| number = ML21337A351 | | number = ML21337A351 | ||
| issue date = 10/12/2021 | | issue date = 10/12/2021 | ||
| title = E-mail, D. Hardesty, NRC to S. Lassel, North Carolina State Univ ( | | title = E-mail, D. Hardesty, NRC to S. Lassel, North Carolina State Univ (NCSU) Granting 30-day Extension on Environmental RAIs | ||
| author name = Hardesty D | | author name = Hardesty D | ||
| author affiliation = NRC/NRR/DANU/UNPL | | author affiliation = NRC/NRR/DANU/UNPL | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: | {{#Wiki_filter:From: Hardesty, Duane To: scott_lassell@ncsu.edu | ||
==Subject:== | ==Subject:== | ||
RE: Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf Date: | RE: Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf Date: Tuesday, October 12, 2021 1:43:00 PM | ||
Hello Scott: | |||
I did receive your request and after consultation with management, we have extended the due date as requested. Please ensure that your response is submitted by 30 November 2021 for the environmental RAIs. | I did receive your request and after consultation with management, we have extended the due date as requested. Please ensure that your response is submitted by 30 November 2021 for the environmental RAIs. | ||
Kind Regards, Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL From: Scott Lassell <salassel@ncsu.edu> | Kind Regards, Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL | ||
From: Scott Lassell <salassel@ncsu.edu> | |||
Sent: Tuesday, October 12, 2021 12:15 PM To: Hardesty, Duane <Duane.Hardesty@nrc.gov> | Sent: Tuesday, October 12, 2021 12:15 PM To: Hardesty, Duane <Duane.Hardesty@nrc.gov> | ||
==Subject:== | ==Subject:== | ||
[External_Sender] Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf Hi Duane - | [External_Sender] Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf | ||
Hi Duane - | |||
I just wanted to confirm that you had received our request below. | I just wanted to confirm that you had received our request below. | ||
Thanks - Scott | Thanks - Scott | ||
-------- Forwarded Message -------- | -------- Forwarded Message -------- | ||
Line 33: | Line 42: | ||
Reply-To:scott_lassell@ncsu.edu Organization:Nuclear Reactor Program, N.C. State University To:Hardesty, Duane <Duane.Hardesty@nrc.gov> | Reply-To:scott_lassell@ncsu.edu Organization:Nuclear Reactor Program, N.C. State University To:Hardesty, Duane <Duane.Hardesty@nrc.gov> | ||
CC:Montgomery, Cindy <Cindy.Montgomery@nrc.gov>, O'Bryan, Phil | CC:Montgomery, Cindy <Cindy.Montgomery@nrc.gov>, O'Bryan, Phil | ||
<Phil.O'Bryan@nrc.gov>, ayman.hawari@ncsu.edu <ayman.hawari@ncsu.edu>, | |||
Gerald Wicks <wicks@ncsu.edu> | Gerald Wicks <wicks@ncsu.edu> | ||
Hi Duane - | Hi Duane - | ||
We have reviewed the RAIs and are requesting to have 60 days to respond given our current workload. | We have reviewed the RAIs and are requesting to have 60 days to respond given our current workload. | ||
Thank you for your consideration. Please let me know if you have any questions. | Thank you for your consideration. Please let me know if you have any questions. | ||
Sincerely, | |||
Scott | |||
Mr. Scott Lassell, MEng, MBA Manager of Engineering and Operations, Nuclear Reactor Program Lecturer, Dept. of Nuclear Engineering North Carolina State University Room 2120 Burlington Laboratory, 2500 Stinson Drive Raleigh, NC 27695-7909 (v): 919.515.3347 (m): 919.260.4646 email: salassel@ncsu.edu URL: https://nrp.ne.ncsu.edu | |||
On 9/23/2021 10:24 AM, Hardesty, Duane wrote: | |||
Good Morning Dr. Hawari: | Good Morning Dr. Hawari: | ||
Attached is an electronic version of the NRC staffs request for additional information (RAI) related to the environmental analyses being conducted for license renewal. The letter is dated 21 September 2021 with a requested 30 day response. Scott and I previously discussed this RAI and the overlap with the RAI on breakaway oxidation. Per the letter, if additional time is required, or if you need clarification on any questions, please contact me. | Attached is an electronic version of the NRC staffs request for additional information (RAI) related to the environmental analyses being conducted for license renewal. The letter is dated 21 September 2021 with a requested 30 day response. Scott and I previously discussed this RAI and the overlap with the RAI on breakaway oxidation. Per the letter, if additional time is required, or if you need clarification on any questions, please contact me. | ||
Thank you, Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL U.S. Nuclear Regulatory Commission MS O-12D20 Washington, DC 20555 Phone: (301) 415-3724}} | Thank you, | ||
Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL U.S. Nuclear Regulatory Commission MS O-12D20 Washington, DC 20555 Phone: (301) 415-3724}} |
Latest revision as of 03:45, 19 November 2024
ML21337A351 | |
Person / Time | |
---|---|
Site: | North Carolina State University |
Issue date: | 10/12/2021 |
From: | Duane Hardesty NRC/NRR/DANU/UNPL |
To: | Lassell S North Carolina State University |
Hardesty D | |
References | |
Download: ML21337A351 (2) | |
Text
From: Hardesty, Duane To: scott_lassell@ncsu.edu
Subject:
RE: Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf Date: Tuesday, October 12, 2021 1:43:00 PM
Hello Scott:
I did receive your request and after consultation with management, we have extended the due date as requested. Please ensure that your response is submitted by 30 November 2021 for the environmental RAIs.
Kind Regards, Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL
From: Scott Lassell <salassel@ncsu.edu>
Sent: Tuesday, October 12, 2021 12:15 PM To: Hardesty, Duane <Duane.Hardesty@nrc.gov>
Subject:
[External_Sender] Fwd: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf
Hi Duane -
I just wanted to confirm that you had received our request below.
Thanks - Scott
Forwarded Message --------
Subject:
Re: NORTH CAROLINA STATE UNIVERSITY REQUEST FOR ADDITIONAL INFORMATION RE LICENSE RENEWAL APPLICATION FOR FACILITY OPERATING LICENSE NO. R-120 FOR THE PULSTAR NUCLEAR RESEARCH REACTOR.pdf Date:Tue, 28 Sep 2021 17:17:25 -0400 From:Scott Lassell <salassel@ncsu.edu>
Reply-To:scott_lassell@ncsu.edu Organization:Nuclear Reactor Program, N.C. State University To:Hardesty, Duane <Duane.Hardesty@nrc.gov>
CC:Montgomery, Cindy <Cindy.Montgomery@nrc.gov>, O'Bryan, Phil
<Phil.O'Bryan@nrc.gov>, ayman.hawari@ncsu.edu <ayman.hawari@ncsu.edu>,
Gerald Wicks <wicks@ncsu.edu>
Hi Duane -
We have reviewed the RAIs and are requesting to have 60 days to respond given our current workload.
Thank you for your consideration. Please let me know if you have any questions.
Sincerely,
Scott
Mr. Scott Lassell, MEng, MBA Manager of Engineering and Operations, Nuclear Reactor Program Lecturer, Dept. of Nuclear Engineering North Carolina State University Room 2120 Burlington Laboratory, 2500 Stinson Drive Raleigh, NC 27695-7909 (v): 919.515.3347 (m): 919.260.4646 email: salassel@ncsu.edu URL: https://nrp.ne.ncsu.edu
On 9/23/2021 10:24 AM, Hardesty, Duane wrote:
Good Morning Dr. Hawari:
Attached is an electronic version of the NRC staffs request for additional information (RAI) related to the environmental analyses being conducted for license renewal. The letter is dated 21 September 2021 with a requested 30 day response. Scott and I previously discussed this RAI and the overlap with the RAI on breakaway oxidation. Per the letter, if additional time is required, or if you need clarification on any questions, please contact me.
Thank you,
Duane A. Hardesty Sr. Project Manager - NRR/DANU/UNPL U.S. Nuclear Regulatory Commission MS O-12D20 Washington, DC 20555 Phone: (301) 415-3724