TECHNICAL SPECIFICATIONS TASK FORCE TSTF A JOINT OWNERS GROUP ACTIVITY December 20, 2006 TSTF-06-36 PROJ0753 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Request to Revise Response Schedule for TSTF-476

REFERENCE:

Letter from T. J. Kobetz (NRC) to Technical Specifications Task Force (TSTF), dated October 27, 2006, regarding TSTF-476.

Dear Sir or Madam:

The referenced letter regarding TSTF-476, "Improved BPWS Control Rod Insertion Process (NEDO-33091)," requested a response from the TSTF within 60 days. At the August 17, 2006 public meeting between the TSTF and the NRC, the TSTF requested that 90 days be scheduled for the TSTF to respond to NRC Requests for Additional Information (RAIs). The TSTF requests that the NRC extend the scheduled time for the TSTF to respond to the referenced RAI to 90 days.

Should you have any questions, please do not hesitate to contact us.

Wesley Sparkman (PWROG/W) Michael Crowthers (BWROG)

Brian Woods (PWROG/CE) Paul Infanger (PWROG/B&W) cc: Tim Kobetz, Technical Specifications Branch, NRC Ross Telson, Technical Specifications Branch, NRC 11921 Rockville Pike, Suite 100, Rockville, MD 20852 Phone: 301-984-4400, Fax: 301-984-7600 Email: tstf@excelservices.com Administered by EXCEL Services Corporation