.1 equate. The

licensee developed an adequate OD after the inspectors brought this issue to the

attention of plant management.

E2.1

Positive System Enciaeer Performance

The licensee committed to test and maintain spare ventilation equipment in

LER 266/97-020-00. While preparing a safety evaluation for the required test, a

system engineer identified that an unreviewed safety question (USQ) would exist if

the test were performed with a unit at power. This issue was identified as the result

of a thorough review of references in the FSAR. The inspectors considered the

performance of the extensive research required to identify this potential USQ to be a

positive.

E4

Engineering Staff Knowledge and Performance

The inspectors found system engineers to be knowledgeable of their systems in

most cases. However, during the course of the CCW system inspection, the

inspectors requested information on the operation of valve 1(2)CC-130. During

subsequent discussion between the inspectors anO the system engineer for the CCW

system, the system engineer stated that valve 1(2)CC-130 was a fail-closed valve.

The inspectors questioned this conclusion based on field observation of the valve

actuator arrangement. Additionally, check list 6A contained a note which stated that

valve 1(2)CC-130 was gagged to prevent CCW pump run out should the valve fail.

ihe difference between a fail-open and fail-closed valve was also significant

because of potential CCW flow diversion under accident conditions (see Section

O3.2). The system engineer later informed the inspectors that valve 1(2)CC-130

was a fail-open. The system engineer wrote a CR which indicated that the vender

information for the valve was incorrect. The inspectors considered the system

engineer's lack of familiarity with the as-installed method of operation of the valve

actuator to be a weakness.

IV, Plant Support

R1

Radiological Protection and Chemistry (RP&C) Controls (IP 71750)

During the inspection period the inspectors frequently entered the PAB to conduct

housekeeping inspections and surveillances observations. Generally, radiological

housekeeping was good. However, during an inspection on November 25,1997, the

inspectors identified that a piece of drain tubing associated with Unit 1 Leakage

Reduction and Preventive Maintenance Program tests was dripping a small amount

of reactor coolant onto the floor of the #2 pipeway within the PAB. The inspectors

21

. _ _ - _ _ _ _ .

___

._

_ _ - _ - _ - _ _ _ _ _ _ _ _ _ - - - - - - - _ _ - - .

.

informed operations and health physics personnel of the condition and it was

appropriately addressed,

i

22

.

.-

_ _ _ _ . _

- _ _ _ _ - _ _ _ _ - _ - _ _ _ _

-

.

V. Manaaement Meetinas

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on December 2,1997. The licensee acknowledged the findings

presented.

The insoectors asked the licensee whether any materials examined during the inspection

should be considered proprietary. No proprietary information was identified.

,

X2

Management Meeting Summary

A public meeting with the licensee was held on October 29,1997, in Manitowoc. Wisconsin.

Licensee senior management provided the NRC Point Beach Oversight Panel with the

current status of improvement initiatives. Individual managers described the review and

approval process for ensuring that Unit 1 was ready to be restarted. Planned improvements

in the work planning process were also discussed in detail. The NRC was also told that an

Operating Plan for 1998 was being developed. This plan will prioritize licensee initiatives

and commitments to the NRC, such as development of comprehensive current licensing

bases documents. It will also provide a means for licensee management to track the status

of the improvement initiatives. The NRC welcomed this initiative because the prioritization

tools in place, the QA Program Significant issues Listing, the Level 1 Report, the Plan for

Achievement of Operational Excellence, and the corrective action program Significant

Conditions Adverse to Quality allidentified appropriate information but did not appear to be

integrated.

23

_ _ - _ _ - _ _ _

. _ _ _ _

.. .

= '

PARTIAL LIST OF PERSONS CONTACTED

. Wisconsin Electric Power Comoany

S. A.- Patuiski, Site Vice President

A. J. Cayla, Plant Manager

. R. G. Mende, Operations Manager

W. B. Fromm, Maintenance Manager

.J. G. Schweitzer, Site Engineering Manager

P. B. Tindall, Health Physics Manager

D. F. Johnson, Regulatory Services and Licensing Manager

_

'l

-

__

24

.. .

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -_

.

' INSPECTION PROCEDURES USED

IP 37551:

Onsite Engineering

IP 40500:

Effectiveness of Licensee Controls in Identifying, Resolving, and Preventing

Problems

IP 61726:

Surveillance Observations

IP 62707:

Maintenance Observation

IP 71707:

Plant Operations

IP 71714:

Cold Weather Preparations

IP 71750:

Plant Support Activities

ITEMS GPENED, CLOSED, AND DISCUSSED

Opened

50-266/97021-01(DRP)

_

_

50-301/97021-01(DRP)

NCV

Procedural Inadequacies

50-266/97021-02(DRP)

50-301/97021-02(DRP)

VIO

Containment Hatch Interlock Inoperability

50-266/97021-03(DRP)

'

50-301/97021-03(DRP)

IFl

Closed System Without Boundary Checks CCW

System

50-266/97021-04(DRP)

_ VIO

Inadequate Testing of CCW System

50-301/97021-04(DRP)_

_

50-266/97021-05(DRP)

50-301/97021-05(DRP)

_VIO

Inadequate Operability Determination for CCW

System

Closed

50-266/97021-01(DRP)

50-301/97021-01(DRP)

NCV

Procedural Inadequacies

50-266/97003 01(DRP)

50-301/97003-01(DRP)

IFl

Concems with Facade Freeze Protection

-50-266/95005

LER

Manual Reactor Trip During Startup

Physics Testing

Discussed

50-266/97020-02(DRP)

IFl

Review of Procedure Adherence and

25

_ __________

_ _ _ _ _ _ _

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _

.

Effectiveness

50-301/97020-02(DRP)

IFl

LIST OF ACRONYMS USED IN POINT BEACH REPORTS

AC

Alternating Current

AFW

Auxiliary Feedwater

AOP

Abnormal Operating Procedure

ASME

American Society of Mechanical Engineers

CCW

- Component Cooling Water System

CFR

- Code of Federal Regulations

CLUB

Current Licensing Basis

CR

Condition Report

CVCS

Chemical and Volume Control System

ECCS

Emergency Core Cooling System

EOP

Emergency Operating Procedure

ESF

Engineered Safety Feature

EP

Emergency Planning

FAR

Final Safety Analysis Report

IFl

Inspection Follow-up item

IP

inspection Procedure

IPE

Individual Plant Evaluation

IR

Inspection Report

ILRT

Integrated Leak Rate Test

IT -

In-service Test

LCO

Limiting Condition for Operation

LER

Licensee Event Report

LTOP

Low Temperature Overpressure Protection

MSIV

Main Steam Isolation Valve

MSS

Manager's Supervisory Staff

NCV

Non-Cited Violation -

NDE

Non-Destructive Examination

NRC

Nuclear Regulatory Commission

OD

Operability Determination

01

Operating Instruction

OM

Operations Manual

OOS

Out-of-Service

OP

Operating Procedure

ORT

Operations Refueling Test

PAB

Primary Auxiliary Building

PASS

Post-accident Sampling System

PBTP

Point Beach Test Procedure

PDR

Public Document Room

POD

Prompt Operability Determination

QA

Quality Assurance

RCP

Reactor Coolant Pump

26

l

_ - _ - _ - _ _ _ _ _ .

.

RCS

_ Reactor Coolant System

- RHR

Residual Heat Removal

RMP

Routine Maintenance Procedure

RP.

Radiation Protection

RWST -

Refueling Water Storage Tank

SALP

Systematic Assessment of Licensee Performance

SER

Safety Evaluation Report

SFP

Spent Fuel Pool

SI-

Safety injection

SW

Service Water

TDAFW

Turbine Driven Auxiliary Feedwater

-T/S

-Technical Specification-

TS

Technical Specification Test

URI

Unresolved item

USQ

Unreviewed Safety Question

VIO

Violation

VNCR

Control Room Ventilation

WMTP

Wisconsin Michigan Test Procedure

t'

l

-

27

.

.. . .

.. .

.

____

_ _ _ _ _ _ _ _ _ _