05000387/FIN-2015001-06: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
Line 12: Line 12:
| identified by = Licensee
| identified by = Licensee
| Inspection procedure =  
| Inspection procedure =  
| Inspector = A Turilin, F Bower, J Grieves, N Graneto, T Daun, T O,'Har
| Inspector = A Turilin, F Bower, J Grieves, N Graneto, T Daun, T O, 'Har
| CCA = N/A for ROP
| CCA = N/A for ROP
| INPO aspect =  
| INPO aspect =  
| description = 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires activities affecting quality be prescribed by documented procedures which include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished. On February 6, 2014, PPL identified that the startup and shutdown procedures for both Units 1 and 2 were inadequate such that they allowed operation of the RPV at a vacuum. This resulted in twenty-seven separate violations of TS 3.4.10, Reactor Coolant System Pressure and Temperature Limits, which requires RPV pressure to be maintained within limits at all times. The limits specified by TS 3.4.10 do not permit operating the RPV at a vacuum. Contrary to these requirements, on multiple occasions during startup and shutdowns over the past 3 years, PPL operated the RPV at a vacuum. PPL entered this issue into the corrective action program as CR-2014-06949. The inspectors determined that the finding was more than minor because it was associated with the procedure quality attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. The inspectors determined through a review of IMC 0609.04, Initial Characterization of Findings, and Exhibit 3 of IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, issued June 19, 2012, that the finding required a detailed risk evaluation since it was associated with the reactor coolant system boundary (e.g., pressurized thermal shock). Inspectors determined the finding to be of very low safety significance (Green) based on a qualitative assessment that there was no appreciable effect on the reactor pressure vessel as a barrier. Specifically, this conclusion was based on review of PPLs evaluation of acceptability of the RCS for continued operation, which determined that the stresses on a postulated crack, when the RPV is under vacuum conditions, would be less than the stresses when the RPV is under positive pressure conditions.
| description = 10 CFR 50 Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires activities affecting quality be prescribed by documented procedures which include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished. On February 6, 2014, PPL identified that the startup and shutdown procedures for both Units 1 and 2 were inadequate such that they allowed operation of the RPV at a vacuum. This resulted in twenty-seven separate violations of TS 3.4.10, Reactor Coolant System Pressure and Temperature Limits, which requires RPV pressure to be maintained within limits at all times. The limits specified by TS 3.4.10 do not permit operating the RPV at a vacuum. Contrary to these requirements, on multiple occasions during startup and shutdowns over the past 3 years, PPL operated the RPV at a vacuum. PPL entered this issue into the corrective action program as CR-2014-06949. The inspectors determined that the finding was more than minor because it was associated with the procedure quality attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. The inspectors determined through a review of IMC 0609.04, Initial Characterization of Findings, and Exhibit 3 of IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, issued June 19, 2012, that the finding required a detailed risk evaluation since it was associated with the reactor coolant system boundary (e.g., pressurized thermal shock). Inspectors determined the finding to be of very low safety significance (Green) based on a qualitative assessment that there was no appreciable effect on the reactor pressure vessel as a barrier. Specifically, this conclusion was based on review of PPLs evaluation of acceptability of the RCS for continued operation, which determined that the stresses on a postulated crack, when the RPV is under vacuum conditions, would be less than the stresses when the RPV is under positive pressure conditions.
}}
}}

Revision as of 20:52, 20 February 2018

06
Site: Susquehanna Talen Energy icon.png
Report IR 05000387/2015001 Section 4OA7
Date counted Mar 31, 2015 (2015Q1)
Type: NCV: Green
cornerstone Mitigating Systems
Identified by: Licensee-identified
Inspection Procedure:
Inspectors (proximate) A Turilin
F Bower
J Grieves
N Graneto
T Daun
T O
'Har
Violation of: 10 CFR 50 Appendix B Criterion V

Technical Specification

Technical Specification - Procedures
INPO aspect
'