Submits Response Schedule for SER Outstanding Items
ML20032D163
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/09/1981
From: Schmidt H
TEXAS UTILITIES SERVICES, INC.
To: Tedesco R
Office of Nuclear Reactor Regulation
References
TASK-1.C.1, TASK-1.C.8, TASK-1.D.1, TASK-2.B.2, TASK-2.F.1, TASK-2.F.2, TASK-3.A.1.2, TASK-3.D.1.1, TASK-TM TXX-3435, NUDOCS 8111130453
Download: ML20032D163 (2)


Text

,... r TEXAS UTILITIES SERVICES INC.

Log # TXX-3435 ami mwas wwsn. o4u.as. TEXAM 752OI File # 10010 November 9,1981

~

/

N i

Mr. Robert L. Tedesco f.,

NOV121981 Assistant Director for Licensing d 848mgjgm Division of Licensing

\\^

N O/

U. S. Nuclear Regulatory Comission

, %P/

Washington, D.C.

20555

.y es,,,.-

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION OUTSTANDING ITEMS RESPONSE SCHEDULE DOCKET NOS. 50-445 and 50-446

Dear Mr. Tedesco:

In order to aid in your planning the following schedule for su!)mitting information on CPSES SSER outstanding issues is provided:

Subject Response Schedule 1.

Pipe break damage analysis September 1982 2.

Seismic qualification of equipment July 1982 3.

Environmental qualification of equipment July 1982 4.

Preservice and inservice inspection June 1982 5.

Transfer of containment spray February 1982 l

6.

Low-temperature overpressure protection Submitted l

control system TXX-3433 dated l

November 2, 1981 7.

Control system failure consequenses Resolved from harsh environment 8.

Fire protection program 00Dl l

- Alternate shutdown system March 1982 D

l

- Confonnance with Appendix R June 1982 5

f

,/o 8111130453 811109 PDR ADOCK 05000445 E

PDR

.; 9.

TMI Action Plan I.C.1 Guidance for emergency procedures I.C.8 Pilot monitoring program I.D.1 Control room design review July 1982 II.B.2 Plant shielding December 1981 II.F.1 Added accident monitoring Submitted A27

~

instrumentation FSAR II.F.2 Instrumentation to detect July 1982 inadequate core cooling-I I I.~ A.1. 2 Upgrading emergency support Submitted A27 facilities FSAR III.A.2 Improving licensee emergency Submitted A28 preparedness FSAR III.D.1.1 ~ Integrity of systems outside March 1982 containment

  • Schedule contingent on completion of I.C.9.

CPSES will use Westinghouse Owners Group guidelines in preparation of emergency procedures.

Sincerely,

\\

H. C. Schmidt JSM:grr cc: