Line 3: Line 3:
| issue date = 12/27/2006
| issue date = 12/27/2006
| title = Withdrawal of Amendment Extension of Technical Specification 3.8.3.1, Onsite Power Distribution
| title = Withdrawal of Amendment Extension of Technical Specification 3.8.3.1, Onsite Power Distribution
| author name = Miller G E
| author name = Miller G
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-2
| author affiliation = NRC/NRR/ADRO/DORL/LPLI-2
| addressee name = Peschel J M, St.Pierre G
| addressee name = Peschel J, St.Pierre G
| addressee affiliation = Florida Power & Light Energy Seabrook, LLC
| addressee affiliation = Florida Power & Light Energy Seabrook, LLC
| docket = 05000443
| docket = 05000443
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:December 27, 2006Mr. Gene St. Pierre, Site Vice Presidentc/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874
{{#Wiki_filter:December 27, 2006 Mr. Gene St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874


==SUBJECT:==
==SUBJECT:==
SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE: EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, "ONSITE POWER DISCTIBUTION" (TAC NO. MC9165)
SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE:
EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, ONSITE POWER DISCTIBUTION (TAC NO. MC9165)


==Dear Mr. St. Pierre:==
==Dear Mr. St. Pierre:==


By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, andOctober 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, "Onsite Power Distribution," to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days.
By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, and October 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days.
As part of the Nuclear Regulatory Commission (NRC or the Commission) staff's review, an independent analysis of the proposed change was performed. While the NRC staff's analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request. The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment toFacility Operating License with the Office of the Federal Register for publication.Sincerely,/RA/   G. Edward Miller, Project ManagerPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-443
As part of the Nuclear Regulatory Commission (NRC or the Commission) staffs review, an independent analysis of the proposed change was performed. While the NRC staffs analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request.
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.
Sincerely,
                                              /RA/
G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443


==Enclosure:==
==Enclosure:==
Notice of Withdrawalcc w/encl:  See next page Seabrook Station, Unit No. 1 cc:
Mr. J. A. StallSenior Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL  33408-0420Mr. Peter BrannAssistant Attorney General State House, Station #6 Augusta, ME  04333Resident InspectorU.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH  03874Town of Exeter10 Front Street Exeter, NH  03823Regional Administrator, Region IU.S. Nuclear Regulatory Commission


475 Allendale Road King of Prussia, PA  19406Office of the Attorney GeneralOne Ashburton Place, 20th Floor Boston, MA  02108Board of SelectmenTown of Amesbury Town Hall Amesbury, MA  01913Mr. Robert PooleFederal Emergency Management Agency Region I J.W. McCormack P.O. &
Notice of Withdrawal cc w/encl: See next page
Courthouse Building, Room 401 Boston, MA 02109Mr. Tom CrimminsPolestar Applied Technology One First Street, Suite 4 Los Altos, CA  94019Ms. Cristine McComb, DirectorATTN: John Giarrusso Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399Ms. Kelly Ayotte, Attorney GeneralMr. Orvil Fitch, Deputy Attorney General 33 Capitol Street Concord, NH 03301Mr. Christopher M. Pope, DirectorHomeland Security & Emergency Mgmt.
 
New Hampshire Department of Safety Bureau of Emergency Management 33 Hazen Drive Concord, NH 03301Mr. M. S. Ross, Managing AttorneyFlorida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420Mr. Rajiv S. KundalkarVice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420James M. PeschelRegulatory Programs Manager FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874Ms. Marjan MashhadiSenior Attorney Florida Power & Light Company 801 Pennsylvania Ave., NW Suite 220 Washington, DC 20004 Seabrook Station, Unit No. 1 cc:
Seabrook Station, Unit No. 1 cc:
Mr. Mark E. WarnerVice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 7590-01-PUNITED STATES NUCLEAR REGULATORY COMMISSIONFPL ENERGY SEABROOK, LLCDOCKET NO. 50-443NOTICE OF WITHDRAWAL OF APPLICATION FORAMENDMENT TO FACILITY OPERATING LICENSEThe U.S. Nuclear Regulatory Commission (NRC or the Commission) has granted therequest of FPL Energy Seabrook, LLC (the licensee) to withdraw its December 6, 2005, application (as supplemented by letters dated March 30, 2006, and October 1, 2006) for a proposed amendment to Facility Operating License No. NPF-86 for Seabrook Station, Unit No. 1, located in Rockingham County.                   The proposed amendment would have modified Technical Specification (TS) 3.8.3.1,"Onsite Power Distribution," to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days. The Commission had previously issued a Notice of Consideration of Issuance ofAmendment published in the FEDERAL REGISTER on January 17, 2006 (71 FR 2592).
Mr. J. A. Stall                    Ms. Cristine McComb, Director Senior Vice President, Nuclear and ATTN: John Giarrusso Chief Nuclear Officer              Massachusetts Emergency Management Agency Florida Power & Light Company      400 Worcester Road P.O. Box 14000                      Framingham, MA 01702-5399 Juno Beach, FL 33408-0420 Ms. Kelly Ayotte, Attorney General Mr. Peter Brann                    Mr. Orvil Fitch, Deputy Attorney General Assistant Attorney General          33 Capitol Street State House, Station #6            Concord, NH 03301 Augusta, ME 04333 Mr. Christopher M. Pope, Director Resident Inspector                  Homeland Security & Emergency Mgmt.
However, by letter dated September 26, 2006, the licensee withdrew the proposed change.For further details with respect to this action, see the application for amendment datedDecember 6, 2005 (as supplemented by letters dated March 30, 2006, and October 1, 2006),
U.S. Nuclear Regulatory Commission  New Hampshire Department of Safety Seabrook Nuclear Power Station      Bureau of Emergency Management P.O. Box 1149                      33 Hazen Drive Seabrook, NH 03874                  Concord, NH 03301 Town of Exeter                      Mr. M. S. Ross, Managing Attorney 10 Front Street                    Florida Power & Light Company Exeter, NH 03823                    P.O. Box 14000 Juno Beach, FL 33408-0420 Regional Administrator, Region I U.S. Nuclear Regulatory Commission  Mr. Rajiv S. Kundalkar 475 Allendale Road                  Vice President - Nuclear Engineering King of Prussia, PA 19406          Florida Power & Light Company P.O. Box 14000 Office of the Attorney General      Juno Beach, FL 33408-0420 One Ashburton Place, 20th Floor Boston, MA 02108                    James M. Peschel Regulatory Programs Manager Board of Selectmen                  FPL Energy Seabrook, LLC Town of Amesbury                    PO Box 300 Town Hall                          Seabrook, NH 03874 Amesbury, MA 01913 Ms. Marjan Mashhadi Mr. Robert Poole                    Senior Attorney Federal Emergency Management Agency Florida Power & Light Company Region I                            801 Pennsylvania Ave., NW Suite 220 J.W. McCormack P.O. &              Washington, DC 20004 Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019
and the licensee's letter dated December 20, 2006, which withdrew the application for license amendment. Documents may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly-available records will be accessible electronically from the Agencywide Documents Access and Management Systems (ADAMS) Public Electronic Reading Room on the internet at the NRC Web site, http://www.nrc.gov/reading-rm.html. Persons who do not have access to ADAMS or whoencounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by email to pdr@nrc.gov
 
. Dated at Rockville, Maryland, this 27th day of December, 2006FOR THE NUCLEAR REGULATORY COMMISSION/RA/   G. Edward Miller, Project ManagerPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation December 27, 2006Mr. Gene St. Pierre, Site Vice Presidentc/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874
Seabrook Station, Unit No. 1 cc:
Mr. Mark E. Warner Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420
 
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION FPL ENERGY SEABROOK, LLC DOCKET NO. 50-443 NOTICE OF WITHDRAWAL OF APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE The U.S. Nuclear Regulatory Commission (NRC or the Commission) has granted the request of FPL Energy Seabrook, LLC (the licensee) to withdraw its December 6, 2005, application (as supplemented by letters dated March 30, 2006, and October 1, 2006) for a proposed amendment to Facility Operating License No. NPF-86 for Seabrook Station, Unit No. 1, located in Rockingham County.
The proposed amendment would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days.
The Commission had previously issued a Notice of Consideration of Issuance of Amendment published in the FEDERAL REGISTER on January 17, 2006 (71 FR 2592).
However, by letter dated September 26, 2006, the licensee withdrew the proposed change.
For further details with respect to this action, see the application for amendment dated December 6, 2005 (as supplemented by letters dated March 30, 2006, and October 1, 2006),
and the licensee's letter dated December 20, 2006, which withdrew the application for license amendment. Documents may be examined, and/or copied for a fee, at the NRCs Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly-available records will be accessible electronically from the Agencywide Documents Access and Management Systems (ADAMS) Public Electronic Reading Room on the internet at the NRC Web site,
 
http://www.nrc.gov/reading-rm.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by email to pdr@nrc.gov.
Dated at Rockville, Maryland, this 27th day of December, 2006 FOR THE NUCLEAR REGULATORY COMMISSION
                                      /RA/
G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
 
December 27, 2006 Mr. Gene St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874


==SUBJECT:==
==SUBJECT:==
SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE: EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, "ONSITE POWER DISCTIBUTION" (TAC NO. MC9165)
SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE:
EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, ONSITE POWER DISCTIBUTION (TAC NO. MC9165)


==Dear Mr. St. Pierre:==
==Dear Mr. St. Pierre:==


By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, andOctober 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, "Onsite Power Distribution," to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days.
By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, and October 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours to 7 days.
As part of the Nuclear Regulatory Commission (NRC or the Commission) staff's review, an independent analysis of the proposed change was performed. While the NRC staff's analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request. The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment toFacility Operating License with the Office of the Federal Register for publication.Sincerely,/RA/   G. Edward Miller, Project ManagerPlant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-443Distribution
As part of the Nuclear Regulatory Commission (NRC or the Commission) staffs review, an independent analysis of the proposed change was performed. While the NRC staffs analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request.
:PUBLICRidsNrrLACRaynorJChung PDI-2 R/FRidsOgcRpMMcConnell RidsNrrDlpmLpdI-2RidsAcrsAcnwMailCenterGWilson RidsNrrPMGMillerRidsRgn1MailCenterGMorris RISNrrDorlDprLMrowca Accession Number: ML063560237NRR106OFFICELPL1-2/PMLPL1-2/LALPL1-2/BCNAMEGEMillerCRaynorHChernoffDATE12/27/0612/27/0612/26/06OFFICIAL RECORD COPY}}
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.
Sincerely,
                                              /RA/
G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 Distribution:
PUBLIC                                RidsNrrLACRaynor            JChung PDI-2 R/F                              RidsOgcRp                    MMcConnell RidsNrrDlpmLpdI-2                      RidsAcrsAcnwMailCenter      GWilson RidsNrrPMGMiller                      RidsRgn1MailCenter          GMorris RISNrrDorlDpr                          LMrowca Accession Number: ML063560237                              NRR106 OFFICE      LPL1-2/PM      LPL1-2/LA        LPL1-2/BC NAME        GEMiller      CRaynor          HChernoff DATE        12/27/06      12/27/06          12/26/06 OFFICIAL RECORD COPY}}

Latest revision as of 12:05, 23 November 2019

Withdrawal of Amendment Extension of Technical Specification 3.8.3.1, Onsite Power Distribution
ML063560237
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 12/27/2006
From: Geoffrey Miller
NRC/NRR/ADRO/DORL/LPLI-2
To: Peschel J, St.Pierre G
Florida Power & Light Energy Seabrook
miller g e
References
TAC MC9165
Download: ML063560237 (6)


Text

December 27, 2006 Mr. Gene St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE:

EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, ONSITE POWER DISCTIBUTION (TAC NO. MC9165)

Dear Mr. St. Pierre:

By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, and October 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 7 days.

As part of the Nuclear Regulatory Commission (NRC or the Commission) staffs review, an independent analysis of the proposed change was performed. While the NRC staffs analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request.

The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.

Sincerely,

/RA/

G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443

Enclosure:

Notice of Withdrawal cc w/encl: See next page

Seabrook Station, Unit No. 1 cc:

Mr. J. A. Stall Ms. Cristine McComb, Director Senior Vice President, Nuclear and ATTN: John Giarrusso Chief Nuclear Officer Massachusetts Emergency Management Agency Florida Power & Light Company 400 Worcester Road P.O. Box 14000 Framingham, MA 01702-5399 Juno Beach, FL 33408-0420 Ms. Kelly Ayotte, Attorney General Mr. Peter Brann Mr. Orvil Fitch, Deputy Attorney General Assistant Attorney General 33 Capitol Street State House, Station #6 Concord, NH 03301 Augusta, ME 04333 Mr. Christopher M. Pope, Director Resident Inspector Homeland Security & Emergency Mgmt.

U.S. Nuclear Regulatory Commission New Hampshire Department of Safety Seabrook Nuclear Power Station Bureau of Emergency Management P.O. Box 1149 33 Hazen Drive Seabrook, NH 03874 Concord, NH 03301 Town of Exeter Mr. M. S. Ross, Managing Attorney 10 Front Street Florida Power & Light Company Exeter, NH 03823 P.O. Box 14000 Juno Beach, FL 33408-0420 Regional Administrator, Region I U.S. Nuclear Regulatory Commission Mr. Rajiv S. Kundalkar 475 Allendale Road Vice President - Nuclear Engineering King of Prussia, PA 19406 Florida Power & Light Company P.O. Box 14000 Office of the Attorney General Juno Beach, FL 33408-0420 One Ashburton Place, 20th Floor Boston, MA 02108 James M. Peschel Regulatory Programs Manager Board of Selectmen FPL Energy Seabrook, LLC Town of Amesbury PO Box 300 Town Hall Seabrook, NH 03874 Amesbury, MA 01913 Ms. Marjan Mashhadi Mr. Robert Poole Senior Attorney Federal Emergency Management Agency Florida Power & Light Company Region I 801 Pennsylvania Ave., NW Suite 220 J.W. McCormack P.O. & Washington, DC 20004 Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019

Seabrook Station, Unit No. 1 cc:

Mr. Mark E. Warner Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION FPL ENERGY SEABROOK, LLC DOCKET NO. 50-443 NOTICE OF WITHDRAWAL OF APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE The U.S. Nuclear Regulatory Commission (NRC or the Commission) has granted the request of FPL Energy Seabrook, LLC (the licensee) to withdraw its December 6, 2005, application (as supplemented by letters dated March 30, 2006, and October 1, 2006) for a proposed amendment to Facility Operating License No. NPF-86 for Seabrook Station, Unit No. 1, located in Rockingham County.

The proposed amendment would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 7 days.

The Commission had previously issued a Notice of Consideration of Issuance of Amendment published in the FEDERAL REGISTER on January 17, 2006 (71 FR 2592).

However, by letter dated September 26, 2006, the licensee withdrew the proposed change.

For further details with respect to this action, see the application for amendment dated December 6, 2005 (as supplemented by letters dated March 30, 2006, and October 1, 2006),

and the licensee's letter dated December 20, 2006, which withdrew the application for license amendment. Documents may be examined, and/or copied for a fee, at the NRCs Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly-available records will be accessible electronically from the Agencywide Documents Access and Management Systems (ADAMS) Public Electronic Reading Room on the internet at the NRC Web site,

http://www.nrc.gov/reading-rm.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by email to pdr@nrc.gov.

Dated at Rockville, Maryland, this 27th day of December, 2006 FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

December 27, 2006 Mr. Gene St. Pierre, Site Vice President c/o James M. Peschel Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF AMENDMENT RE:

EXTENSION OF TECHNICAL SPECIFICATION 3.8.3.1, ONSITE POWER DISCTIBUTION (TAC NO. MC9165)

Dear Mr. St. Pierre:

By letter dated December 6, 2005, as supplemented by letters dated March 30, 2006, and October 1, 2006, FPL Energy Seabrook, LLC (FPLE) applied for an amendment to the Seabrook Station, Unit No. 1 Facility Operating License No. NPF-86. The proposed change would have modified Technical Specification (TS) 3.8.3.1, Onsite Power Distribution, to extend the allowed outage time for vital instrument bus inverters 1E and 1F from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 7 days.

As part of the Nuclear Regulatory Commission (NRC or the Commission) staffs review, an independent analysis of the proposed change was performed. While the NRC staffs analysis indicated that the proposed change may be acceptable, differences were identified during performance of the confirmatory analysis that would require further NRC and FPLE staff communication to resolve. Subsequently, by letter dated December 20, 2006, FPLE withdrew the amendment request to allow these questions to be addressed, and incorporated in a revised license amendment request.

The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.

Sincerely,

/RA/

G. Edward Miller, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 Distribution:

PUBLIC RidsNrrLACRaynor JChung PDI-2 R/F RidsOgcRp MMcConnell RidsNrrDlpmLpdI-2 RidsAcrsAcnwMailCenter GWilson RidsNrrPMGMiller RidsRgn1MailCenter GMorris RISNrrDorlDpr LMrowca Accession Number: ML063560237 NRR106 OFFICE LPL1-2/PM LPL1-2/LA LPL1-2/BC NAME GEMiller CRaynor HChernoff DATE 12/27/06 12/27/06 12/26/06 OFFICIAL RECORD COPY