ML22067A185: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot insert) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:NRC Regulatory Conference - March 1, 2022 | {{#Wiki_filter:NRC Regulatory Conference - March 1, 2022 | ||
Columbia Gener ating Station Reactor Water Cleanup Uptake Event Re gulator y Confer ence March 1, 2022 | |||
NRC Regulatory Conference - March 1, 2022 | 1 NRC Regulatory Conference - March 1, 2022 | ||
Intr oduction and Agenda | |||
Introduction and Agenda Desirée Wolfgramm, Regulatory Affairs Manager Management Overview Dave Brown, Site Vice President Event Description Tony Hedges, Chemistry/Radiological Services Manager Root Cause and Corrective Actions Sam Nappi, Assistant Chemistry/Radiological Services Manager Significance Determination Desirée Wolfgramm, Regulatory Affairs Manager Closing Comments Grover Hettel, Vice President Nuclear Generation / Chief Nuclear Officer | |||
NRC Regulatory Conference - March 1, 2022 Reactor Water Cleanup Heat Exchanger Replacement Major activities of the project: | 2 NRC Regulatory Conference - March 1, 2022 | ||
Mana gement Over view Dave Brown Site Vice President | |||
3 NRC Regulatory Conference - March 1, 2022 | |||
4 NRC Regulatory Conference - March 1, 2022 | |||
Event Description | |||
Tony Hedges Chemistry/Radiological Services Manager | |||
5 NRC Regulatory Conference - March 1, 2022 | |||
Reactor Water Cleanup Heat Exchanger Replacement Major activities of the project: | |||
* Preparing system for replacement of components | * Preparing system for replacement of components | ||
* Performing destructive chemical decontamination of heat exchangers and piping | * Performing destructive chemical decontamination of heat exchangers and piping | ||
| Line 37: | Line 51: | ||
* Planning incorporated elevated and high-risk aspects of the project | * Planning incorporated elevated and high-risk aspects of the project | ||
* Planning addressed Locked High Radiation Area (LHRA) controls, contamination and airborne controls | * Planning addressed Locked High Radiation Area (LHRA) controls, contamination and airborne controls | ||
* Dedicated staffing to the project for each shift included a RP Supervisor and RP Lead Technician | * Dedicated staffing to the project for each shift included a RP Supervisor and RP Lead Technician | ||
NRC Regulatory Conference - March 1, 2022 RP | 6 NRC Regulatory Conference - March 1, 2022 | ||
RP Pr eplanning for Weld Pr epar ations | |||
* Remote dose and dose rate monitoring | * Remote dose and dose rate monitoring | ||
* Visual monitoring by camera | * Visual monitoring by camera | ||
- Portable video cameras, placed by RP, monitored at remote monitoring station (RMS) | |||
* Supervisory oversight - required per procedure 11.2.7.3 | * Supervisory oversight - required per procedure 11.2.7.3 | ||
- PROVIDE direct oversight during activities that have a potential for unplanned exposures, such as: | |||
* Work involving Dose Significant Activities as defined by this procedure | * Work involving Dose Significant Activities as defined by this procedure | ||
* Diving operations into pools, tanks, or cavities | * Diving operations into pools, tanks, or cavities | ||
* Radiography | * Radiography | ||
* Access to plant components that contain or may contain highly radioactive materials | * Access to plant components that contain or may contain highly radioactive materials | ||
NRC Regulatory Conference - March 1, 2022 | 7 NRC Regulatory Conference - March 1, 2022 | ||
Pr e-Wor k Activities Cut Location #3 - As seen through camer as at Remote Monitoring Station May 27 - Nightshift - glove bag task preview at the mock-up with pipefitters, RP Lead Tech, and RP Tech #3 | |||
* Mock-up not effectively used for practice | * Mock-up not effectively used for practice | ||
* Decision to use smaller glove bag | * Decision to use smaller glove bag | ||
* Pipefitters controlled installation and removal of glove bag May 28 - Dayshift - Successful weld prep on Cut #4 using larger glove bag under RP control | * Pipefitters controlled installation and removal of glove bag | ||
May 28 - Dayshift - Successful weld prep on Cut #4 using larger glove bag under RP control | |||
* Mock-up used for practice | * Mock-up used for practice | ||
* Used larger glove bag | * Used larger glove bag | ||
* RP controlled installation and removal of glove bag | * RP controlled installation and removal of glove bag | ||
NRC Regulatory Conference - March 1, 2022 Uptake Event | 8 NRC Regulatory Conference - March 1, 2022 | ||
Uptake Event | |||
* May 28 - Nightshift | * May 28 - Nightshift | ||
- Project Team Pre-job Brief and LHRA Brief | |||
- RP Job Coverage Tech changeout from RP Tech #1 to RP Tech #2 | |||
- Glove bag was removed contrary to briefed steps | |||
- Pipe was wiped inside and out after glove bag removal | |||
- Actions performed after glove bag removal were observed by RP Lead Tech and RP Supervisor via cameras at RMS | |||
- RP Lead Tech directed RP Tech #1 to stop work | |||
- RPT #1 directed pipefitters to cover pipe and exit | |||
- Bag installed over pipe, then removed and foreign material exclusion (FME) cover installed, leaving jobsite in a safe condition | |||
NRC Regulatory Conference - March 1, 2022 Briefed Steps | 9 NRC Regulatory Conference - March 1, 2022 Briefed Steps Perfor med Steps | ||
* Removed pipe plug in plastic bag | * Removed pipe plug in plastic bag | ||
* Removed pipe plug in plastic bag | * Removed pipe plug in plastic bag | ||
| Line 77: | Line 99: | ||
* Installing the glove bag onto the cut location | * Installing the glove bag onto the cut location | ||
* Attaching a HEPA vacuum to the glove bag to control any | * Attaching a HEPA vacuum to the glove bag to control any | ||
* Attaching a HEPA vacuum to the glove bag to control any contaminants contaminants disturbed during the work | * Attaching a HEPA vacuum to the glove bag to control any contaminants contaminants disturbed during the work disturbed during the work | ||
* Turning the HEPA vacuum on | * Turning the HEPA vacuum on | ||
* Turning the HEPA vacuum on | * Turning the HEPA vacuum on | ||
| Line 84: | Line 106: | ||
* Installing the wetted FME plug into the pipe through the glove bag | * Installing the wetted FME plug into the pipe through the glove bag | ||
* Cleaning the inside of the pipe using a flapping wheel inside of the | * Cleaning the inside of the pipe using a flapping wheel inside of the | ||
* Cleaning the inside of the pipe using a flapping wheel inside of the glove glove bag | * Cleaning the inside of the pipe using a flapping wheel inside of the glove glove bag bag | ||
* Removing the FME plug through the glove bag | * Removing the FME plug through the glove bag | ||
* Removing the glove bag from the cut location | * Removing the glove bag from the cut location | ||
* Wetting down the inside of the pipe and wiping down the surfaces | * Wetting down the inside of the pipe and wiping down the surfaces | ||
* Wetting down the inside of the pipe and wiping down the surfaces with with the glove bag still in place | * Wetting down the inside of the pipe and wiping down the surfaces with with the glove bag still in place the glove bag removed | ||
* Removing the FME plug through the glove bag | * Removing the FME plug through the glove bag | ||
* Removing the glove bag from the cut location | * Removing the glove bag from the cut location | ||
* Installing FME cover | * Installing FME cover | ||
* Installation of plastic bag, removal of bag and replaced with FME cover | * Installation of plastic bag, removal of bag and replaced with FME cover | ||
NRC Regulatory Conference - March 1, 2022 Root Cause Clarifications | 10 NRC Regulatory Conference - March 1, 2022 | ||
Root Cause Clarifications | |||
* Information discovered during the root cause investigation provides clarity on the sequence of events and circumstances of the night of May 28, 2021 | * Information discovered during the root cause investigation provides clarity on the sequence of events and circumstances of the night of May 28, 2021 | ||
* The following 5 slides provides this additional information | * The following 5 slides provides this additional information | ||
NRC Regulatory Conference - March 1, 2022 Additional | 11 NRC Regulatory Conference - March 1, 2022 | ||
Additional Infor mation fr om Root Cause Evaluation for ALARA Planning and Pr e-Job Sur veys Inspection Report Root Cause Clarifications | |||
* The ALARA Work Plan included specific instructions | * The ALARA Work Plan included specific instructions | ||
* The ALARA Work Plan was inclusive of the entire such as using powered air purifying respirators | * The ALARA Work Plan was inclusive of the entire such as using powered air purifying respirators RWCU Project which did consist of work in PAPRs, (PAPRs) on highly contaminated components which included removal of old components from the room, the RWP was specific to the job of the uptake event | ||
* there were inadequate surveys used to support | * there were inadequate surveys used to support | ||
* Surveys 20210527-23 & 20210529-6, supported down-down-posting the RWCU HX area from a high | * Surveys 20210527-23 & 20210529-6, supported down-down-posting the RWCU HX area from a high posting the RWCU HX area to a contamination area contamination area to a contamination area | ||
NRC Regulatory Conference - March 1, 2022 Additional | 12 NRC Regulatory Conference - March 1, 2022 | ||
Additional Infor mation fr om Root Cause Evaluation for Local Job Cover a ge Inspection Report Root Cause Clarifications | |||
* Contrary to the RWP requirements for continuous job | * Contrary to the RWP requirements for continuous job | ||
* Continuous coverage was not required. Dose rates coverage, RP Tech #1 left the workers unattended | * Continuous coverage was not required. Dose rates coverage, RP Tech #1 left the workers unattended were 450- 550 mR/hr during the work at the jobsite location | ||
* RP Tech #2 was not a part of the required formal | * RP Tech #2 was not a part of the required formal | ||
* RP Tech #2 was at LHRA brief the day of the uptake briefing for this job | * RP Tech #2 was at LHRA brief the day of the uptake briefing for this job event but not the task preview | ||
NRC Regulatory Conference - March 1, 2022 Additional | 13 NRC Regulatory Conference - March 1, 2022 | ||
Additional Infor mation fr om Root Cause Evaluation for Dir ect Over sight at Remote Monitoring Station Inspection Report Root Cause Clarifications | |||
* the lead RP tech, who is an RP Supervisor but was | * the lead RP tech, who is an RP Supervisor but was | ||
* There were three people at the RMS , RP Tech #3, RP not assigned to provide continuous coverage | * There were three people at the RMS, RP Tech #3, RP not assigned to provide continuous coverage Lead Tech, and RP Supervisor | ||
* The RP tech (not credited as job coverage) was at the | * The RP tech (not credited as job coverage) was at the | ||
* In accordance with PPM 11.2.7.3 Step 3.4.1.b the RP remote monitoring station with a view of the glove | * In accordance with PPM 11.2.7.3 Step 3.4.1.b the RP remote monitoring station with a view of the glove Supervisor was providing direct oversight from the bag activity RMS | ||
* the RP tech viewed the grinding activity at the right | * the RP tech viewed the grinding activity at the right | ||
* The RP Supervisor and RP Lead Tech both recognized point in time on the correct monitor and camera | * The RP Supervisor and RP Lead Tech both recognized point in time on the correct monitor and camera that steps were being performed out of the briefed sequence | ||
* the RP tech had enough background information | * the RP tech had enough background information | ||
* The RP Lead Tech was a part of the task preview at the and/or experience to recognize the abnormal | * The RP Lead Tech was a part of the task preview at the and/or experience to recognize the abnormal mock-up, and RP Supervisor and RP Lead Tech were in situation the brief the day of the uptake event | ||
14 NRC Regulatory Conference - March 1, 2022 | |||
Additional Infor mation fr om Root Cause Evaluation for Job Completion Inspection Report Root Cause Clarifications | |||
* the additional time needed to clean up the area, | * the additional time needed to clean up the area, | ||
* The pipefitters documented work complete. All gather tools, and leave the job in a safe work | * The pipefitters documented work complete. All gather tools, and leave the job in a safe work briefed steps were completed, some out of order. All condition is a reasonable scenario with minor tools were contained in the glove bag. The pipe was alterations could have led to overexposure covered by the FME cover when the pipefitters left the platform, leaving the job in a safe condition. | ||
15 | |||
15 NRC Regulatory Conference - March 1, 2022 | |||
Additional Infor mation fr om Root Cause Evaluation for Dose Assessment Inspection Report Root Cause Clarifications | |||
* Airborne radioactive material was released from the | * Airborne radioactive material was released from the | ||
* Opportunities for airborne contamination include glove bag and dispersed into the RWCU HX room | * Opportunities for airborne contamination include glove bag and dispersed into the RWCU HX room glove bag removal, wiping pipe inside and out, and installation and removal of plastic bag | ||
* Based on the | * Based on the inspector s derived air concentration | ||
* Based upon further investigation, there were multiple (DAC) estimate, the pipefitters could have reasonably | * Based upon further investigation, there were multiple (DAC) estimate, the pipefitters could have reasonably opportunities for airborne contamination which received greater than 5 rem if they had remained in invalidates the assumption in the calculation that the the work area for an additional five minutes. These entire dose was received in one puff release estimates were confirmed by the results of the licensees Calculation 21 -02. | ||
NRC Regulatory Conference - March 1, 2022 | 16 NRC Regulatory Conference - March 1, 2022 | ||
NRC Regulatory Conference - March 1, 2022 Results of Causal Evaluations | Root Cause and Cor r ective Actions Sam Nappi Assistant Chemistry/Radiological Services Manager | ||
17 NRC Regulatory Conference - March 1, 2022 | |||
Results of Causal Evaluations | |||
* Direct Cause: | * Direct Cause: | ||
- Improper setup, use (without HEPA vacuum), and removal of a glove bag (engineering control) while performing pipe preparation activities. | |||
* Root Cause: | * Root Cause: | ||
- The Radiological Risk for the work was evaluated by staff presupposing the successful use of engineering controls to mitigate radiological hazards and didnt evaluate or recognize the overall risk associated with the work being performed or potential consequences of engineering control failure or incorrect use. | |||
NRC Regulatory Conference - March 1, 2022 Completed | 18 NRC Regulatory Conference - March 1, 2022 | ||
Completed Cor r ective Actions | |||
* Immediate Corrective Actions: | * Immediate Corrective Actions: | ||
- Stopped work | |||
- Assigned additional resources | |||
- Performed coaching to the RP supervision and Leads | |||
- Ensured the remaining cuts were completed appropriately | |||
* Actions Taken Since the Uptake Event | * Actions Taken Since the Uptake Event | ||
- Revised the radiological risk screening form for high contamination work | |||
- Revised the Radiation Work Permit (RWP) procedure and Contamination Control Containment Devices procedure | |||
- Developed a new procedure for RP outage preparation | |||
19 NRC Regulatory Conference - March 1, 2022 | |||
Cor r ective Actions | |||
* Additional Actions to Be Taken: | * Additional Actions to Be Taken: | ||
- Revising the radiological risk assessment procedure | |||
- Provide training to individuals on how to assess radiological risk when elimination or mitigation actions are prescribed | |||
- Revising the TEDE/ALARA evaluation process | |||
- Require RWP revisions to be screened for changes in risk classification | |||
- Establishing clear roles and responsibilities for glove bag use in HPI -12.90 | |||
- Formally perform culpability assessments per station procedures for the individuals involved | |||
20 NRC Regulatory Conference - March 1, 2022 | |||
Significance Deter mination Desirée Wolfgramm Regulatory Affairs Manager | |||
21 NRC Regulatory Conference - March 1, 2022 | |||
Perfor mance Deficiency and A ppar ent V iolations | |||
Performance Deficiency Energy Northwest agrees with the Performance Deficiency Apparent Violation #1 Energy Northwest agrees with Apparent Violation #1 but suggest some wording changes to reflect the issue. The engineering control was not planned for with enough specificity in accordance with station procedures, specifically HPI-12.90, to ensure proper control for installation and removal to prevent airborne contamination Apparent Violation #2 Energy Northwest disagrees with Apparent Violation #2. The dose rates in the area at the time of the uptake event were less than those requiring continuous coverage Apparent Violation #3 Energy Northwest disagrees with Apparent Violation #3. Adequate dose surveys were completed in the field by RP Technicians during the work activity | |||
NRC Regulatory Conference - March 1, 2022 | 22 NRC Regulatory Conference - March 1, 2022 | ||
Inspection Repor t Significance Deter mination Assessed under the NRC's Reactor Oversight Process (ROP) Occupational Radiation Safety Significance Determination Process (SDP) Inspection Manual Chapter (IMC) 0609 Appendix C: | |||
Finding Identified No | |||
Finding Identified | |||
23 | No No No NoWas the ALARA Was It An Was there A Ability to Planning or Over-Substantial Assess Dose Green Wo r k exposure? Potential? Compromised Controls? ? | ||
Ye s No Was it a No SDE/DRP Whole Body White Exposure? Exposure in a VHRA? | |||
23 NRC Regulatory Conference - March 1, 2022 | |||
Substantial Potential for Over exposur e IMC 0609 Appendix C II.C Substantial Potential for Overexposure An event presents a substantial potential when it was fortuitous that the resulting exposure did not exceed the limits of 10 CFR 20. The concern is not the significance of the resulting, or potential, exposure, but whether the licensee provided adequate controls over the situation, as required, to ensure the Part 20 dose limits are not exceeded. No credit is given for luck. | |||
Required Controls per ALARA Plan and/or Station Procedures: | Required Controls per ALARA Plan and/or Station Procedures: | ||
- Engineered Control - Glove bag | |||
- Job coverage - RPT #2 | |||
- Direct Oversight - RP Supervisor at RMS | |||
- Tele-dosimetry - RPT #3 at RMS | |||
NRC Regulatory Conference - March 1, 2022 Substantial Potential for | 24 NRC Regulatory Conference - March 1, 2022 | ||
Substantial Potential for Over exposur e (cont.) | |||
IMC 0609 Appendix C II.C Substantial Potential for Overexposure (continued) | IMC 0609 Appendix C II.C Substantial Potential for Overexposure (continued) | ||
When assessing whether a finding constitutes a substantial potential for overexposure, consider if it is possible to construct a reasonable scenario in which a minor alteration of circumstances (as they actually happened) would have resulted in a violation of the Part 20 limits. The following circumstances should be considered: timing, source strength, distance, and shielding. | When assessing whether a finding constitutes a substantial potential for overexposure, consider if it is possible to construct a reasonable scenario in which a minor alteration of circumstances (as they actually happened) would have resulted in a violation of the Part 20 limits. The following circumstances should be considered: timing, source strength, distance, and shielding. | ||
"Fortuitous" circumstances as described in the Inspection Report, but through the root cause investigation were found to be pre-planned in the ALARA Plan and/or station procedures: | "Fortuitous" circumstances as described in the Inspection Report, but through the root cause investigation were found to be pre-planned in the ALARA Plan and/or station procedures: | ||
- RP tech (not credited as job coverage) was at the remote monitoring station with a view of the glove bag activity | |||
- The RP tech viewed the grinding activity at the right point in time on the correct monitor and camera | |||
- The RP tech had enough background information and/or experience to recognize the abnormal situation | |||
- The RP tech only had a "40 foot/30 second" walking path to the entrance of the RWCU HX room from the remote monitoring station | |||
25 NRC Regulatory Conference - March 1, 2022 | |||
Alter ation of Cir cumstances | |||
From Inspection Report If the lead RP tech had not intervened, the additional time needed to clean up the area, gather tools, and leave the job in a safe work condition is a reasonable scenario with minor alterations [that] could have led to overexposure. | |||
Additional Clarification from further investigation: | Additional Clarification from further investigation: | ||
- Calculation 21- 002 assumptions are invalid | |||
- Pipefitters completed work and left jobsite in a safe condition | |||
26 NRC Regulatory Conference - March 1, 2022 | |||
Significance Deter mination | |||
Assessed with additional information discovered through the root cause under the NRC's ROP Occupational Radiation Safety SDP IMC 0609 Appendix C: | |||
Finding Identified | |||
No No No NoWas the ALARA Was It An Was there A Ability to Planning or Over-Substantial Assess Dose Green Wo r k exposure? Potential? Compromised Controls? ? | |||
Ye s No Was it a No SDE/DRP Whole Body White Exposure? Exposure in a VHRA? | |||
27 NRC Regulatory Conference - March 1, 2022 | |||
Closing Comments Grover Hettel Vice President Nuclear Generation / | |||
Chief Nuclear Officer | |||
28}} | |||
Revision as of 14:14, 18 November 2024
| ML22067A185 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 03/01/2022 |
| From: | Energy Northwest |
| To: | NRC Region 4 |
| Greene N | |
| Shared Package | |
| ML22067A190 | List: |
| References | |
| EA-21-170 | |
| Download: ML22067A185 (28) | |
Text
NRC Regulatory Conference - March 1, 2022
Columbia Gener ating Station Reactor Water Cleanup Uptake Event Re gulator y Confer ence March 1, 2022
1 NRC Regulatory Conference - March 1, 2022
Intr oduction and Agenda
Introduction and Agenda Desirée Wolfgramm, Regulatory Affairs Manager Management Overview Dave Brown, Site Vice President Event Description Tony Hedges, Chemistry/Radiological Services Manager Root Cause and Corrective Actions Sam Nappi, Assistant Chemistry/Radiological Services Manager Significance Determination Desirée Wolfgramm, Regulatory Affairs Manager Closing Comments Grover Hettel, Vice President Nuclear Generation / Chief Nuclear Officer
2 NRC Regulatory Conference - March 1, 2022
Mana gement Over view Dave Brown Site Vice President
3 NRC Regulatory Conference - March 1, 2022
4 NRC Regulatory Conference - March 1, 2022
Event Description
Tony Hedges Chemistry/Radiological Services Manager
5 NRC Regulatory Conference - March 1, 2022
Reactor Water Cleanup Heat Exchanger Replacement Major activities of the project:
- Preparing system for replacement of components
- Performing destructive chemical decontamination of heat exchangers and piping
- Removal of old components from the room
- Installing new components and welding new pipe to system piping The planning and staffing aspects:
- Dedicated Radiation Protection (RP) Technician with planning qualifications
- Planning incorporated elevated and high-risk aspects of the project
- Planning addressed Locked High Radiation Area (LHRA) controls, contamination and airborne controls
6 NRC Regulatory Conference - March 1, 2022
RP Pr eplanning for Weld Pr epar ations
- Remote dose and dose rate monitoring
- Visual monitoring by camera
- Portable video cameras, placed by RP, monitored at remote monitoring station (RMS)
- Supervisory oversight - required per procedure 11.2.7.3
- PROVIDE direct oversight during activities that have a potential for unplanned exposures, such as:
- Work involving Dose Significant Activities as defined by this procedure
- Diving operations into pools, tanks, or cavities
- Radiography
- Access to plant components that contain or may contain highly radioactive materials
7 NRC Regulatory Conference - March 1, 2022
Pr e-Wor k Activities Cut Location #3 - As seen through camer as at Remote Monitoring Station May 27 - Nightshift - glove bag task preview at the mock-up with pipefitters, RP Lead Tech, and RP Tech #3
- Mock-up not effectively used for practice
- Decision to use smaller glove bag
- Pipefitters controlled installation and removal of glove bag
May 28 - Dayshift - Successful weld prep on Cut #4 using larger glove bag under RP control
- Mock-up used for practice
- Used larger glove bag
- RP controlled installation and removal of glove bag
8 NRC Regulatory Conference - March 1, 2022
Uptake Event
- May 28 - Nightshift
- Project Team Pre-job Brief and LHRA Brief
- RP Job Coverage Tech changeout from RP Tech #1 to RP Tech #2
- Glove bag was removed contrary to briefed steps
- Pipe was wiped inside and out after glove bag removal
- Actions performed after glove bag removal were observed by RP Lead Tech and RP Supervisor via cameras at RMS
- RP Lead Tech directed RP Tech #1 to stop work
- RPT #1 directed pipefitters to cover pipe and exit
- Bag installed over pipe, then removed and foreign material exclusion (FME) cover installed, leaving jobsite in a safe condition
9 NRC Regulatory Conference - March 1, 2022 Briefed Steps Perfor med Steps
- Removed pipe plug in plastic bag
- Removed pipe plug in plastic bag
- Wetting a FME plug inside of a glove bag
- Wetting a FME plug inside of a glove bag
- Installing the glove bag onto the cut location
- Installing the glove bag onto the cut location
- Attaching a HEPA vacuum to the glove bag to control any
- Attaching a HEPA vacuum to the glove bag to control any contaminants contaminants disturbed during the work disturbed during the work
- Turning the HEPA vacuum on
- Turning the HEPA vacuum on
- Turning the HEPA vacuum off
- Installing the wetted FME plug into the pipe through the glove bag
- Installing the wetted FME plug into the pipe through the glove bag
- Cleaning the inside of the pipe using a flapping wheel inside of the
- Cleaning the inside of the pipe using a flapping wheel inside of the glove glove bag bag
- Removing the FME plug through the glove bag
- Removing the glove bag from the cut location
- Wetting down the inside of the pipe and wiping down the surfaces
- Wetting down the inside of the pipe and wiping down the surfaces with with the glove bag still in place the glove bag removed
- Removing the FME plug through the glove bag
- Removing the glove bag from the cut location
- Installing FME cover
- Installation of plastic bag, removal of bag and replaced with FME cover
10 NRC Regulatory Conference - March 1, 2022
Root Cause Clarifications
- Information discovered during the root cause investigation provides clarity on the sequence of events and circumstances of the night of May 28, 2021
- The following 5 slides provides this additional information
11 NRC Regulatory Conference - March 1, 2022
Additional Infor mation fr om Root Cause Evaluation for ALARA Planning and Pr e-Job Sur veys Inspection Report Root Cause Clarifications
- The ALARA Work Plan included specific instructions
- The ALARA Work Plan was inclusive of the entire such as using powered air purifying respirators RWCU Project which did consist of work in PAPRs, (PAPRs) on highly contaminated components which included removal of old components from the room, the RWP was specific to the job of the uptake event
- there were inadequate surveys used to support
- Surveys 20210527-23 & 20210529-6, supported down-down-posting the RWCU HX area from a high posting the RWCU HX area to a contamination area contamination area to a contamination area
12 NRC Regulatory Conference - March 1, 2022
Additional Infor mation fr om Root Cause Evaluation for Local Job Cover a ge Inspection Report Root Cause Clarifications
- Contrary to the RWP requirements for continuous job
- Continuous coverage was not required. Dose rates coverage, RP Tech #1 left the workers unattended were 450- 550 mR/hr during the work at the jobsite location
- RP Tech #2 was not a part of the required formal
- RP Tech #2 was at LHRA brief the day of the uptake briefing for this job event but not the task preview
13 NRC Regulatory Conference - March 1, 2022
Additional Infor mation fr om Root Cause Evaluation for Dir ect Over sight at Remote Monitoring Station Inspection Report Root Cause Clarifications
- There were three people at the RMS, RP Tech #3, RP not assigned to provide continuous coverage Lead Tech, and RP Supervisor
- The RP tech (not credited as job coverage) was at the
- In accordance with PPM 11.2.7.3 Step 3.4.1.b the RP remote monitoring station with a view of the glove Supervisor was providing direct oversight from the bag activity RMS
- the RP tech viewed the grinding activity at the right
- The RP Supervisor and RP Lead Tech both recognized point in time on the correct monitor and camera that steps were being performed out of the briefed sequence
- the RP tech had enough background information
- The RP Lead Tech was a part of the task preview at the and/or experience to recognize the abnormal mock-up, and RP Supervisor and RP Lead Tech were in situation the brief the day of the uptake event
14 NRC Regulatory Conference - March 1, 2022
Additional Infor mation fr om Root Cause Evaluation for Job Completion Inspection Report Root Cause Clarifications
- the additional time needed to clean up the area,
- The pipefitters documented work complete. All gather tools, and leave the job in a safe work briefed steps were completed, some out of order. All condition is a reasonable scenario with minor tools were contained in the glove bag. The pipe was alterations could have led to overexposure covered by the FME cover when the pipefitters left the platform, leaving the job in a safe condition.
15 NRC Regulatory Conference - March 1, 2022
Additional Infor mation fr om Root Cause Evaluation for Dose Assessment Inspection Report Root Cause Clarifications
- Airborne radioactive material was released from the
- Opportunities for airborne contamination include glove bag and dispersed into the RWCU HX room glove bag removal, wiping pipe inside and out, and installation and removal of plastic bag
- Based on the inspector s derived air concentration
- Based upon further investigation, there were multiple (DAC) estimate, the pipefitters could have reasonably opportunities for airborne contamination which received greater than 5 rem if they had remained in invalidates the assumption in the calculation that the the work area for an additional five minutes. These entire dose was received in one puff release estimates were confirmed by the results of the licensees Calculation 21 -02.
16 NRC Regulatory Conference - March 1, 2022
Root Cause and Cor r ective Actions Sam Nappi Assistant Chemistry/Radiological Services Manager
17 NRC Regulatory Conference - March 1, 2022
Results of Causal Evaluations
- Direct Cause:
- Improper setup, use (without HEPA vacuum), and removal of a glove bag (engineering control) while performing pipe preparation activities.
- Root Cause:
- The Radiological Risk for the work was evaluated by staff presupposing the successful use of engineering controls to mitigate radiological hazards and didnt evaluate or recognize the overall risk associated with the work being performed or potential consequences of engineering control failure or incorrect use.
18 NRC Regulatory Conference - March 1, 2022
Completed Cor r ective Actions
- Immediate Corrective Actions:
- Stopped work
- Assigned additional resources
- Performed coaching to the RP supervision and Leads
- Ensured the remaining cuts were completed appropriately
- Actions Taken Since the Uptake Event
- Revised the radiological risk screening form for high contamination work
- Revised the Radiation Work Permit (RWP) procedure and Contamination Control Containment Devices procedure
- Developed a new procedure for RP outage preparation
19 NRC Regulatory Conference - March 1, 2022
Cor r ective Actions
- Additional Actions to Be Taken:
- Revising the radiological risk assessment procedure
- Provide training to individuals on how to assess radiological risk when elimination or mitigation actions are prescribed
- Revising the TEDE/ALARA evaluation process
- Require RWP revisions to be screened for changes in risk classification
- Establishing clear roles and responsibilities for glove bag use in HPI -12.90
- Formally perform culpability assessments per station procedures for the individuals involved
20 NRC Regulatory Conference - March 1, 2022
Significance Deter mination Desirée Wolfgramm Regulatory Affairs Manager
21 NRC Regulatory Conference - March 1, 2022
Perfor mance Deficiency and A ppar ent V iolations
Performance Deficiency Energy Northwest agrees with the Performance Deficiency Apparent Violation #1 Energy Northwest agrees with Apparent Violation #1 but suggest some wording changes to reflect the issue. The engineering control was not planned for with enough specificity in accordance with station procedures, specifically HPI-12.90, to ensure proper control for installation and removal to prevent airborne contamination Apparent Violation #2 Energy Northwest disagrees with Apparent Violation #2. The dose rates in the area at the time of the uptake event were less than those requiring continuous coverage Apparent Violation #3 Energy Northwest disagrees with Apparent Violation #3. Adequate dose surveys were completed in the field by RP Technicians during the work activity
22 NRC Regulatory Conference - March 1, 2022
Inspection Repor t Significance Deter mination Assessed under the NRC's Reactor Oversight Process (ROP) Occupational Radiation Safety Significance Determination Process (SDP) Inspection Manual Chapter (IMC) 0609 Appendix C:
Finding Identified
No No No NoWas the ALARA Was It An Was there A Ability to Planning or Over-Substantial Assess Dose Green Wo r k exposure? Potential? Compromised Controls? ?
Ye s No Was it a No SDE/DRP Whole Body White Exposure? Exposure in a VHRA?
23 NRC Regulatory Conference - March 1, 2022
Substantial Potential for Over exposur e IMC 0609 Appendix C II.C Substantial Potential for Overexposure An event presents a substantial potential when it was fortuitous that the resulting exposure did not exceed the limits of 10 CFR 20. The concern is not the significance of the resulting, or potential, exposure, but whether the licensee provided adequate controls over the situation, as required, to ensure the Part 20 dose limits are not exceeded. No credit is given for luck.
Required Controls per ALARA Plan and/or Station Procedures:
- Engineered Control - Glove bag
- Job coverage - RPT #2
- Direct Oversight - RP Supervisor at RMS
- Tele-dosimetry - RPT #3 at RMS
24 NRC Regulatory Conference - March 1, 2022
Substantial Potential for Over exposur e (cont.)
IMC 0609 Appendix C II.C Substantial Potential for Overexposure (continued)
When assessing whether a finding constitutes a substantial potential for overexposure, consider if it is possible to construct a reasonable scenario in which a minor alteration of circumstances (as they actually happened) would have resulted in a violation of the Part 20 limits. The following circumstances should be considered: timing, source strength, distance, and shielding.
"Fortuitous" circumstances as described in the Inspection Report, but through the root cause investigation were found to be pre-planned in the ALARA Plan and/or station procedures:
- RP tech (not credited as job coverage) was at the remote monitoring station with a view of the glove bag activity
- The RP tech viewed the grinding activity at the right point in time on the correct monitor and camera
- The RP tech had enough background information and/or experience to recognize the abnormal situation
- The RP tech only had a "40 foot/30 second" walking path to the entrance of the RWCU HX room from the remote monitoring station
25 NRC Regulatory Conference - March 1, 2022
Alter ation of Cir cumstances
From Inspection Report If the lead RP tech had not intervened, the additional time needed to clean up the area, gather tools, and leave the job in a safe work condition is a reasonable scenario with minor alterations [that] could have led to overexposure.
Additional Clarification from further investigation:
- Calculation 21- 002 assumptions are invalid
- Pipefitters completed work and left jobsite in a safe condition
26 NRC Regulatory Conference - March 1, 2022
Significance Deter mination
Assessed with additional information discovered through the root cause under the NRC's ROP Occupational Radiation Safety SDP IMC 0609 Appendix C:
Finding Identified
No No No NoWas the ALARA Was It An Was there A Ability to Planning or Over-Substantial Assess Dose Green Wo r k exposure? Potential? Compromised Controls? ?
Ye s No Was it a No SDE/DRP Whole Body White Exposure? Exposure in a VHRA?
27 NRC Regulatory Conference - March 1, 2022
Closing Comments Grover Hettel Vice President Nuclear Generation /
Chief Nuclear Officer
28