{{#Wiki_filter:March 26, 2003 Mr. J. S. Keenan Vice President Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461
 
==SUBJECT:==
BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 - REQUEST FOR RELIEF FROM THIRD 10-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN REQUEST FOR RELIEF RR-31 (TAC NOS. MB5631 AND MB5632)
 
==Dear Mr. Keenan:==
 
In a letter dated July 16, 2002, as supplemented February 11, 2003, Carolina Power & Light Company (CP&L, the licensee) submitted Relief Request RR-31 for the third 10-year interval inservice inspection program for the Brunswick Steam Electric Plant (BSEP), Units 1 and 2. In Relief Request RR-31, the licensee proposed an alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code (Code), Section XI, Appendix VIII, Supplement 11 requirements. In lieu of the Code requirements, the licensee proposed using the qualification process as administered by the Electric Power Research Institute Performance Demonstration Initiative for weld overlay qualifications. The proposed alternative is for the third 10-year interval, which began on May 11, 1998, and ends on May 10, 2008.
The NRC staff, with technical assistance from its contractor, Pacific Northwest National Laboratory (PNNL), has reviewed and evaluated the information provided in Relief Request RR-31 and the associated proposed alternative testing method against the requirements of the ASME B&PV Code, 1989 Edition, which was referenced in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a. The NRC staff has found the licensees request to use the proposed alternative acceptable. Pursuant to 10 CFR 50.55a(a)(3)(i), Relief Request RR-31 is authorized based on the alternative providing an acceptable level of quality and safety.
The NRC staff's evaluation and conclusions are contained in the Safety Evaluation (SE) provided in the enclosure. The evaluation provided by PNNL is the Technical Letter Report provided as an attachment to the SE.
 
J. S. Keenan                                  If you have any questions regarding this issue, please contact Ms. Brenda Mozafari at 301-415-2020 or by e-mail at blm@nrc.gov.
Sincerely,
                                              /RA/
Allen G. Howe, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324
 
==Enclosure:==
Safety Evaluation
 
J. S. Keenan                                  If you have any questions regarding this issue, please contact Ms. Brenda Mozafari at 301-415-2020 or by e-mail at blm@nrc.gov.
Sincerely,
                                              /RA/
Allen G. Howe, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324
 
==Enclosure:==
Safety Evaluation cc w/encl: See next page DISTRIBUTION:
PUBLIC                AHowe          EDunnington            ACRS PDII-2 Reading        BMozafari      OGC                    PFredrickson, RII
 
==Attachment:==
ML030860823                              *No substantial changes to SE ADAMS ACCESSION NO. ML030860525                      Package: ML0308 OFFICE    PDII-2/PM    PDII-2/LA        SE*          OGC          PDII-2/SC NAME      BMozafari    EDunnington      TChan        RHoefling    AHowe DATE      03/18/03      03/18/03          03/14 /03    03/24/03    03/26/03 OFFICIAL RECORD COPY
 
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION FOR THIRD 10-YEAR INTERVAL INSERVICE INSPECTION REQUEST FOR RELIEF RR-31 FOR BRUNSWICK ELECTRIC PLANT, UNITS 1 AND 2 CAROLINA POWER & LIGHT COMPANY DOCKET NOS. 50-325 AND 50-324
 
==1.0 INTRODUCTION==
 
The staff of the U.S. Nuclear Regulatory Commission (NRC), with technical assistance from its contractor, Pacific Northwest National Laboratory (PNNL), reviewed and evaluated the information submitted by Carolina Power & Light Company (CP&L, the licensee) in a letter dated July 16, 2002. The licensee proposed an alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code, Section XI, Appendix VIII, Supplement 11, Qualification Requirements for Full Structural Overlaid Wrought Austenitic Piping Welds, requirements at Brunswick Steam Electric Plant (BSEP), Units 1 and 2. In lieu of the Code requirements, the licensee proposed using the qualification process as administered by the Electric Power Research Institute (EPRI) Performance Demonstration Initiative (PDI) for weld overlay qualifications. In a telephone discussion with the NRC staff on December 17, 2002, the NRC staff requested that CP&L provide additional information regarding the relief request. The information requested was the same information requested of Southern Nuclear Operating Company (SNC) for the Edwin I. Hatch Nuclear Plant and referenced in the SNC response dated October 4, 2002 (ADAMS Accession Number ML0228200260). The licensee provided a response to each RAI question in a letter dated February 11, 2003.
2.0 REGULATORY REQUIREMENTS Inservice inspection (ISI) of the ASME Code Class 1, 2, and 3 components is performed in accordance with Section XI of the ASME B&PV Code and applicable addenda as required by Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(g), except where specific written relief has been granted by the Commission pursuant to 10 CFR 50.55a(g)(6)(i). The requirements of 10 CFR 50.55a(a)(3) state that alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if: (i) the proposed alternatives
 
would provide an acceptable level of quality and safety or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the pre-service examination requirements, set forth in the ASME Code, Section XI, "Rules for Inservice Inspection (ISI) of Nuclear Power Plant Components," to the extent practical within the limitations of design, geometry, and materials of construction of the components. The regulations require that inservice examination of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of Section XI of the ASME Code incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein. The applicable Code of record for the third 10-year ISI for BSEP, Units 1 and 2, is the 1989 Edition of the ASME Code, Section XI and the 1995 Edition with 1996 Addenda of Appendix VIII of Section XI of the ASME Code.
 
==3.0 TECHNICAL EVALUATION==
 
The U.S. nuclear utilities created the PDI to implement performance demonstration requirements contained in Appendix VIII of Section XI of the Code. To this end, PDI has developed a program for qualifying equipment, procedures, and personnel in accordance with the ultrasonic testing criteria of Appendix VIII, Supplement 11. Prior to the Supplement 11 program, EPRI was maintaining a performance demonstration program for weld overlay qualification under the Tri-party Agreement.1 Instead of having two programs with similar objectives, the NRC staff recognized the PDI program for weld overlay qualifications as an acceptable alternative to theTri-party Agreement.2 The PDI program does not fully comport with the existing requirements of Supplement 11. PDI presented the differences at public meetings in which the NRC participated.3,4 The differences are in flaw location within test specimens and fabricated flaw tolerances. The changes in flaw location permitted using test specimens from the Tri-party Agreement, and the changes in fabricated flaw tolerances provide ultrasonic testing acoustic responses similar to the responses associated with an intergranular stress corrosion crack. Based on the discussion at these 1        The Tri-party Agreement is between NRC, EPRI, and the Boiling Water Reactor Owners Group (BWROG),
Coordination Plan for NRC/EPRI/BWROG Training and Qualification Activities of NDE (Nondestructive Examination) Personnel, July 3, 1984.
2        Letter from William H. Bateman to Michael Bratton, Weld Overlay Performance Demonstration Administered by PDI as an Alternative for Generic Letter 88-01 Recommendations, January 15, 2002.
(ADAMS Accession Number: ML020160532) 3        Memorandum from Donald G. Naujock to Terence Chan, Summary of Public Meeting Held January 31 -
February 2, 2002, with PDI Representatives, March 22, 2001. (ADAMS Accession Number:
ML010940402) 4        Memorandum from Donald G. Naujock to Terence Chan, Summary of Public Meeting Held June 12 through June 14, 2001, with PDI Representatives, November 29, 2001. (ADAMS Accession Number:
ML013330156)
 
public meetings and the review presented in the technical letter report (TLR) (Attachment), the NRC staff determined that the PDI program provides assurance of an acceptable level of quality and safety.
The NRC staff adopts PNNLs TLR with its evaluations and recommendations of the proposed alternative.
 
==4.0 CONCLUSION==
 
The NRC staff adopts the evaluations and recommendations for authorizing alternatives contained in the TLR prepared by PNNL.
The NRC staff has determined that the licensees proposed alternative (RR-31) to use the PDI program for weld overlay qualifications as described in the submittal as supplemented, in lieu of Supplement 11 to Appendix VIII of Section XI of the Code, will provide an acceptable level of quality and safety. Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), the proposed alternative in Relief Request RR-31 is authorized for the third 10-year ISI interval at BSEP, Units 1 and 2.
All other requirements of the ASME Code, Section XI for which relief has not been specifically requested remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
 
==Attachment:==
 
Technical Letter Report Principal Contributor: D. G. Naujock Date: March 26, 2003
 
Mr. J. S. Keenan                        Brunswick Steam Electric Plant Carolina Power & Light Company          Units 1 and 2 cc:
Steven R. Carr                          Ms. Margaret A. Force Associate General Counsel - Legal      Assistant Attorney General Department                              State of North Carolina Progress Energy Service Company, LLC    Post Office Box 629 Post Office Box 1551                    Raleigh, North Carolina 27602 Raleigh, North Carolina 27602-1551 Mr. Robert P. Gruber Mr. David R. Sandifer, Chairperson      Executive Director Brunswick County Board of Commissioners Public Staff - NCUC Post Office Box 249                    4326 Mail Service Center Bolivia, North Carolina 28422          Raleigh, North Carolina 27699-4326 Resident Inspector                      Mr. C. J. Gannon U. S. Nuclear Regulatory Commission    Director - Site Operations 8470 River Road                        Carolina Power & Light Company Southport, North Carolina 28461        Brunswick Steam Electric Plant Post Office Box 10429 Mr. John H. ONeill, Jr.                Southport, North Carolina 28461-0429 Shaw, Pittman, Potts & Trowbridge 2300 N Street NW.                      Mr. Norman R. Holden, Mayor Washington, DC 20037-1128              City of Southport 201 East Moore Street Ms. Beverly Hall, Section Chief        Southport, North Carolina 28461 Division of Radiation Protection N.C. Department of Environment          Mr. Dan E. Summers and Natural Resources                Emergency Management Coordinator 3825 Barrett Dr.                        New Hanover County Department of Raleigh, North Carolina 27609-7721        Emergency Management Post Office Box 1525 Mr. W. C. Noll                          Wilmington, North Carolina 28402 Plant Manager Carolina Power & Light Company          Mr. James W. Holt, Manager Brunswick Steam Electric Plant          Performance Evaluation and Post Office Box 10429                      Regulatory Affairs PEB 7 Southport, North Carolina 28461        Progress Energy Post Office Box 1551 Public Service Commission              Raleigh, North Carolina 27602-1551 State of South Carolina Post Office Drawer 11649                Mr. Edward T. ONeil Columbia, South Carolina 29211          Manager - Support Services Carolina Power & Light Company Brunswick Steam Electric Plant Post Office Box 10249 Southport, North Carolina 28461}}

Latest revision as of 23:31, 25 March 2020

Request for Relief from Third 10-Year Interval Inservice Inspection Program Plan Request for Relief RR-31
ML030860525
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 03/26/2003
From: Howe A
NRC/NRR/DLPM/LPD2
To: Keenan J
Carolina Power & Light Co
mozafari B, NRR/DLPM, 415-2020
References
TAC MB5631, TAC MB5632
Download: ML030860525 (8)


Text

March 26, 2003 Mr. J. S. Keenan Vice President Brunswick Steam Electric Plant Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461

SUBJECT:

BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 - REQUEST FOR RELIEF FROM THIRD 10-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN REQUEST FOR RELIEF RR-31 (TAC NOS. MB5631 AND MB5632)

Dear Mr. Keenan:

In a letter dated July 16, 2002, as supplemented February 11, 2003, Carolina Power & Light Company (CP&L, the licensee) submitted Relief Request RR-31 for the third 10-year interval inservice inspection program for the Brunswick Steam Electric Plant (BSEP), Units 1 and 2. In Relief Request RR-31, the licensee proposed an alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code (Code),Section XI, Appendix VIII, Supplement 11 requirements. In lieu of the Code requirements, the licensee proposed using the qualification process as administered by the Electric Power Research Institute Performance Demonstration Initiative for weld overlay qualifications. The proposed alternative is for the third 10-year interval, which began on May 11, 1998, and ends on May 10, 2008.

The NRC staff, with technical assistance from its contractor, Pacific Northwest National Laboratory (PNNL), has reviewed and evaluated the information provided in Relief Request RR-31 and the associated proposed alternative testing method against the requirements of the ASME B&PV Code, 1989 Edition, which was referenced in Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a. The NRC staff has found the licensees request to use the proposed alternative acceptable. Pursuant to 10 CFR 50.55a(a)(3)(i), Relief Request RR-31 is authorized based on the alternative providing an acceptable level of quality and safety.

The NRC staff's evaluation and conclusions are contained in the Safety Evaluation (SE) provided in the enclosure. The evaluation provided by PNNL is the Technical Letter Report provided as an attachment to the SE.

J. S. Keenan If you have any questions regarding this issue, please contact Ms. Brenda Mozafari at 301-415-2020 or by e-mail at blm@nrc.gov.

Sincerely,

/RA/

Allen G. Howe, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324

Enclosure:

Safety Evaluation

J. S. Keenan If you have any questions regarding this issue, please contact Ms. Brenda Mozafari at 301-415-2020 or by e-mail at blm@nrc.gov.

Sincerely,

/RA/

Allen G. Howe, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324

Enclosure:

Safety Evaluation cc w/encl: See next page DISTRIBUTION:

PUBLIC AHowe EDunnington ACRS PDII-2 Reading BMozafari OGC PFredrickson, RII

Attachment:

ML030860823 *No substantial changes to SE ADAMS ACCESSION NO. ML030860525 Package: ML0308 OFFICE PDII-2/PM PDII-2/LA SE* OGC PDII-2/SC NAME BMozafari EDunnington TChan RHoefling AHowe DATE 03/18/03 03/18/03 03/14 /03 03/24/03 03/26/03 OFFICIAL RECORD COPY

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION FOR THIRD 10-YEAR INTERVAL INSERVICE INSPECTION REQUEST FOR RELIEF RR-31 FOR BRUNSWICK ELECTRIC PLANT, UNITS 1 AND 2 CAROLINA POWER & LIGHT COMPANY DOCKET NOS. 50-325 AND 50-324

1.0 INTRODUCTION

The staff of the U.S. Nuclear Regulatory Commission (NRC), with technical assistance from its contractor, Pacific Northwest National Laboratory (PNNL), reviewed and evaluated the information submitted by Carolina Power & Light Company (CP&L, the licensee) in a letter dated July 16, 2002. The licensee proposed an alternative to the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code,Section XI, Appendix VIII, Supplement 11, Qualification Requirements for Full Structural Overlaid Wrought Austenitic Piping Welds, requirements at Brunswick Steam Electric Plant (BSEP), Units 1 and 2. In lieu of the Code requirements, the licensee proposed using the qualification process as administered by the Electric Power Research Institute (EPRI) Performance Demonstration Initiative (PDI) for weld overlay qualifications. In a telephone discussion with the NRC staff on December 17, 2002, the NRC staff requested that CP&L provide additional information regarding the relief request. The information requested was the same information requested of Southern Nuclear Operating Company (SNC) for the Edwin I. Hatch Nuclear Plant and referenced in the SNC response dated October 4, 2002 (ADAMS Accession Number ML0228200260). The licensee provided a response to each RAI question in a letter dated February 11, 2003.

2.0 REGULATORY REQUIREMENTS Inservice inspection (ISI) of the ASME Code Class 1, 2, and 3 components is performed in accordance with Section XI of the ASME B&PV Code and applicable addenda as required by Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(g), except where specific written relief has been granted by the Commission pursuant to 10 CFR 50.55a(g)(6)(i). The requirements of 10 CFR 50.55a(a)(3) state that alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if: (i) the proposed alternatives

would provide an acceptable level of quality and safety or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.

Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the pre-service examination requirements, set forth in the ASME Code,Section XI, "Rules for Inservice Inspection (ISI) of Nuclear Power Plant Components," to the extent practical within the limitations of design, geometry, and materials of construction of the components. The regulations require that inservice examination of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of Section XI of the ASME Code incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein. The applicable Code of record for the third 10-year ISI for BSEP, Units 1 and 2, is the 1989 Edition of the ASME Code,Section XI and the 1995 Edition with 1996 Addenda of Appendix VIII of Section XI of the ASME Code.

3.0 TECHNICAL EVALUATION

The U.S. nuclear utilities created the PDI to implement performance demonstration requirements contained in Appendix VIII of Section XI of the Code. To this end, PDI has developed a program for qualifying equipment, procedures, and personnel in accordance with the ultrasonic testing criteria of Appendix VIII, Supplement 11. Prior to the Supplement 11 program, EPRI was maintaining a performance demonstration program for weld overlay qualification under the Tri-party Agreement.1 Instead of having two programs with similar objectives, the NRC staff recognized the PDI program for weld overlay qualifications as an acceptable alternative to theTri-party Agreement.2 The PDI program does not fully comport with the existing requirements of Supplement 11. PDI presented the differences at public meetings in which the NRC participated.3,4 The differences are in flaw location within test specimens and fabricated flaw tolerances. The changes in flaw location permitted using test specimens from the Tri-party Agreement, and the changes in fabricated flaw tolerances provide ultrasonic testing acoustic responses similar to the responses associated with an intergranular stress corrosion crack. Based on the discussion at these 1 The Tri-party Agreement is between NRC, EPRI, and the Boiling Water Reactor Owners Group (BWROG),

Coordination Plan for NRC/EPRI/BWROG Training and Qualification Activities of NDE (Nondestructive Examination) Personnel, July 3, 1984.

2 Letter from William H. Bateman to Michael Bratton, Weld Overlay Performance Demonstration Administered by PDI as an Alternative for Generic Letter 88-01 Recommendations, January 15, 2002.

(ADAMS Accession Number: ML020160532) 3 Memorandum from Donald G. Naujock to Terence Chan, Summary of Public Meeting Held January 31 -

February 2, 2002, with PDI Representatives, March 22, 2001. (ADAMS Accession Number:

ML010940402) 4 Memorandum from Donald G. Naujock to Terence Chan, Summary of Public Meeting Held June 12 through June 14, 2001, with PDI Representatives, November 29, 2001. (ADAMS Accession Number:

ML013330156)

public meetings and the review presented in the technical letter report (TLR) (Attachment), the NRC staff determined that the PDI program provides assurance of an acceptable level of quality and safety.

The NRC staff adopts PNNLs TLR with its evaluations and recommendations of the proposed alternative.

4.0 CONCLUSION

The NRC staff adopts the evaluations and recommendations for authorizing alternatives contained in the TLR prepared by PNNL.

The NRC staff has determined that the licensees proposed alternative (RR-31) to use the PDI program for weld overlay qualifications as described in the submittal as supplemented, in lieu of Supplement 11 to Appendix VIII of Section XI of the Code, will provide an acceptable level of quality and safety. Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), the proposed alternative in Relief Request RR-31 is authorized for the third 10-year ISI interval at BSEP, Units 1 and 2.

All other requirements of the ASME Code,Section XI for which relief has not been specifically requested remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.

Attachment:

Technical Letter Report Principal Contributor: D. G. Naujock Date: March 26, 2003

Mr. J. S. Keenan Brunswick Steam Electric Plant Carolina Power & Light Company Units 1 and 2 cc:

Steven R. Carr Ms. Margaret A. Force Associate General Counsel - Legal Assistant Attorney General Department State of North Carolina Progress Energy Service Company, LLC Post Office Box 629 Post Office Box 1551 Raleigh, North Carolina 27602 Raleigh, North Carolina 27602-1551 Mr. Robert P. Gruber Mr. David R. Sandifer, Chairperson Executive Director Brunswick County Board of Commissioners Public Staff - NCUC Post Office Box 249 4326 Mail Service Center Bolivia, North Carolina 28422 Raleigh, North Carolina 27699-4326 Resident Inspector Mr. C. J. Gannon U. S. Nuclear Regulatory Commission Director - Site Operations 8470 River Road Carolina Power & Light Company Southport, North Carolina 28461 Brunswick Steam Electric Plant Post Office Box 10429 Mr. John H. ONeill, Jr. Southport, North Carolina 28461-0429 Shaw, Pittman, Potts & Trowbridge 2300 N Street NW. Mr. Norman R. Holden, Mayor Washington, DC 20037-1128 City of Southport 201 East Moore Street Ms. Beverly Hall, Section Chief Southport, North Carolina 28461 Division of Radiation Protection N.C. Department of Environment Mr. Dan E. Summers and Natural Resources Emergency Management Coordinator 3825 Barrett Dr. New Hanover County Department of Raleigh, North Carolina 27609-7721 Emergency Management Post Office Box 1525 Mr. W. C. Noll Wilmington, North Carolina 28402 Plant Manager Carolina Power & Light Company Mr. James W. Holt, Manager Brunswick Steam Electric Plant Performance Evaluation and Post Office Box 10429 Regulatory Affairs PEB 7 Southport, North Carolina 28461 Progress Energy Post Office Box 1551 Public Service Commission Raleigh, North Carolina 27602-1551 State of South Carolina Post Office Drawer 11649 Mr. Edward T. ONeil Columbia, South Carolina 29211 Manager - Support Services Carolina Power & Light Company Brunswick Steam Electric Plant Post Office Box 10249 Southport, North Carolina 28461