ML070960078: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 05/03/2007 | | issue date = 05/03/2007 | ||
| title = Administrative Change to Renewed Facility Operating Licenses in Conjunction with the Commission Order EA-06-037 and Revisions to Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan | | title = Administrative Change to Renewed Facility Operating Licenses in Conjunction with the Commission Order EA-06-037 and Revisions to Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan | ||
| author name = Mozafari B | | author name = Mozafari B | ||
| author affiliation = NRC/NRR/ADRO/DORL/LPLII-2 | | author affiliation = NRC/NRR/ADRO/DORL/LPLII-2 | ||
| addressee name = Stall J | | addressee name = Stall J | ||
| addressee affiliation = Florida Power & Light Co | | addressee affiliation = Florida Power & Light Co | ||
| docket = 05000250, 05000251 | | docket = 05000250, 05000251 | ||
| license number = DPR-031, DPR-041 | | license number = DPR-031, DPR-041 | ||
| contact person = Mozafari B | | contact person = Mozafari B, NRR/ADRO/DORL, 415-2020 | ||
| case reference number = TAC MD2288, TAC MD2289 | | case reference number = TAC MD2288, TAC MD2289 | ||
| package number = ML070950534 | | package number = ML070950534 | ||
Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:4 D. Fire Protection FPL shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report (UFSAR) for Turkey Point Units 3 and 4 and as approved in the Safety Evaluation Report (SER) dated March 21, 1979 and supplemented by NRC letters dated April 3, 1980, July 9, 1980, December 8, 1980, January 26, 1981, May 10, 1982, March 27, 1984, April 16, 1984, August 12, 1987, and by Safety Evaluations dated February 25, 1994, February 24, 1998, October 8, 1998, December 22, 1998, May 4, 1999, and May 5, 1999, subject to the following provision: | ||
The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire. | |||
E. The licensee shall fully implement and maintain in effect all provisions of l the Commission-approved physical security, training and qualification, l and safeguards contingency plans including amendments made pursuant l to provision of the Miscellaneous Amendments and Search Requirements l revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority l of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, l which contains Safeguards Information protected under 10 CFR 73.21, is l entitled: "Florida Power and Light & FPL Energy Seabrook Physical l Security Plan, Training and Qualification Plan and Safeguards l Contingency Plan - Revision 3," submitted by letter dated May 18, 2006. l F. 1. The licensee shall restrict the combined number of fuel assemblies loaded in the existing spent fuel pool storage racks and cask pit rack to no more than the capacity of the spent fuel pool storage racks. | |||
This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary. | This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary. | ||
2.The licensee shall establish two hold points within the rack | : 2. The licensee shall establish two hold points within the rack installation procedure to ensure proper orientation of the cask rack in each unit's spent fuel pool. Verification of proper cask pit rack orientation will be implemented by an authorized Quality Control inspector during installation of the racks to ensure consistency with associated spent fuel pool criticality analysis assumptions. | ||
Renewed License No. DPR-31 Amendment No. 226 Revised by letter dated May 3, 2007 | |||
4 D. Fire Protection FPL shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report (UFSAR) for Turkey Point Units 3 and 4 and as approved in the Safety Evaluation Report (SER) dated March 21, 1979 and supplemented by NRC letters dated April 3, 1980, July 9, 1980, December 8, 1980, January 26, 1981, May 10, 1982, March 27, 1984, April 16, 1984, August 12, 1987, and by Safety Evaluations dated February 25, 1994, February 24, 1998, October 8, 1998, December 22, 1998, May 4, 1999, and May 5, 1999, subject to the following provision: | |||
The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire. | |||
E. The licensee shall fully implement and maintain in effect all provisions of l the Commission-approved physical security, training and qualification, l and safeguards contingency plans including amendments made pursuant l to provision of the Miscellaneous Amendments and Search Requirements l revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority l of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, l which contains Safeguards Information protected under 10 CFR 73.21, is l entitled: "Florida Power and Light & FPL Energy Seabrook Physical l Security Plan, Training and Qualification Plan and Safeguards l Contingency Plan Revision 3," submitted by letter dated May 18, 2006. l F. 1. The licensee shall restrict the combined number of fuel assemblies loaded in the existing spent fuel pool storage racks and cask pit rack to no more than the capacity of the spent fuel pool storage racks. | |||
This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary. | This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary. | ||
2.The licensee shall establish two hold points within the rack | : 2. The licensee shall establish two hold points within the rack installation procedure to ensure proper orientation of the cask rack in each unit's spent fuel pool. Verification of proper cask pit rack orientation will be implemented by an authorized Quality Control inspector during installation of the racks to ensure consistency with associated spent fuel pool criticality analysis assumptions. | ||
Renewed License No. DPR-41 Amendment No. 222 Revised by letter dated May 3, 2007}} |
Latest revision as of 08:38, 23 November 2019
ML070960078 | |
Person / Time | |
---|---|
Site: | Turkey Point ![]() |
Issue date: | 05/03/2007 |
From: | Mozafari B NRC/NRR/ADRO/DORL/LPLII-2 |
To: | Stall J Florida Power & Light Co |
Mozafari B, NRR/ADRO/DORL, 415-2020 | |
Shared Package | |
ML070950534 | List: |
References | |
TAC MD2288, TAC MD2289 | |
Download: ML070960078 (2) | |
Text
4 D. Fire Protection FPL shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report (UFSAR) for Turkey Point Units 3 and 4 and as approved in the Safety Evaluation Report (SER) dated March 21, 1979 and supplemented by NRC letters dated April 3, 1980, July 9, 1980, December 8, 1980, January 26, 1981, May 10, 1982, March 27, 1984, April 16, 1984, August 12, 1987, and by Safety Evaluations dated February 25, 1994, February 24, 1998, October 8, 1998, December 22, 1998, May 4, 1999, and May 5, 1999, subject to the following provision:
The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
E. The licensee shall fully implement and maintain in effect all provisions of l the Commission-approved physical security, training and qualification, l and safeguards contingency plans including amendments made pursuant l to provision of the Miscellaneous Amendments and Search Requirements l revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority l of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, l which contains Safeguards Information protected under 10 CFR 73.21, is l entitled: "Florida Power and Light & FPL Energy Seabrook Physical l Security Plan, Training and Qualification Plan and Safeguards l Contingency Plan - Revision 3," submitted by letter dated May 18, 2006. l F. 1. The licensee shall restrict the combined number of fuel assemblies loaded in the existing spent fuel pool storage racks and cask pit rack to no more than the capacity of the spent fuel pool storage racks.
This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary.
- 2. The licensee shall establish two hold points within the rack installation procedure to ensure proper orientation of the cask rack in each unit's spent fuel pool. Verification of proper cask pit rack orientation will be implemented by an authorized Quality Control inspector during installation of the racks to ensure consistency with associated spent fuel pool criticality analysis assumptions.
Renewed License No. DPR-31 Amendment No. 226 Revised by letter dated May 3, 2007
4 D. Fire Protection FPL shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report (UFSAR) for Turkey Point Units 3 and 4 and as approved in the Safety Evaluation Report (SER) dated March 21, 1979 and supplemented by NRC letters dated April 3, 1980, July 9, 1980, December 8, 1980, January 26, 1981, May 10, 1982, March 27, 1984, April 16, 1984, August 12, 1987, and by Safety Evaluations dated February 25, 1994, February 24, 1998, October 8, 1998, December 22, 1998, May 4, 1999, and May 5, 1999, subject to the following provision:
The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
E. The licensee shall fully implement and maintain in effect all provisions of l the Commission-approved physical security, training and qualification, l and safeguards contingency plans including amendments made pursuant l to provision of the Miscellaneous Amendments and Search Requirements l revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority l of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, l which contains Safeguards Information protected under 10 CFR 73.21, is l entitled: "Florida Power and Light & FPL Energy Seabrook Physical l Security Plan, Training and Qualification Plan and Safeguards l Contingency Plan Revision 3," submitted by letter dated May 18, 2006. l F. 1. The licensee shall restrict the combined number of fuel assemblies loaded in the existing spent fuel pool storage racks and cask pit rack to no more than the capacity of the spent fuel pool storage racks.
This condition applies at all times, except during activities associated with a reactor core offload/reload refueling condition. This restriction will ensure the capability to unload and remove the cask pit rack when cask loading operations are necessary.
- 2. The licensee shall establish two hold points within the rack installation procedure to ensure proper orientation of the cask rack in each unit's spent fuel pool. Verification of proper cask pit rack orientation will be implemented by an authorized Quality Control inspector during installation of the racks to ensure consistency with associated spent fuel pool criticality analysis assumptions.
Renewed License No. DPR-41 Amendment No. 222 Revised by letter dated May 3, 2007