ULNRC-06070, RAI Respose to Application for Amendment, (LDCN 12-0015), Revision to Technical Specification 3.7.9
| ML14016A337 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 01/16/2014 |
| From: | Maglio S Ameren Missouri |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LDCN 12-0015, TAC MF0378, ULNRC-06070 | |
| Download: ML14016A337 (30) | |
Text
~~
WAmeren MISSOURI January 16, 2014 ULNRC-06070 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
10 CFR 50.90 DOCKET NUMBER 50-483 CALLAWAY PLANT UNION ELECTRIC CO.
APPLICATION FOR AMENDMENT TO FACILITY OPERATING LICENSE NPF-30 (T AC NO. MF0378, LDCN 12-0015)
REVISION TO TECHNICAL SPECIFICATION 3.7.9
References:
- 1. ULNRC-05867 dated December 13, 2012, Revision to Technical Specification 3.7.9 (LDCN 12-0015)
- 2. ULNRC-05995 dated June 11, 2013, Revision to Technical Specification 3.7.9 (LDCN 12-0015), Response to Request for Additional Information
- 3. NRC Request for Additional Information, Carl F. Lyon (NRC) to Thomas B. Elwood (Union Electric Company) dated December 20, 2013 Callaway Plant In Reference 1 above, Ameren Missouri (Union Electric Company) submitted an application for amendment to Facility Operating License Number NPF -30 for the Callaway Plant. The amendment application addresses a non-conservative Technical Specification as discussed in NRC Administrative Letter 98-10, "Dispositioning of Technical Specifications That Are Insufficient To Assure Plant Safety."
The amendment application proposes changes to Technical Specification (TS) 3.7.9, "Ultimate Heat Sink (UHS)," to incorporate more restrictive UHS level and pond temperature limits which are specified in Surveillance Requirements (SRs) 3.7.9.1 and 3.7.9.2, respectively. In addition, new SR 3.7.9.4 would be added to verify that the UHS cooling tower fans respond appropriately to automatic start signals.
PO Box 620 Fulton, MD 65251 AmerenMissouri.com
ULNRC-06070 January 16, 2014 Page 2 In Reference 2 above, Ameren Missouri responded to an NRC request for additional information.
In Reference 3 above, the NRC requested additional information to complete their review. The attachments to this letter provide the requested information. No commitments are contained in this letter.
If you have any questions on this amendment application, please contact me at (573) 676-8719 or Mr. Tom Elwood at (314) 225-1905.
I declare under penalty of perjury that the foregoing is true and correct.
Very truly yours, Executed on: l II L2../ U t a-J
~A?tty Scott Maglio Manager, Regulatory Affairs GGY/
Attachments:
1 - RAI Response 2-Setpoint Calculation J-UEF03 Revision 1
ULNRC-06070 January 16, 2014 Page 3 cc:
Mr. Marc L. Dapas Regional Administrator U.S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 7 60 11-4 511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Fred Lyon Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8B 1 Washington, DC 20555-2738
ULNRC-06070 January 16, 2014 Page 4 Index and send hardcopy to QA File A160.0761 Hardcopy:
Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)
Electronic distribution for the following can be made via Tech Spec ULNRC Distribution:
A. C. Heflin F. M. Diya C. 0. Reasoner III B.L.Cox L. H. Graessle J. S. Geyer S. A. Maglio Corporate Communications NSRB Secretary T. B. Elwood G. G. Yates STARS Regulatory Affairs Mr. John O'Neill (Pillsbury, Winthrop, Shaw, Pittman LLP)
Missouri Public Service Commission Ms. Leanne Tippett-Mosby (DNR) to ULNRC-06070 ATTACHMENT 1 RAIRESPONSE
Question:
The NRC Staff has a question on the safety status of the setpoints for cooling tower fan speed control and cooling tower bypass valve automatic closure. The licensee has credited manual operator actions for these functions. If it is determined that these items are safety-related, the Staff requests the calculations for each setpoint; a statement of whether each is, or is not, a limiting safety system setting (LSSS), and a TSTF -493 statement.
Response
This question has multiple parts which will be addressed in order.
There are three credited operator actions in the LDCN 12-0015 license amendment request (LAR) which have defined completion times as discussed on pages 14-15 of the LAR
Enclosure:
- 1. Verification of proper UHS Cooling Tower operation and securing affected ESW train within 70 minutes of the accident.
- 2. UHS Cooling Tower Inlet temperature switchover within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to ESW Pump Discharge temperature.
- 3. Securing one train of ESW within 7 days.
Actions 2 and 3 are time-driven and do not rely on indication inputs for progression through the applicable Emergency Operating Procedures (EOPs). (See LAR Enclosure pages 14-16 and item 8 (pages 6-7) ofLAR Attachment 6.)
Action 1 requires the isolation of an ESW train within 70 minutes if a failed system component is discovered, as discussed in detail on LAR Enclosure pages 15 and 16. The credited operator action requires the use of the following indications in EOP E-1 step 11:
Step 11.a-Annunciators 30E [NG07 bus undervoltage I overvoltage annunciator] and 31 E [NG08 bus undervoltage I overvoltage annunciator]: Check NG07 [ 480 V AC load center, train 'A' separation group 1] and NG08 [480 VAC load center, train 'B' separation group 4] bus trouble annunciators (non-safety related);
Step 11. b - Computer points EFT0067 A [UHS cooling tower inlet temperature from ESW train 'A'] or EFT0068A [UHS cooling tower inlet temperature from ESW train 'B']
- Determine ESW return temperature (UHS cooling tower inlet temperature) (non-safety related);
Step 11.b Response Not Obtained (RNO) If computer points are unavailable, determine UHS cooling tower inlet temperature using High/Low ESW return temperature indications EFTSHL0067B, EFTSHL0068B (non-safety related);
Page 1 of3
Step 11.c-EFHIS0065A and 66A [UHS cooling tower bypass valve hand indicating switches for ESW trains 'A' and 'B' respectively] on control room panel RL019 or locally at EFHV0065 and 66: Check UHS cooling tower bypass valve position indication is appropriate for the temperatures determined in step 11.b (These valve "HIS" hand-indicating switches are safety-related, but are similar to the devices excluded from the scope ofTSTF-493-A Revision 4, i.e., devices that derive input from contacts which have no associated sensor or adjustable device.)
Step 11.d - EFHIS0061 A & 62A [UHS cooling tower fans hand indicating switches for ESW trains 'A' and 'B' respectively] on control room panel RL019 or locally at EFHIS0063A/B/C/D, EFHIS0064A/B/C/D [local UHS cooling tower fans hand indicating switches for ESW trains 'A' and 'B' respectively]: Check UHS cooling tower fan speed indication is appropriate for the temperatures determined in step 11. b (These fan "HIS" hand-indicating switches are safety-related, but are excluded from the scope of TSTF-493-A Revision 4.)
If the indications in the RNO column are unavailable, E-1 directs a transfer to EOP Addendum 17 to secure the ESW train in which a failure is suspected. Verification of successful ESW train isolation can be achieved using the ESW pump running indications found on safety-related hand indication switches EFHIS0055A and EFHIS0056A on control room panel RL019.
The ESW pump hand-indicating switches are safety-related, but are excluded from the scope of TSTF-493-A Revision 4. LAR Attachment 6 (pages 8-11) provides detailed discussions ofEOP device pedigree. As such, there are no TSTF-493-A implications associated with cues for the above operator actions.
As discussed in detail on LAR Enclosure pages 15-17, step 19 ofEOP E-1 directs the performance ofEOP Addendum 40 to transfer the automatic control of the UHS cooling tower bypass valves and fans to the ESW pump discharge temperature channels (EFT-0061 and EFT-0062). Although not a credited operator action with a defined completion time (LAR Enclosure page 15), Step 5 ofEOP Addendum 40 is a continuous action step to check UHS cooling tower fan speeds (safety-related EFHIS0061A & 62A discussed above under E-1 Step 1l.d) vs. the ESW pump discharge (ESW supply) temperature (safety-related temperature indicators EFTI0061, EFTI0062) so that any equipment failures involving the temperature control handswitches (EFHS0067, EFHS0068) or ESW supply temperature loops (EFT-0061, EFT-0062) would be recognized and addressed (e.g., by securing the affected ESW train, if necessary) to support maintaining the necessary UHS pond inventory.
There is one setpoint calculation associated with the safety-related, temperature-based circuitry used to automatically position the EFHV0065/0066 UHS cooling tower return bypass valves and to automatically establish the speed of UHS cooling tower fans. That setpoint calculation is included as Attachment 2 and demonstrates that a 2.5°F Channel Uncertainty must be accounted for when establishing the Nominal Trip Setpoints that protect the Safety Analysis Limits defined in Calculation EF -123 (LAR Enclosure pages 8-12). E-1 step 11 (discussed above) verifies the proper operation of the bypass valves and cooling tower fans from the EFT -0067 A and EFT-0068A channels. E-1 step 19 (manual enabling of automatic control from ESW pump Page 2 of3
discharge temperature loops at 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />) directs the performance of EOP Addendum 40 which verifies proper operation of the bypass valves and cooling tower fans from the EFT -0061 and EFT -0062 channels. However, none of the setpoints in the EFT -0067 A, EFT -0068A, EFT -0061, or EFT -0062 temperature channels satisfy the definition of a Safety Limit-Limiting Safety System Setting (SL-LSSS) as agreed to between the NRC Staff and the industry during the review and approval ofTSTF-493-A Revision 4.
During the NRC review ofTSTF-493 the Staff posted a comment on March 22, 2006 that stated:
"TSTF-493, Revision 0 did not generically define the scope of the instrumentation affected. To cover those systems that should be covered to meet 10 CFR 50.36 the TSTF scope for identifying LSSS should apply to TSs instrumentation related to variables which protect the integrity of the reactor fuel and the integrity of the reactor coolant pressure boundary (RCPB) physical barriers. This translates to TSs instrumentation, excluding manual trip functions, that trip the reactor (i.e.,
reactor trip system instrumentation, reactor protection system instrumentation);
TSs instrumentation that ensure the core is adequately cooled in the event of a design basis accident or transient (i.e., engineered safety feature actuation instrumentation, emergency core cooling system instrumentation); TSs instrumentation that provides additional margin to core safety limits, such as the end-of-cycle recirculation pump trip instrumentation [for BWR plants]; and TSs instrumentation that provides RCPB overpressure protection (pressurizer safety valves, safety/relief valves)."
In response to this comment the Owners Groups had the NSSS vendors identify a list of generic LSSSs that protected the reactor core and reactor coolant pressure boundary pressure Safety Limits during anticipated operational occurrences, which are the only events that are considered for determining the Safety Limit (SL) LSSSs. TSTF-493 was subsequently revised to include the identified list of LSSS functions for each NUREG.
Additional supporting or exempting statements were also included to further define the components that must be considered in the LSSS scope. For Westinghouse plants, the SL-LSSS functions that are within the scope of additional, setpoint-related surveillance and operability footnotes are limited to the functions specified in TS 3.3.1, "RTS Instrumentation," and TS 3.3.2, "ESFAS Instrumentation," as discussed in TSTF-493-A, Revision 4, Attachment A, "Identification of Functions to be Annotated with the TSTF-493 Footnotes-NUREG-1431, Westinghouse Plants." TSTF-493 does not apply to the LDCN 12-0015 LAR since no SL-LSSSs are involved.
Page 3 of3 to ULNRC-06070 ATTACHMENT 2 SETPOINT CALCULATION J-UEF03 REVISION 1
Calculation J-UEF03 Rev. 001 Instrument Loop Uncertainty Estimate: UHS Cooling Tower Fan Speed and Bypass Valve Control Temperature loops EFT-0061/62 (ESW Supply Line) and EFT-0067 A/68A (ESW Return Line) setpoint uncertainty calculation for the Ultimate Heat Sink (UHS) Cooling Tower fan speed control and ESW to UHS Cooling Tower bypass valve control.
Responsible Engineer:
Scott Taylor Date:
(See Elect. Sign.)
Qualified Reviewer:
Ed Goss Date:
(See Elect. Sign.)
Approver:
Jesse Hutchison Date:
(See Elect. Sign.)
Approx. Date:
08/2011 Director W.O.:
CALCOOOO 1666 Page 1 of 14
1.0 Purpose & Scope Calculation J-UEF03, Rev. 001 Page 2 of21 This calculation determines the UHS Cooling Tower fan speed control and ESW to UHS Cooling Tower bypass valve control setpoints considering instrument uncertainties.
Post Implementation of Calculation EF -123 Temperature loops EFT-0061/62 (ESW supply line) and EFT-0067A/68A (ESW return line) actuate the UHS Cooling Tower fans (CEF01A/B/C/D); first in slow speed then into high speed as the temperature rises. The fans are normally controlled via the return line and switched to the supply line post Design Basis Accident (DBA) initiation. Fan control is used to protect two design basis parameters. In the initial hours of a DBA these loops protect the maximum UHS temperature limit (FSAR SP Chapter 9.2, Calc. EF-123).
The fans are then used to ensure an adequate UHS inventory is maintained throughout the UHS's 30 day action statement (FSAR SA Chapter 9.2, Calc. EF-123).
These temperature loops also actuate the ESW to UHS Cooling Tower bypass valves (EFHV0065/66). Bypass valve control is set up to ensure freeze protection (FSAR SA Chapter 9.2, RFR 200802059). This valve also aids the above mentioned fan operation in that cooling is only achieved when the valve is closed, allowing return water over the UHS Cooling Tower fill.
Configuration A below details temperature instrumentation loops EFT -0061/62 (ESW supply line) and EFT-0067A/68A (ESW return line) for UHS Cooling Tower fan and bypass valve control.
Each output isolation card feeds a selector switch (no signal impact/uncertainty) to allow selection between the supply and return lines. (EFT -0067 A to EFT-0061 & EFT-0068A to EFT-0062)
Post Implementation of MP 11-0004, Pre Implementation of Calculation EF -123 MP 11-0004 is incorporating physical SSC changes to allow the plant operational changes shown above per the requirements of EF -123 once they have been approved by the NRC. Until NRC approval of the EF-123 changes, MP 11-0004 will approve the physical SSC changes against the existing UHS design basis documentation, specifically calculation EF-54. Per EF-54 and FSAR SA 9.2.5.2.3 & FSAR SA 9.2.5.5 the current design basis function of these setpoints is freeze protection only. As the EF-123 changes also review the instrumentation setpoints with respect to freeze protection, the analysis of setpoints for the "Post Implementation of Calculation EF -123" used in the remaining sections of this calculation is bounding over the interim state of operation post MP 11-0004 implementation. No further review for this is necessary or will be performed.
Calculation J-UEF03, Rev. 001 Page 3 of21 Configuration A: UHS (an speed and bypass valve control loop Temp. Switch Output lso.
{
To ESW Cooling Tower Fan Controls 2
2 (Fast Speed Selection)
Foxboro Foxboro 2AP+ALM-AR 2AO-L2C-R Temp. Element Temp. Transmitter Temp. Switch Interlock Output lso.
8 8
@ @ @{
To ESW Cooling Tower Fan Controls 3
3 3
(Slow Speed Selection)
Weed Foxboro Foxboro Foxboro Foxboro 612-1 B-C-4-C-14-0-0 2AI-P2V 2AP+ALM-AR 2AO-L2C-R 2AO-L2C-R Temp. Switch Output lso.
{
To ESW Cooling Tower By-Pass Valve Controls 2
(Valve Open/Close)
Foxboro Foxboro 2AP+ALM-AR 2AO-L2C-R Table 1: Configuration A Director Location IDs Train TSHH 1/2*
TSHH 2/2*
Supply A
EFTSHH006112 EFTSHH006122 B
EFTSHH006212 EFTSHH006222 Return A
EFTSHH0067 A 12 EFTSHH0067 A22 B
EFTSHH0068A 12 EFTSHH0068A22 TE TT TSH 1/3*
TSH 2/3*
TSH 3/3*
Supply A
EFTE0061 EFTT0061 EFTSH006113 EFTSH006123 EFTSH006133 B
EFTE0062 EFTT0062 EFTSH006213 EFTSH006223 EFTSH006233 Return A
EFTE0067A EFTT0067A EFTSH0067 A13 EFTSH0067 A23 EFTSH0067 A33 B
EFTE0068A EFTT0068A EFTSH0068A 13 EFTSH0068A23 EFTSH0068A33 TSL 1/2*
TSL 2/2*
Supply A
EFTSL006112 EFTSL006122 B
I EFTSL006212 EFTSL006222 Return A
EFTSL0067 A 12 EFTSL0067 A22 B
EFTSL0068A 12 EFTSL0068A22
Train Supply A
B Return A
B Calculation J-UEF03, Rev. 001 Page 4 of21 Table 2: Director Switch Location IDs TSHH*
TSH*
TSL*
EFTSHH0061 EFTSH0061 EFTSL0061 EFTSHH0062 EFTSH0062 EFTSL0062 EFTSHH0067 A EFTSH0067A EFTSL0067A EFTSHH0068A EFTSH0068A EFTSL0068A
- Callaway has given each circuit card (1/3, 2/3, 3/3, etc) a singular location ID for tracking purposes. The setpoint and tolerance data is maintained on a generic switch ID shown on Table 2 above.
- Hand switches EFHS0067 and EFHS0068 are used after each switch to select between the supply and return line for each control function (Low, High, and High-High Setpoints) 1.1 Calculation History 1.1.1 J-UEF03, Revision 000, INSTRUMENT LOOP UNCERTAINTY ESTIMATE:
SYSTEM EF LOOPS 67 A AND 68A.
DETERMINE THE DEGREE OF UNCERTAINTY IN THE CALIBRATION AND MEASUREMENT OF THE SUBJECT INSTRUMENT LOOPS. - This Calculation determined the instrument loop uncertainty of EF Loops 67 A and 68A when they exclusively controlled the UHS Cooling Tower fans/bypass valve.
1.1.2 J-IEF03, Revision 000, INSTRUMENT LOOP UNCERTAINTY ESTIMATE:
SYSTEM EF LOOPS 67A & 68A DETERMINE THE DEGREE OF UNCERTAINTY IN THE SUBJECT INSTRUMENTATION LOOPS-This calculation is identical to J-UEF03, Revision 000. It shows one revision performed prior to the creation of J-UEF03, but is otherwise identical. The 'I' in the title implies a link to the Wolf Creek Power Plant, but there is no UHS at Wolf Creek. J-UEF03, Revision 001 has superseded J-UEF03, Revision 000; it has also superseded J-1EF03, Revision 000.
1.1.3 J-UEF03A, Revision 000, MIN ALLOW SETPT LIMIT RACK TRIP VAL & LIMIT SYS TRIP VAL: LPS 67A & 68A. DETERMINE THE SAFETY RELATED SETPOINT RACK ALLOW ABLE VALUE AND SYSTEM ALLOW ABLE VALUE OF THE EF-TSL-67A & 68A, EF-TSH-67A & 68A AND EF-TSHH-67A & 68A BISTABLES.- This Calculation used the uncertainty determined via J-UEF03/J-IEF03 to determine the UHS Cooling Tower Fan and Bypass Valve setpoints. This calculation determined the setpoints when they were controlled via EF Loops EFT -0067 A and EFT-0068A exclusively. This document was superseded by J-UEF03, Revision 001.
Calculation J-UEF03, Rev. 001 Page 5 of21 1.1.4 J-UEF03, Revision 001, Instrument Loop Uncertainty Estimate: UHS Cooling Tower Fan Speed and Bypass Valve Control - This revision incorporates the changes done by MP 11-0004 to the UHS Cooling Tower Fan Speed and Bypass Valve Control. The MP added a hand switch to allow control off of the existing ESW return line temperature instrumentation loops EFT -0067 A and EFT -0068A or the new ES W supply line temperature instrumentation loops EFT -0061 and EFT -0062.
2.0 Methodology 2.1 The methodology used to determine this uncertainty will be that of ISA-S67.04, Dated September 1994, Setpoints for Nuclear Safety-Related Instrumentation, and ISA-RP67.04, Dated September 1994, Methodologies for the Determination of Setpoints for Nuclear Safety-Related Instrumentation.
2.2 The general equation for channel uncertainty (CU) is:
2 2
2 2
2 ] 1/2 IRB I CU = [PM + PE + e 1 + e 2 +... + e N
+ BT +
T
- Where, PM = Random component of the process measurement uncertainty PE = Random component of the primary element uncertainty en= Square Root Sum of the Squares of all random independent components of uncertainty associated with a module n BT = Algebraic sum of all bias estimates for all biases in a channel (2.2)
RBT =Sum of the absolute value of all random bias (and arbitrary distribution) estimates in a channel.
2.3 The general equation for a module uncertainty (en from equation 2.2) is:
e= [RA2 + DR2 + TE2 + RE2 + SE2 + HE2 + SP2 + MTE2]
112 + B+ IRBI (2.3)
- Where, e = Module total uncertainty RA = Module reference accuracy DR = Module drift over a specified period TE = Module temperature effect RE = Module radiation effect SE =Module seismic (vibration) effect HE = Module humidity effect SP = Module static pressure effect MTE = Maintenance and test equipment used during module calibration B =Bias uncertainty estimates associated with module RB = Sum of absolute values of all random biases or abnormally distributed uncertainties for the module.
2.4 Bounding Uncertainty Loop Calculation J-UEF03, Rev. 001 Page 6 of21 Configuration A, in section 1.0 above, shows all of the loop components necessary to actuate the UHS Cooling Tower fans and by-pass valves. This section breaks down Configuration A into a bounding set of loop modules that shows the loop uncertainty for any one component actuation.
The 2AO-L2C-R circuit cards have no impact on signal transmission. These cards are used for isolation and interlocking. For this reason they have been removed from the uncertainty. The supply/return line loop selector hand switch will also not be included as it also has no impact on signal transmission. The three Low, High, and High-High setpoint bistable (switch) circuit cards are identical and for any one component actuation only one switch will be used. Thus for any one component actuation the signal is impacted by the three modules shown below.
The bounding uncertainty case is as follows:
Configuration B: Bounding Uncertainty Loop Environment A Process {
Weed 612-1 8-C-4-C-14-0-0 Environment B Foxboro 2AI-P2V Foxboro 2AP+ALM-AR
{
Component Actuation
Calculation J-UEF03, Rev. 001 Page 7 of21 2.5 Dependent uncertainties, shared amongst the separate modules, will be combined in such a way that independent variables will be combined using a square root sum of the square technique, (SRSS) while dependent variables will be combined by algebraic addition.
Reference 8.3.2 describes how the dependence of the various effects is related. The variables described in section 2.3 are compared in Table 3, Variable Dependency, for each component in the loop.
Table 3: Variable Dependency Effect TE TT TS PM -Process Measurement Accuracy i
PE - Primary Element Accuracy 1
RA - Reference Accuracy a
a DR - Module Drift 1
a a
TE-Temperature Effect b
b RE - Radiation Effect*
SE - Seismic Effect b
b HE - Humidity Effect b
b SP - Static Pressure Effect*
Power Supply c
c MTE**
a**
a**
a: The reference accuracy, or calibrated accuracy, and the module drift are both dependent with respect to M&TE and independent with respect to each other.
This does not include the TE as it is not calibrated.
b: Since these components are all located in the same cabinet, they are all exposed to the same environment and seismic effect.
Thus, the temperature, humidity, and seismic effects will be considered dependent between modules (circuit cards), but independent with respect to each other.
c: Since these components all use the same power supply, the power supply effects will be considered dependent.
i:
This effect is considered independent of all other effects.
Calculation J-UEF03, Rev. 001 Page 8 of21
- Since all of the components are exposed to no more than atmospheric pressure and minimal radiation, the only environmental effects are temperature and humidity.
- Only one piece of M&TE will be considered for all of the rack mounted components.
2.6 Final Setpoint Determination The final step in this calculation is to determine the setpoints for UHS Cooling Tower Fan and Bypass Valve control. Each setpoint is determined by combining the Safety Analysis Limits (SALs) found in the Design Inputs section, the setpoint uncertainties derived in this calculation, and margin.
The formula for a rising setpoint:
TS = SAL - CU - Margin The formula for a falling setpoint:
TS = SAL + CU + Margin
- Where, TS = Trip Setpoint SAL = Safety Analysis Limit CU = Channel Uncertainty 3.0 Assumptions 3.1 Assumptions concerning the values of specific error terms for the loop components are included within the "Design Inputs" section for that component.
Calculation J-UEF03, Rev. 00 I Page 9 of21 4.0 Design Inputs 4.1 Environmental data for temperature loops (Configuration B, section 2. 4) 4.1.1 Environment A: Room 3101, Pipe Space & Tank Area, Elevation 1974 The following data has been taken from FSAR Table 3.11(B)-1 (Normal Environment) and FSAR Table 3.11(B)-2 (Design Basis Accident (DBA) Accident) for this room:
a e :
T bl 5 E tdE xpec e nv1ronmen tA VI a ues Pressure Temp Humidity Dose Normal PH CF)
(maximin)
Dose Normal Atmospheric 104/60 70/30%
<0.0005
<200 7
DBA Atmospheric 120 95%
<2.5 X
X 4.1.2 Environment B: Room 3605, Control Room Equipment Cabinet Area The following data has been taken from FSAR Table 3.11(B)-1 (Normal Environment) and FSAR Table 3.11 (B)-2 (Design Basis Accident (DBA) Accident) for this room:
Table 6: Expected Environment B Values Pressure Temp Humidity Dose Normal PH CF)
(maximin)
Dose Normal Atmospheric 84/60 70/30%
<0.0005
<200 7
DBA Atmospheric 84*
95%
<2.5 X
X
- Qualified to 104 OF 4.2 Process Measurement Accuracy:
The Process Measurement Accuracy is an error that is introduced due to possible fluctuations in the process medium that will impact the temperature measurement.
Per calculation J-2B01, environmental effects are not considered. The temperature linearity is included in the basic accuracy. The humidity is assumed to have no effect as the RTD's are sealed devices that are also protected by a closed thermo-well and 0-ring sealed connection head assembly. No Process Measurement Accuracy will be incorporated for this loop.
Calculation J-UEF03, Rev. 001 Page 10 of21 4.3 Temperature Element Accuracy (TE, Primary Element Accuracy):
T bl 7 T a e : em perature El ement A ccuracy D.
I es1~n nputs EffectN aloe Formula Value References RA - Reference Accuracy l/2oF or 1/4% max temp, 0.5 OF whichever is greater DR-Module Drift 0.15°F/yr max* 0.5 yr 0.075 OF
- ' 4.3.1 TE-Temperature Effect See section 4.2.2, 4.2.2.1 None
- ' 4.3.2, 4.3.2.1 RE - Radiation Effect See Section 4.2.2 None SE - Seismic Effect See section 4.2.3 1 OF
- , 4.3.3, J-5588-000 18 HE - Humidity Effect See section 4.2.2, 4.2.2.2 None
- ' 4.3.2, 4.3.2.2 SP - Static Pressure Effect Not applicable for RTD None Power Supply Not applicable for RTD None
- , J2R03 MTE - Maint. & Test Equip.
R TD can not be calibrated None
- Calculation J-280 1 details the uncertainties associated with Weed Instruments Platinum RTD, model number 612-18-C-4-C-14-0-0.
4.3.1 Frequency of Element Accuracy Confirmation: Every 6 Months per MP 11-0004.
4.3.2 No uncertainty will be given to the temperature elements for temperature, radiation, and humidity. FSAR 3.11(8).5.7 describes a mild environment as being,:SilO OF,< 103 rads, and,:S 90% humidity while FSAR Table 3.11(8) shows this room reaching 120 OF and 95% humidity. However, this section also describes a mild environment as an environment that will not exceed its anticipated abnormal condition.
NUREG0588 implementation has further determined the temperature elements to be rated category 'D' for HEL8, LOCA, and MSL8 design basis accidents (Ref. Director Database). Category D is defined as being located in a mild environment post-accident. Temperature and humidity uncertainties are not necessary for equipment rated for mild environments. The expected radiation levels are within mild environment requirements.
4.3.2.1 Temperature Effect: This component will not be impacted by temperature shifts as its primary function is to measure temperature. Per Table 5, Expected Environment A Values, the element could see a temperature shift of 16°F (120-104oF) which is inside the temperature elements expected range. Per calculation J-2801, the normal environmental temperature effect for this component is included in the Reference Accuracy (RA).
4.3.2.2 Humidity Effect:
Per calculation J-2801, this component will not be impacted by humidity changes as the RTD' s are sealed devices that are protected by a closed Thermo-well and 0-ring sealed connection head assembly.
Calculation J-UEF03, Rev. 001 Page 11 of21 4.3.3 Seismic Effect= I °F. Qualification Report J-558B-OOOI8, pages 95 & I06 provides the pre and post seismic response for the Weed Instruments, model 6I2-I B-C-4-C-I4-0-0 temperature element (Table 8 Below). Comparing the post seismic functional test data to the baseline functional data shows a worst case drift of 0.205 n. Converting to degrees x*: =
0 205 n (Ref4.2.3.1, 4.2.3.2) determines a worst case seismic response of0.952°F.
100 F 21.54 n This value will be rounded to I oF for conservatism.
T bl 8 S 0
0 R a e :
eismic esponse o fT t
El empera ore em en t VII (Baseline XIII Difference Difference Test)
(Post Seismic Test)
(!l)
CF)
Pl: Gl-A (R2a-Rla)
I00.028 I00.04I
-0.013 Pl: Gl-B (R2a-Rlal IOO.l4I 99.981 0.16 P2: Gl-A (R2a-Rla) 99.997 99.964 0.033 P2: Gl-B (R2a-Rla)
I00.075 99.870 0.205 0.952 This qualification report provides an RTD qualification, considering a Design Basis Accident (DBA) effect for seismic uncertainty, which is over-conservative. This test was performed after radiation testing, thermal testing, vibration aging, humidity aging, and vibration aging again. The seismic tests follow IEEE standards IEEE-323 and 344.
4.3.3.1 Temperature Element Input Span: 100 °F. (30- 130 OF per Director Database) 4.3.3.2 Temperature Element Output Span:
Dependent on RTD specifications. EFTE0061:
21.54.0; EFTE0062 (Fitted Serial N1169): 21.54.0; EFTE0067 A (Fitted Serial N4155):
21.577.0; EFTE0068A (Fitted Serial N2051): 21.586 n (See Director Database). The worst case span of 21.54 n was used for this calculation as it bounds the other loops.
4.4 Temperature Transmitter (TT):
a e :
T bl 9 T em t
pera ure T "tt A
ransm1 er ccuracy EffectN alue Formula RA - Reference Accuracy 0.5% output span (1 00 oF)
DR-Module Drift 0.5% output span (1 00 oF)
TE-Temperature Effect 0.686 %output span (1 00 oF)
RE - Radiation Effect See Section 4.3.3 SE - Seismic Effect 0.5% output span (1 00 OF)
HE - Humidity Effect 0.67 % output span (1 00 OF)
SP - Static Pressure Effect Not applicable for Circuit Card Power Supply Effect 0.150% output span (1 00 OF)
MTE-Maint. & Test Equip.
See Section 4.6 Calculation J-UEF03, Rev. 00 I Page 12 of21 es1gn npu s D.
I t
Value References 0.5 OF
- , 4.4.1 0.5 OF
- , 4.4.1 0.686 OF
- , 4.4.2 None
- , 4.4.3 0.5 OF 0.67 OF
- , 4.4.2 None 0.15 OF
- , 4.4.1 0.1123 OF 4.6
- Calculation J-2A03 details the uncertainties associated with the Foxboro, Resistance to Voltage Converter, model number 2AI-P2V.
4.4.1 Transmitter output span: 100 OF. (30 - 130 OF per Director Database) 4.4.2 Temperature and Humidity Effect: DBA effects are not considered for this component.
The accident and normal environment are equivalent.
4.4.3 Radiation Effect: Radiation exposure within mild environment limits. No uncertainty will be considered for this effect.
4.5 Temperature Bistable (TS):
T bl 10 T a e t
empera ure B' t bl A IS a e ccurac_y Effect/Value Formula RA - Reference Accuracy 0.5% input span (1 00 oF)
DR-Module Drift 0.5% input span (100 OF)
TE-Temperature Effect 0.44% input span (1 00 oF)
RE - Radiation Effect See Section 4.3.3 SE - Seismic Effect 0.3% input span (1 00 OF)
HE - Humidity Effect 0.5% input span (1 00 oF)
SP - Static Pressure Effect Not applicable for Circuit Card Power Supply Effect 0.15% input span (1 00 OF)
MTE-Maint. & Test Equip.
See Section 4.6 Calculation J-UEF03, Rev. 001 Page 13 of21 D.
I es1gn t
npu s Value References 0.5 OF
- , 4.5.1 0.5 OF
- , 4.5.1 0.44 OF
- ' 4.5.1' 4.5.2 None
- , 4.5.3 0.3 OF 0.5 OF
- , 4.5.1, 4.5.2 None 0.15 OF
- , 4.5.1 0.1125 OF 4.6
- Calculation J-2A02 details the uncertainties associated with the Foxboro, bistable circuit card, model number 2AP+ALM-AR.
4.5.1 Input span: 100 °F. (30- 130 OF per Director Database) 4.5.2 Temperature and Humidity Effect: DBA effects are not considered for this component.
The accident and normal environment are equivalent.
4.5.3 Radiation Effect: Radiation exposure within mild environment limits. No uncertainty will be considered for this effect.
4.6 Maintenance & Testing Equipment (MTE)
Typically a 1 to 1 accuracy (MTE to Component) is used for calculating MTE uncertainties. I&C craft is then held to a 2 to 1 accuracy for calibration. This is done for conservatism in setpoint uncertainty calculations. However, calculation EF-123, which determines the safety analysis limits (SALs) for these setpoints requires all conservatisms to be removed. In order to remove conservatism, the actual MTE accuracies will be used for this calculation.
The temperature element is not calibrated. The temperature curves are determined at the factory and provided to Callaway for scaling.
Calculation J-UEF03, Rev. 001 Page 14 of21 The rack components (TT, TS) are calibrated using a decade box (RTD simulator) and Digital Multimeter (DMM). The DMM used to calibrate these loops must be a Keithley I97 or equivalent. Per reference 8.2.I 0, the uncertainty of this DMM is 0.03% span (I 00 OF per 4.4.I) or 0.03 °F. The decade box used to calibrate these loops must be a Transcat 70 I OT decade box or equivalent. Per reference 8.2.I 0 the uncertainty of the decade box is 0.02% of the reading. The worst case reading (the highest possible ohms reading) is I2I.I50 per reference 8.2.I, giving an uncertainty of 0.02423!2. Converting to degrees xo~ =
0 02423n (Ref 4.2.3.I, 4.2.3.2) determines a decade box uncertainty ofO.II25°F.
100 F 21.54.0
- 4. 7 Safety Analysis Limits (SAL)
- 4. 7.I Freeze Protection The ESW to UHS Cooling Tower Bypass Valves open on a low temperature to prevent water going over the cooling tower fill and freezing. In addition, when the initial DBA temperature is below freezing, the water, although rising in temperature, cannot be allowed over the fill until a certain point to ensure large droplets don't freeze and impede tower performance.
Per RFR 200802059, the criteria for closing EFHV0065/66 requires either the ambient wet-bulb temperature to be greater than 32 For the ESW return water temperature to be greater than or equal to 6I F. The fans may then be run at any temperature above this to provide cooling. The freeze protection function is necessary for both supply and return line setpoints. The Bypass valve fulfills a secondary role as being necessary for fan operation.
4.7.1.I Freeze Protection SAL-6I F.
(RFR 200802059) 4.7.2 Return Line SALs The UHS Cooling Tower Fan Speed and Bypass Valve Position is controlled off of the return line at the beginning of a DBA to protect the ESW system from reaching the max ESW temperature of 92.3 F (Ref. 8.2.4, 8.I.4) A discussion of the GOTHIC model anticipated max temperature and its acceptability can be found in Calculation EF -123 (Ref 8.I.4 ). With respect to setpoint determination the GOTHIC model requires the UHS Cooling Tower Fast Speed control (high-high setpoint) to actuate (set) between I 02.5 and 107.5 F. The fast speed (high-high setpoint) reset values are of no consequence as the temperature is not anticipated to reach this limit prior to swap over to the supply line temperature loops. The slow speed (high setpoint) fan runs in this scenario are negligible as the temperature in the return line heats up quickly and doesn't reach normal levels until after swap over to the supply line. The bypass valve must be closed prior to reaching the fast speed setpoint to allow for proper cooling.
4.7.2.1 Fan Fast Speed Set-Between I02.5 and 107.5 OF (Calculation EF -123)
4.7.3 Supply Line SALs Calculation J-UEF03, Rev. 001 Page 15 of21 After the ESW DBA temperature has reached a controllable state the UHS Cooling Tower Fan Speed and Bypass Valve Position will be controlled via the supply line temperature. At this point max temperature and UHS inventory is a concern for UHS operation. The GOTHIC model anticipated temperature values, as well as the inventory losses associated with using these setpoints are determined and can be found in calculation EF-123. With respect to setpoint determination the GOTHIC model fast and slow (high-high and high setpoints) set and reset values are used to ensure these two limits are maintained. The bypass valve is not expected to change state during the use of this control, but it must be closed to achieve proper cooling from the tower.
4.7.3.1 Fan Fast Speed Set-Between 87 and 92 OF (Calculation EF-123) 4.7.3.2 Fan Fast Speed Reset-Between 85 and 90 OF (Calculation EF-123) 4.7.3.1 Fan Slow Speed Set-Between 82 and 87 OF (Calculation EF-123) 4.7.3.2 Fan Slow Speed Reset-Between 80 and 85 oF (Calculation EF-123) 5.0 Calculation Table 11 summarizes the design input values for each module in the loop.
Table 11: Complete Accuracy Design Inputs List Effect TE TT TS PM - Process Measurement Ac.
PE - Primary Element A c.
RA - Reference Accuracy 0.5 OF 0.5 OF 0.5 OF DR - Module Drift 0.075 OF 0.5 OF 0.5 OF TE-Temperature Effect 0.686 OF 0.44 OF RE - Radiation Effect SE - Seismic Effect I OF 0.5 OF 0.3 OF HE - Humidity Effect 0.67 OF 0.5 OF SP - Static Pressure Effect PS - Power Supply Effect 0.15 OF 0.15 OF MTE - Maint. & Test Equip.
0.1125 OF 0.1125 OF
Calculation J-UEF03, Rev. 001 Page 16 of21 5.1 The final equation for the Channel Uncertainty combines equation 2.2 and 2.3 for use with the values found in Table 11. Dependant variables between modules from table 4 are taken out of their module specific uncertainty and combined in the overall channel uncertainty. The resultant Channel Uncertainty Equation is calculated below:
Equation 5.1 CU = [PM2 + PE2 + ([DRTE 2 + RATE 2 + SETi]
112)2 + qcRArr + MTErr)2 + (DRrr +
MTETT)2]
112i +([(RATs+ MTETs)2 + (DRTs + MTETs)2] 12i +(TEn+ TETs)2 +(SEn+
SETs)2 + (HETT+ HETs)2 + (PSrr+ PSTs)2]
112 5.2 Using equation 5.1 above with the numbers from Table 11 derives the following Channel Uncertainty:
cu = [02 + 02 + ([0.075 2 + 0.5 2 + 1.02] 112i + ([(0.5 + 0.1125i + (0.5 + 0.1125)2] 112i +
([(0.5 + 0.1125)2 + (0.5 + 0.1125)2] 112) 2 + (0.686+ 0.44)2 + (0.5+ 0.3)2 + (0.67+ 0.5)2 +
(0.15+ 0.15i] 112 cu = 2.475 OF The Setpoint Uncertainty associated with temperature instrumentation loops EFT -0067 A, EFT-0068A, EFT-0061, and EFT-0062 is 2.475 °F. For ease of use and to add margin, the setpoint uncertainty (Channel Uncertainty CU) used in this calculation will be rounded up to 2.5 OF.
5.3 Setpoint Determination Per the methodology for deriving a Trip Setpoint (TS), found in section 2.6, TS is equal to the Safety Analysis Limit (SAL) +/- the Channel Uncertainty (CU) +/- Margin (M).
The values are added or subtracted depending on whether the SAL is triggered rising or falling (directionality). The setpoints found in Tables 12 and 13 have been derived using this equation.
5.3.1 Example Calculation (Tables 12113): Supply Line TSHH Set (Fan Fast speed actuation)
Required action point: 102.5-107.5.
Calculation Methodology (2.6): Rising: TS = SAL - CU -Margin Calculation Methodology (2.6): Falling: TS = SAL+ CU +Margin If TS is known, margin is then: Rising: Margin = SAL - CU - TS IfTS is known, margin is then: Falling: Margin= SAL- (CU + TS)
Trip Setpoint Rising: TS = 107.5 OF - 2.5 OF - 0 OF = 105 OF Trip Setpoint Falling: TS = 102.5 OF+ 2.5 OF + 0 oF= 105 OF Trip Setpoint = 105 OF Margin Rising: 107.5 OF - 2.5 oF - 105 oF = 0 oF Margin Falling: 107.5 OF- (2.5 OF+ 105 OF)= 0 OF
Calculation J-UEF03, Rev. 00 I Page 17 of21 Table 12: Return Line (EFT -0067 A, EFT -0068A) Setpoint Determination Setpoint Required Action Margin References CF)
Point CF)
CF)
TSHH Set (fast 105.0 102.5-107.5 0
EF-123, 4.7.2, fan start)***
4.7.2.1 TSHH Reset (fast 102.5 (Note 1)
(Note 1)
EF-123, 4.7.2 fan stop)
TSH Set (slow 95.0 (Note 1)
(Note 1)
EF-123, 4.7.2 fan start)
TSH Reset (slow 92.5 (Note 1)
(Note 1)
EF-123, 4.7.2 fan stop)
TSL Reset (close 84.0 92.5 (Note 2) 6.0 EF-123, 4.7.1, bypass valve)***
4.7.2, 4.7.3 TSL Set (open 78.0 61.0 14.5 EF-123, 4.7.1, bypass valve)***
200802059
- Setpoint supports a Safety Analysis Limit (SAL). Other setpoints may be changed without impacting the analysis (EF-123).
Note 1: The values chosen for non-SAL setpoints support the values used in calculation EF-123. As their function does not impact the safety analysis results, they may be revised without recourse to the safety analysis. Thus the margin associated with these setpoints is not considered. These setpoints do operate in the proper order. With raising temperature the valve closes followed by the slow start of the fans and finishing with the fast start of the fans. With falling temperature when the fast fans kick off the slow fans will be running. The slow fans will then kick off followed by the valve opening. It is important to note that there is an interlock to ensure the fast fans will run if a set signal has been provided to the slow and fan start circuitry.
Note 2: The valve must be closed prior to the fast speed start signal to ensure the safety analysis is maintained. However, the valve should be closed prior to the slow speed start for proper cooling tower operation. For this reason the slow speed start setpoint was used to determine valve reset margin.
Calculation J-UEF03, Rev. 001 Page 18 of21 Table 13: Supply Line (EFT -0061, EFT -0062) Setpoint Determination Setpoint Required Action Margin References fF)
Point fF) fF)
TSHH Set (fast 89.5 87.0-92.0 0
EF-123, 4.7.3, fan start)***
4.7.3.1 TSHH Reset (fast 87.5 85.0-90.0 0
EF-123 fan stop)***
TSH Set (slow 84.5 82.0-87.0 0
EF-123 fan start) ***
TSH Reset (slow 82.5 80.0-85.0 0
EF-123 fan stop)***
TSL Reset (close 79.0 82.5 1
EF-123, 4.7.1, bypass valve)***
4.7.3 TSL Set (open 73.0 61.0 9.5 EF-123, 4.7.1, bypass valve)***
200802059
- Setpoint supports a Safety Analysis Limit (SAL). Other setpoints may be changed without impacting the analysis (EF-123).
6.0 Impact Assessment 6.1 Upstream Calculations (reviewed, not impacted): J-2801, J-2A02, J-2A03, & EF-123.
6.2 Upstream Calculations (impacted): J-UEF03A, J-1EF03.
This calculation will supersede the two calculations discussed above. See section 1.1, Calculation History, for more information.
6.3 Downstream Calculations: None.
6.4 Downstream Design Basis Documents: Setpoint data for EFTSL0061/62/67 A/68A, EFTSH0061/62/67 A/68A, and EFTSHH0061/62/67 A/68A.
MP 11-0004. FSAR SA 9.2.5.2.3 & FSAR SA 9.2.5.5.
The setpoint data has been revised via MP 11-0004 to reflect the values chosen in this calculation. MP 11-0004 created this calculation revision and is thus not impacted by the changes. The FSAR sections have been revised via the 50.59 review found in MP 11-0004.
6.5 50.59 Applicability This calculation supports the changes identified in MP 11-0004 and calculation EF -123.
The 50.59 review performed via MP 11-0004 covers all changes associated with this calculation.
7.0 Conclusion Calculation J-UEF03, Rev. 001 Page 19 of21 This calculation determines the UHS Cooling Tower fan speed control and ESW to UHS Cooling Tower bypass valve control setpoints considering instrument uncertainties. A Channel Uncertainty for instrumentation temperature loops EFT -0061, EFT -0062, EFT-0067 A, and EFT -0068A of 2.5 OF has been determined via this calculation. The UHS Fan slow and fast speed control setpoints, as well as the UHS bypass valve control setpoints have additionally been determined. See Table 12, Supply Line (EFT-0067A, EFT -0068A) Setpoint Determination, and Table 13, Return Line (EFT -0061, EFT -0062)
Setpoint Determination, for a breakdown of the new values.
7.1 Margin Discussion The margin associated with each setpoint is discussed in Table 12, Supply Line (EFT-0067A, EFT-0068A) Setpoint Determination, and Table 13, Return Line (EFT-0061, EFT-0062) Setpoint Determination.
Per section 5.2, the Channel Uncertainty was rounded up to 2.5 OF, providing a relatively small amount of margin in the setpoint determination section.
Per section 4.3.3, the seismic effect was rounded to 1 oF, providing a relatively small amount of margin to the temperature element uncertainty determination. Section 4.3.3 also discusses inherent margin associated with the testing of this equipment.
8.0 References 8.1 Calculation References 8.1.1 J-2A02, Rev 001 -Accuracy: Foxboro Bistable 2AP+ALM-AR 8.1.2 J-2A03, Rev 001-Accuracy: Foxboro Res to Volt Conv Model2AI-P2V 8.1.3 J-2B01, Rev 001-Accuracy: Temperature Element (RTD) Weed Series 611 & 612 8.1.4 EF-123, Rev 000 -Callaway UHS Cooling Pond Performance using GOTHIC Model CN-CRA-10-21 8.1.5 J-1EF03, Rev 000- Instrument Loop Uncertainty Estimate: EF Loops 67A & 68A 8.1.6 J-UEF03A, Rev 001-Min Allow Setpt Rack Trip Val & Sys Trip Val: Lps 67A & 68A.
8.1. 7 EF -54, Rev 003A -
This Calculation Predicts the UHS performance for the meteorological conditions identified in FSAR SA TABLE 2.3-13 AND 2.3-15.
8.2 Design Basis Documentation References 8.2.1 Director Database (CEL, Callaway Equipment List) 8.2.2 RFR 200802059, Update OTN-EF-00001 Rev. 36 to reflect current UHS CT operating curves 8.2.3 MP 11-0004, Ultimate Heat Sink (UHS) Temperature Issue Solution 8.2.4 FSAR SP Chapter 9.2 8.2.5 FSAR SA Chapter 9.2 8.2.6 FSAR Table 3.11(B)-1, Normal Environment 8.2.7 FSAR Table 3.11(B)-2 Design Basis Accident (DBA) Accident 8.2.8 FSAR 3.11(B).5.7
Calculation J-UEF03, Rev. 001 Page 20 of21 8.2.9 J-5588-00018, Fast Response RTD/RTDT & Thermocouple Assemblies-Test Qual 8.2.1 0 AmerenUE letter NED080004, "Margin Recovery Program - Reactor Protection System Setpoint Uncertainty Calculations Information Request", 1/22/08.
8.2.11 AmerenUE letter NED080025, "Comments on Verified Draft Version of the Overtemperature and Overpower Delta T Uncertainty Calculations", 6/2/08 8.2.12 FSAR SA 9.2.5.2.3, System Operation 8.2.13 FSAR SA 9.2.5.5, Instrument Applications
- 8. 3 Industry References 8.3.1 ISA-S67.04, Dated September
- 1994, Setpoints for Nuclear Safety-Related Instrumentation 8.3.2 ISA-RP67.04, Dated September 1994, Methodologies for the Determination of Setpoints for Nuclear Safety-Related Instrumentation 8.3.3 NUREG0588 8.3.4 IEEE-323 8.3.5 IEEE-344
- 8. 4 Component References 8.4.1 EFT-0061-ESW PMP (2PEF01A) DISCH TEMP 8.4.2 EFT-0062-ESW PMP (2PFE01B) DISCH TEMP 8.4.3 EFT-0067A-ESW COOL TWR A (SEF01) INLET TEMP 8.4.4 EFT -0068A - ESW COOL TWR B (SEFO 1) INLET TEMP 8.4.5 EFTSL0061-UHS COOLTWR Bypass VLV Temp SW Low ESW SPLY TRN A 8.4.6 EFTSL006112-FOXBORO CIRCUIT CARD 8.4.7 EFTSL006122-FOXBORO CIRCUIT CARD 8.4.8 EFTSL0062-UHS COOLTWR Bypass VLV Temp SW Low ESW SPLY TRN B 8.4.9 EFTSL006212-FOXBORO CIRCUIT CARD 8.4.1 0 EFTSL006222-FOXBORO CIRCUIT CARD 8.4.11 EFTSL0067 A-ESW TRN A TO UHS COOL TOWERS A & C LO TEMP SW 8.4.12 EFTSL0067 A12-FOXBORO CIRCUIT CARD 8.4.13 EFTSL0067 A22 -FOXBORO CIRCUIT CARD 8.4.14 EFTSL0068A-ESW TRN B TO UHS COOL TOWERS B & D LO TEMP SW 8.4.15 EFTSL0068A12-FOXBORO CIRCUIT CARD 8.4.16 EFTSL0068A22 -FOXBORO CIRCUIT CARD 8.4.17 EFTSH0061 - UHS COOLTWR FAN A & C TEMP SW HI ESW SPL Y TRN A 8.4.18 EFTSH006113 -FOXBORO CIRCUIT CARD 8.4.19 EFTSH006123-FOXBORO CIRCUIT CARD 8.4.20 EFTSH006133 - FOXBORO CIRCUIT CARD 8.4.21 EFTSH0062-UHS COOLTWR FAN B & D TEMP SW HI ESW SPLY TRN B 8.4.22 EFTSH006213-FOXBORO CIRCUIT CARD 8.4.23 EFTSH006223 -FOXBORO CIRCUIT CARD 8.4.24 EFTSH006233 - FOXBORO CIRCUIT CARD 8.4.25 EFTSH0067 A - ESW TRN A TO UHS COOL TOWERS A & C HI TEMP SW 8.4.26 EFTSH0067A13-ESW COOL TWR A (SEF01) INLET TEMP 8.4.27 EFTSH0067 A23 - FOXBORO CIRCUIT CARD 8.4.27 EFTSH0067 A33 - FOXBORO CIRCUIT CARD
Calculation J-UEF03, Rev. 001 Page 21 of21 8.4.28 EFTSH0068A-ESW PMP B TO UHS COOL TOWERS 8 & D HI TEMP SW 8.4.29 EFTSH0068A13-ESW COOL TWR B (SEFOI) INLET TEMP 8.4.30 EFTSH0068A23 - FOXBORO CIRCUIT CARD 8.4.31 EFTSH0068A33 - FOXBORO CIRCUIT CARD 8.4.32 EFTSHH0061-UHS COOLTWR FAN A & C TEMP SW HIHI ESW SPLY TRN A 8.4.33 EFTSHH006II2-FOXBORO CIRCUIT CARD 8.4.34 EFTSHH006I22-FOXBORO CIRCUIT CARD 8.4.36 EFTSHH0062-UHS COOLTWR FAN B & D TEMP SW HIHI ESW SPLY TRN B 8.4.37 EFTSHH0062I2-FOXBORO CIRCUIT CARD 8.4.38 EFTSHH006222 - FOXBORO CIRCUIT CARD 8.4.39 EFTSHH0067A-ESW TRN A TO UHS COOL TOWERS A & CHI/HI TEMP SW 8.4.40 EFTSHH0067AI2-ESW COOL TWR A (SEFOI) INLET TEMP 8.4.4I EFTSHH0067 A22 - FOXBORO CIRCUIT CARD 8.4.42 EFTSHH0068A-ESW TRN B TO UHS COOL TOWERS B & D HI/HI TEMP SW 8.4.43 EFTSHH0068AI2-FOXBORO CIRCUIT CARD 8.4.44 EFTSHH0068A22 - FOXBORO CIRCUIT CARD 8.4.45 EFTE006I-ESW PMP A DISCH TEMP ELEM 8.4.46 EFTE0062 - ESW PMP B DISCH TEMP ELEM 8.4.47 EFTE0067A-ESW TRN A TO UHS COOL TOWERS A & C TEMP ELEM 8.4.48 EFTE0068A-ESW TRN B TO UHS COOL TOWERS B & D TEMP ELEM 8.4.49 EFTT006I - ESW A TEMP TO POWER BLOCK 8.4.50 EFTT0062-ESW B TEMP TO POWER BLOCK 8.4.5I EFTT0067 A - ESW COOL TWR A (SEFO I) INLET TEMP 8.4.52 EFTT0068A - ESW COOL TWR B (SEFO I) INLET TEMP 8.4.53 EFHS0067-A Train ESW RTN/SPLY (Loops 67A/6I) Line Temp Hand Switch 8.4.54 EFHS0068 - B Train ESW RTN/SPL Y (Loops 68A/62) Line Temp Hand Switch 8.4.55 EFHV0065 - ESW UHS COOL-TWR TRN A BYP HV 8.4.56 EFHV0066-ESW UHS COOL-TWR TRN B BYP HV 8.4.57 CEFOIA-ESW ULTIMATE HEAT SINK COOLING TOWER FAN A 8.4.58 CEFOIB-ESW ULTIMATE HEAT SINK COOLING TOWER FAN B 8.4.59 CEFOIC-ESW ULTIMATE HEAT SINK COOLING TOWER FAN C 8.4.60 CEFOID-ESW ULTIMATE HEAT SINK COOLING TOWER FAN D