TXX-4671, Interim Deficiency Rept CP-85-26 Re Steam Generator Upper Lateral Restraint Embedment Design.Initially Reported on 850719.Concern Being Evaluated & Scheduled for Resolution by 860502.Final Rept Will Be Submitted by 860523
| ML20140D053 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 01/22/1986 |
| From: | Counsil W, Woodlan D TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | Johnson E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| CP-85-26, TXX-4671, NUDOCS 8601290083 | |
| Download: ML20140D053 (1) | |
Text
Log # TXX-4671 TEXAS UTILITIES GENERATING COMPANY File # 10110 NKYW AY TOWER. 400 N(>RTH UEJVE NTREET. L.3,. a t. DALLAM, TEXAM 7820 3 January 22, ?^86 rm
[
- . hMUi?L".1.',2 Mr. Eric H. Johnson, Acting Director i B
- g '2 41%
Division of Reactor Safety and Projects Iy U.S. Nuclear Regulatory Commission kg g
611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012 L
Sf;dJECT:
COMANCHE PEAK STEAM ELECTRIC STATION DOCKET N0. 50-445 UPPER LATERAL RESTRAINT EMBEDMENT DESIGN SDAR:
Dear Mr. Johnson:
On July 19, 1985, we verbally notified your Mr. D. Powell of a deficiency regarding the Unit 1 steam generator upper lateral restraint embedment design.
This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e). We have submitted interim reports TXX-4532 and TXX-4626, dated August 9, 1985, and November 20, 1985, respec-tively.
This concern is oeing evaluated under CPRT Program Plan Item V b and is scheduled for resolution by May 2, 1986.
We are continuing our evaluation and anticipate completion of our final report by May 23, 1986.
Very truly yours, (2.G. O W. G. Counsil By:
0.R. Woodlan Licensing Supervisor JCH/gj c-NRC Region IV (0 + 1 copy)
Director, Inspection & Enforcement (15 copies)
U. S. Nuclear Regulatory Commission Washington, D.C.
20555 9601290003 860122 PDR ADOCK 0500 5