ML18109A041: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 04/12/2018 | | issue date = 04/12/2018 | ||
| title = Notification of Action Completion for Confirmatory Order EA-17-077 - Item D.2 | | title = Notification of Action Completion for Confirmatory Order EA-17-077 - Item D.2 | ||
| author name = Stoddard D | | author name = Stoddard D | ||
| author affiliation = Dominion Energy Nuclear Connecticut, Inc | | author affiliation = Dominion Energy Nuclear Connecticut, Inc | ||
| addressee name = | | addressee name = | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:.... Dominion Energy Nuclear Connecticut, Inc. 5000 Dominion Boulevard, Glen Allen, VA 23060 DominionEnergy.com U.S .. Nuclear R~gulatory Commission Regional Administrator, Region I 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2_713 | {{#Wiki_filter:.... | ||
Dominion Energy Nuclear Connecticut, Inc. | |||
-ITEM D.2 On November 21, 2017, the Nuclear Regulatory Commission (NRG) issued 'confirmatory Order EA-17-077 to Dominion Energy Nuclear Connecticut, Inc. (DENG). Section V of the Confirmatory Order requires DENG to complete Item 0.2 within 90 days of completing item D.1 1 , and to notify the NRC in writing within 30 days of Item 0.2 completion. | 5000 Dominion Boulevard, Glen Allen, VA 23060 DominionEnergy.com April 12, 2018 | ||
On March 9, 2018, DENG evaluated the implementation of the Armorer function at Millstone Power Station (MPS) per Item 0.1. On March 23, 2018, communication of evaluation results to Security Personnel was completed. | [fie Dominion | ||
As specified in Item 0.2, the content of the communication is available to the NRC for review during an. inspection. | ~ Energv U.S .. Nuclear R~gulatory Commission Serial No. 17-4650 Regional Administrator, Region I | ||
* NSSLffFO R1 2100 Renaissance Blvd, Suite 100 Docke*t Nos. 50-336 King of Prussia, PA 19406-2_713 50-423 License Nos. DPR-65 NPF-49 DOMINION ENERGY NUCLEAR CONNECTICUT, INC. | |||
MILLSTONE POWER STATION UNITS 2 AND 3 NOTIFICATION OF ACTION COMPLETION FOR CONFIRMATORY ORDER EA-1.7-077 - ITEM D.2 On November 21, 2017, the Nuclear Regulatory Commission (NRG) issued | |||
'confirmatory Order EA-17-077 to Dominion Energy Nuclear Connecticut, Inc. (DENG). | |||
Section V of the Confirmatory Order requires DENG to complete Item 0.2 within 90 days of completing item D.1 1, and to notify the NRC in writing within 30 days of Item 0.2 completion. On March 9, 2018, DENG evaluated the implementation of the Armorer function at Millstone Power Station (MPS) per Item 0.1. On March 23, 2018, communication of evaluation results to Security Personnel was completed. As specified in Item 0.2, the content of the communication is available to the NRC for review during an. inspection. | |||
If you have* any questions concerning this matter, please contact Michael Whitlock at (804) 273-3123. | If you have* any questions concerning this matter, please contact Michael Whitlock at (804) 273-3123. | ||
Sincerely, Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Dominion Energy Nuclear Connecticut, Inc. Commitments made in this letter: None 1 Notification to the NRC of the completion of Item D.1 was provided to the NRC on March 28, 2018 * .(Serial No. 17-465C). | Sincerely, Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Dominion Energy Nuclear Connecticut, Inc. | ||
*~ Serial No. 17-4650 cc: U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Richard V. Guzman Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 C 2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station | Commitments made in this letter: None 1 | ||
Notification to the NRC of the completion of Item D.1 was provided to the NRC on March 28, 2018 * | |||
.(Serial No. 17-465C). | |||
*~ Serial No. 17-4650 Docket Nos. 50-336/423 Page 2 of 2 cc: U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Richard V. Guzman Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 C 2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station}} |
Latest revision as of 08:29, 21 October 2019
ML18109A041 | |
Person / Time | |
---|---|
Site: | Millstone ![]() |
Issue date: | 04/12/2018 |
From: | Stoddard D Dominion Energy Nuclear Connecticut |
To: | Document Control Desk, NRC Region 1 |
References | |
17-465D, EA-17-077 | |
Download: ML18109A041 (2) | |
Text
....
Dominion Energy Nuclear Connecticut, Inc.
5000 Dominion Boulevard, Glen Allen, VA 23060 DominionEnergy.com April 12, 2018
[fie Dominion
~ Energv U.S .. Nuclear R~gulatory Commission Serial No. 17-4650 Regional Administrator, Region I
- NSSLffFO R1 2100 Renaissance Blvd, Suite 100 Docke*t Nos. 50-336 King of Prussia, PA 19406-2_713 50-423 License Nos. DPR-65 NPF-49 DOMINION ENERGY NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION UNITS 2 AND 3 NOTIFICATION OF ACTION COMPLETION FOR CONFIRMATORY ORDER EA-1.7-077 - ITEM D.2 On November 21, 2017, the Nuclear Regulatory Commission (NRG) issued
'confirmatory Order EA-17-077 to Dominion Energy Nuclear Connecticut, Inc. (DENG).
Section V of the Confirmatory Order requires DENG to complete Item 0.2 within 90 days of completing item D.1 1, and to notify the NRC in writing within 30 days of Item 0.2 completion. On March 9, 2018, DENG evaluated the implementation of the Armorer function at Millstone Power Station (MPS) per Item 0.1. On March 23, 2018, communication of evaluation results to Security Personnel was completed. As specified in Item 0.2, the content of the communication is available to the NRC for review during an. inspection.
If you have* any questions concerning this matter, please contact Michael Whitlock at (804) 273-3123.
Sincerely, Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Dominion Energy Nuclear Connecticut, Inc.
Commitments made in this letter: None 1
Notification to the NRC of the completion of Item D.1 was provided to the NRC on March 28, 2018 *
.(Serial No. 17-465C).
- ~ Serial No. 17-4650 Docket Nos. 50-336/423 Page 2 of 2 cc: U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Richard V. Guzman Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 C 2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station