ML12086A304: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(6 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 04/09/2012
| issue date = 04/09/2012
| title = G20120190/EDATS: OEDO-2012-0158 - Letter - Response to Sam Armijo Re Final Safety Evaluation Report Associated with the Florida Power and Light Turkey Point Nuclear Plant, Units 3 and 4, License Amendment Request for an Extended Power Uprat
| title = G20120190/EDATS: OEDO-2012-0158 - Letter - Response to Sam Armijo Re Final Safety Evaluation Report Associated with the Florida Power and Light Turkey Point Nuclear Plant, Units 3 and 4, License Amendment Request for an Extended Power Uprat
| author name = Borchardt R W
| author name = Borchardt R
| author affiliation = NRC/EDO
| author affiliation = NRC/EDO
| addressee name = Armijo J S
| addressee name = Armijo J
| addressee affiliation = NRC/ACRS
| addressee affiliation = NRC/ACRS
| docket = 05000250, 05000251
| docket = 05000250, 05000251
Line 14: Line 14:
| document type = Letter
| document type = Letter
| page count = 2
| page count = 2
| project = TAC:ME8238, TAC:ME8239
| stage = Approval
}}
}}
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2012 Dr. J. Sam Armijo, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555 SUB.JECT:      FINAL SAFETY EVALUATION REPORT ASSOCIATED WITH THE FLORIDA POWER AND LIGHT TURKEY POINT NUCLEAR PLANT, UNITS 3 AND 4, LICENSE AMENDMENT REQUEST FOR AN EXTENDED POWER UPRATE
==Dear Dr. Armijo:==
During the 592 nd meeting of the Advisory Committee on Reactor Safeguards (ACRS or the Committee) on March 8-10, 2012, ACRS completed its review of the extended power uprate application for Turkey Point Nuclear Plant (PTN), Units 3 and 4, and the associated safety evaluation report prepared by the U.S. Nuclear Regulatory Commission (NRC) staff.
By letter dated March 20, 2012 (Agencywide Documents Access and Management System Accession No. ML12072A200), the Committee provided its final report on the extended power uprate for PTN, Units 3 and 4. The NRC staff agrees with your recommendation that the agency should approve the extended power uprate for PTN, Units 3 and 4.
The NRC staff appreciates the Committee's prompt and very thorough review of this extended power uprate application and the associated safety evaluation report. The NRC staff recognizes the Committee's commitment to safety and appreciates the continued support of the power uprate process.
Sincerely,
                                              .---~~.          .\  I B~G--
R. W. Borchardt Executive Director for Operations cc: Chairman Jaczko Commissioner Svinicki Commissioner Apostolakis Commissioner Magwood Commissioner Ostendorff SECY
April 9, 2012 Dr. J. Sam Armijo, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555
==SUBJECT:==
FINAL SAFETY EVALUATION REPORT ASSOCIATED WITH THE FLORIDA POWER AND LIGHT TURKEY POINT NUCLEAR PLANT, UNITS 3 AND 4, LICENSE AMENDMENT REQUEST FOR AN EXTENDED POWER UPRATE
==Dear Dr. Armijo:==
nd During the 592 meeting of the Advisory Committee on Reactor Safeguards (ACRS or the Committee) on March 8-10,2012, ACRS completed its review of the extended power uprate application for Turkey Point Nuclear Plant (PTN), Units 3 and 4, and the associated safety evaluation report prepared by the U.S. Nuclear Regulatory Commission (NRC) staff.
By letter dated March 20, 2012 (Agencywide Documents Access and Management System Accession No. ML12072A200), the Committee provided its final report on the extended power uprate for PTN, Units 3 and 4. The NRC staff agrees with your recommendation that the agency should approve the extended power uprate for PTN, Units 3 and 4.
The NRC staff appreciates the Committee's prompt and very thorough review of this extended power uprate application and the associated safety evaluation report. The NRC staff recognizes the Committee's commitment to safety and appreciates the continued support of the power uprate process.
Sincerely, IRA by Martin J. Virgilio fori R. W. Borchardt Executive Director for Operations cc: Chairman Jaczko Commissioner Svinicki Commissioner Apostolakis Commissioner Magwood Commissioner Ostendorff SECY DISTRIBUTION: G20120190/EDATS: OEDO-2012-0158 PUBLIC                      RidsNrrDeEeeb                  RidsNrrDssSbpb                RidsResOdRids Lp12-2 r/f                  RidsNrrDeEicb                  RidsNrrDssScvb                RidsRgn2MailCenter RidsAcrsAcnw_MailCTR        RidsNrrDeEmcb                  RidsNrrDssSrxb                RidsSecyMailCenter RidsEdoMailCenter          RidsNrrDirslqvb                RidsNrrDssStsb                TAlexion RidsNrrOd                  RidsNrrDraAhpb                  RidsNrrDlrRerb                NDiFrancesco RidsNrrMailCenter          RidsNrrDraAadb                  RidsNrrLABClayton            SRosenberg RidsNrrDeEpnb              RidsNrrDraApla                  RidsNrrPMTurkey Point        ACRS File RidsNrrDeEptb              RidsNrrDraAfpb                  RidsOcaMailCenter RidsNrrDeEsgb                RidsNrrDorl                    RidsOgcMailCenter RidsNrrDeEvib              RidsNrrDorlLpl2-2              RidsOgcRp ADAMS Accession Nos.:    Package: ML12086A298      Incoming: ML12082A124    Res~onse Letter: ML12086A304 OFFICE    LPL2-2/PM    LPL2-21LA        Tech Editor*    LPL2-2/BC      DORUD          NRRlD          EDO DBroaddus      MEvans        ELeeds          RWBorchardt NAME      JPaige      BClayton        JDougherty      (EBrown for)    (AHowe for)    (DDorman for)  (MVirgilio for)
DATE      3/28112      3/28/12          03/27/12        413/12          4/3/12        4/5/12          4/9/12
'Concurrence vIa Email                      OFFICIAL RECORD COpy}}

Latest revision as of 07:20, 12 November 2019

G20120190/EDATS: OEDO-2012-0158 - Letter - Response to Sam Armijo Re Final Safety Evaluation Report Associated with the Florida Power and Light Turkey Point Nuclear Plant, Units 3 and 4, License Amendment Request for an Extended Power Uprat
ML12086A304
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 04/09/2012
From: Borchardt R
NRC/EDO
To: Armijo J
Advisory Committee on Reactor Safeguards
Paige J, NRR/DORL, 415-5888
Shared Package
ML12086A298 List:
References
G20120190, TAC ME8238, TAC ME8239, EDATS: OEDO-2012-0158
Download: ML12086A304 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2012 Dr. J. Sam Armijo, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555 SUB.JECT: FINAL SAFETY EVALUATION REPORT ASSOCIATED WITH THE FLORIDA POWER AND LIGHT TURKEY POINT NUCLEAR PLANT, UNITS 3 AND 4, LICENSE AMENDMENT REQUEST FOR AN EXTENDED POWER UPRATE

Dear Dr. Armijo:

During the 592 nd meeting of the Advisory Committee on Reactor Safeguards (ACRS or the Committee) on March 8-10, 2012, ACRS completed its review of the extended power uprate application for Turkey Point Nuclear Plant (PTN), Units 3 and 4, and the associated safety evaluation report prepared by the U.S. Nuclear Regulatory Commission (NRC) staff.

By letter dated March 20, 2012 (Agencywide Documents Access and Management System Accession No. ML12072A200), the Committee provided its final report on the extended power uprate for PTN, Units 3 and 4. The NRC staff agrees with your recommendation that the agency should approve the extended power uprate for PTN, Units 3 and 4.

The NRC staff appreciates the Committee's prompt and very thorough review of this extended power uprate application and the associated safety evaluation report. The NRC staff recognizes the Committee's commitment to safety and appreciates the continued support of the power uprate process.

Sincerely,

.---~~. .\ I B~G--

R. W. Borchardt Executive Director for Operations cc: Chairman Jaczko Commissioner Svinicki Commissioner Apostolakis Commissioner Magwood Commissioner Ostendorff SECY

April 9, 2012 Dr. J. Sam Armijo, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555

SUBJECT:

FINAL SAFETY EVALUATION REPORT ASSOCIATED WITH THE FLORIDA POWER AND LIGHT TURKEY POINT NUCLEAR PLANT, UNITS 3 AND 4, LICENSE AMENDMENT REQUEST FOR AN EXTENDED POWER UPRATE

Dear Dr. Armijo:

nd During the 592 meeting of the Advisory Committee on Reactor Safeguards (ACRS or the Committee) on March 8-10,2012, ACRS completed its review of the extended power uprate application for Turkey Point Nuclear Plant (PTN), Units 3 and 4, and the associated safety evaluation report prepared by the U.S. Nuclear Regulatory Commission (NRC) staff.

By letter dated March 20, 2012 (Agencywide Documents Access and Management System Accession No. ML12072A200), the Committee provided its final report on the extended power uprate for PTN, Units 3 and 4. The NRC staff agrees with your recommendation that the agency should approve the extended power uprate for PTN, Units 3 and 4.

The NRC staff appreciates the Committee's prompt and very thorough review of this extended power uprate application and the associated safety evaluation report. The NRC staff recognizes the Committee's commitment to safety and appreciates the continued support of the power uprate process.

Sincerely, IRA by Martin J. Virgilio fori R. W. Borchardt Executive Director for Operations cc: Chairman Jaczko Commissioner Svinicki Commissioner Apostolakis Commissioner Magwood Commissioner Ostendorff SECY DISTRIBUTION: G20120190/EDATS: OEDO-2012-0158 PUBLIC RidsNrrDeEeeb RidsNrrDssSbpb RidsResOdRids Lp12-2 r/f RidsNrrDeEicb RidsNrrDssScvb RidsRgn2MailCenter RidsAcrsAcnw_MailCTR RidsNrrDeEmcb RidsNrrDssSrxb RidsSecyMailCenter RidsEdoMailCenter RidsNrrDirslqvb RidsNrrDssStsb TAlexion RidsNrrOd RidsNrrDraAhpb RidsNrrDlrRerb NDiFrancesco RidsNrrMailCenter RidsNrrDraAadb RidsNrrLABClayton SRosenberg RidsNrrDeEpnb RidsNrrDraApla RidsNrrPMTurkey Point ACRS File RidsNrrDeEptb RidsNrrDraAfpb RidsOcaMailCenter RidsNrrDeEsgb RidsNrrDorl RidsOgcMailCenter RidsNrrDeEvib RidsNrrDorlLpl2-2 RidsOgcRp ADAMS Accession Nos.: Package: ML12086A298 Incoming: ML12082A124 Res~onse Letter: ML12086A304 OFFICE LPL2-2/PM LPL2-21LA Tech Editor* LPL2-2/BC DORUD NRRlD EDO DBroaddus MEvans ELeeds RWBorchardt NAME JPaige BClayton JDougherty (EBrown for) (AHowe for) (DDorman for) (MVirgilio for)

DATE 3/28112 3/28/12 03/27/12 413/12 4/3/12 4/5/12 4/9/12

'Concurrence vIa Email OFFICIAL RECORD COpy