- 05000029/LER-1977-032-03, /03L-0:on 770611,during Surveillance testing,TV- 209 Containment Drain Line Trip Isolation Valve Failed to Close.Caused by Excessively Tightened Packing.Packing Probably Overtightened During Recent Containment Leak Insp + (15:39:29, 24 December 2024)
- ML19345A645 + (15:39:30, 24 December 2024)
- 05000029/LER-1977-032, Forwards LER 77-032/03L-0 + (15:39:32, 24 December 2024)
- ML19345A641 + (15:39:33, 24 December 2024)
- ML19345A639 + (15:39:36, 24 December 2024)
- ML19345A637 + (15:39:37, 24 December 2024)
- 05000029/LER-1976-008, Updated LER 76-008/010-0:on 760730,review of Rod Ejection Accident Analysis Revealed Error in Method Used for Core 11 Analysis.Caused by Error in Methods & Application of Analysis Codes.Sys of Documentation Control Initiated + (15:39:42, 24 December 2024)
- 05000029/LER-1977-020-03, /03L-0:on 770415,during Paper Replacement in Main Coolant Leakage Vapor Container Air Particulate Monitor Paper Drive Found Inoperative.Caused by Deterioration of Reduction Gears.Reduction Gears Rebuilt & Lubricated + (15:39:45, 24 December 2024)
- 05000029/LER-1977-020, Forwards LER 77-020/03L-0 + (15:39:47, 24 December 2024)
- 05000029/LER-1977-024-03, /03L-0:on 770428,loop Seal Discharge Radioactive Gaseous Monitor Indication Went to Zero.Caused by Drift in RM-40 Power Supply High Voltage.High Voltage Adjusted + (15:39:50, 24 December 2024)
- 05000029/LER-1977-024, Forwards LER 77-024/03L-0 + (15:39:52, 24 December 2024)
- 05000029/LER-1977-026-03, /03L-0:on 770518,control Room Received Low Flow Alarm on Primary Vent Stack Particulate Radiation Monitor Channel.Caused by Paper in Util Being Slightly Oversized & Boundup.New Roll of Paper Installed + (15:39:54, 24 December 2024)
- 05000029/LER-1977-026, Forwards LER 77-026/03L-0 + (15:39:56, 24 December 2024)
- 05000029/LER-1977-028-03, /03L-0:on 770530,noble Gas Monitor of Primary Vent Stack Radiation Detection Sys Failed.Cause Could Not Be Ascertained as Trouble Could Not Be Repeated After Alarm Reset + (15:39:58, 24 December 2024)
- 05000029/LER-1977-028, Forwards LER 77-028/03L-0 + (15:40:00, 24 December 2024)
- 05000029/LER-1977-027-03, /03L-0:on 770524,biannual Recalibr Performed on Two LPIS Accumulator Channels.Instruments Below Tech Specs Limit.Recalibr Adjustments Made to Bring Channels within Tech Specs Limit + (15:40:03, 24 December 2024)
- ML19345A618 + (15:40:05, 24 December 2024)
- 05000029/LER-1977-027, Forwards LER 77-027/03L-0 + (15:40:06, 24 December 2024)
- ML19345A614 + (15:40:07, 24 December 2024)
- ML19345A612 + (15:40:08, 24 December 2024)
- W3P80-0167, Forwards Amend 13 to OL Application & to Fsar,Including Responses to Addl Info Requests from Auxiliary Sys Branch, I&C Branch,Reactor Sys Branch & Info on Emergency Feedwater Sys.Two Hundred Oversize Drawings Encl + (15:40:09, 24 December 2024)
- 05000029/LER-1977-018-03, /03L-0:on 770326,steam Generator Chloride Concentration Increased to Max Level of 4 Ppm in Steam Generator 2,exceeding Tech Specs Limit + (15:40:14, 24 December 2024)
- 05000029/LER-1977-018, Forwards LER 77-018/03L-0 + (15:40:16, 24 December 2024)
- 05000029/LER-1977-014-03, /03L-0:on 770308,iodine Channel of Primary Vent Stack Radiation Monitoring Sys Failed to Meet High Level Count Rate Acceptance Criteria.Caused by Voltage Drift. Voltage Adjusted + (15:40:21, 24 December 2024)
- 05000029/LER-1977-014, Forwards LER 77-014/03L-0 + (15:40:23, 24 December 2024)
- 05000029/LER-1977-029-03, /03L-0:on 770603,during Mode 1,primary Vent Stack Radiation Detection Sys Particulate Channel Failed.Caused by Control Setpoint Being Set Too Close Together.Control Setpoint Readjusted + (15:40:25, 24 December 2024)
- 05000029/LER-1977-029, Forwards LER 77-029/03L-0 + (15:40:27, 24 December 2024)
- 05000029/LER-1976-012-01, /01T-0:on 761119,safety Injection Accumulator for Boron Was 30 Ppm Over Tech Specs & 80 Ppm Over Administrative Limits.Investigation Revealed That Std Sodium Hydroxide Titrant Had Concentrations Lower than Predicted + (15:40:29, 24 December 2024)
- 05000029/LER-1976-012, Forwards LER 76-012/01T-0 + (15:40:31, 24 December 2024)
- 05000029/LER-1976-005-03, /03L-0:on 760520,auxiliary Operator Noted Slight Leakage from Weld on Inlet Charging Pump 3 Relief Valve. Caused by Pullback Gap Not Allowed During Installation of Pipe & Vibration Induced Fatigue Failure + (15:40:33, 24 December 2024)
- 05000029/LER-1976-005, Forwards LER 76-005/03L-0 + (15:40:35, 24 December 2024)
- 05000029/LER-1977-013-03, /03L-0:on 770307,following Power Reduction to Identify Plug Leaking Condenser Tube,Chlorides in Steam Generators 1 & 4 Exceeded Tech Specs Limits.Caused by Chloride Concentration Buildup in Steam Generator + (15:40:37, 24 December 2024)
- ML19345A593 + (15:40:39, 24 December 2024)
- 05000029/LER-1977-013, Forwards LER 77-013/03L-0 + (15:40:40, 24 December 2024)
- ML19345A590 + (15:40:43, 24 December 2024)
- 05000029/LER-1977-012-03, /03L-0:on 770306,alarm Setpoint Adjustment of Radiation Monitor for Steam Generator Blowdown Found Defective.Caused by Alarm Setpoint Control Failure to Adjust.Control Replaced + (15:40:44, 24 December 2024)
- ML19345A587 + (15:40:46, 24 December 2024)
- 05000029/LER-1977-012, Forwards LER 77-012/03L-0 + (15:40:48, 24 December 2024)
- 05000029/LER-1977-011-03, /03L-0:on 770301,emergency Diesel Generator 1 Starter Motor Failed During Surveillance Test.Caused by Armmature Shaft Being Broke.Starting Motor Replaced + (15:40:50, 24 December 2024)
- 05000029/LER-1977-011, Forwards LER 77-011/03L-0 + (15:40:52, 24 December 2024)
- ML19345A581 + (15:40:53, 24 December 2024)
- 05000029/LER-1977-010-03, /03L-0:on 770224,light Leakage Found from Weld on Discharge Line of Charging Pump 3 at Inlet to Pump Relief Valve.Caused by Failure of Weld & Pipe Nipple.Piping Sections Replaced + (15:40:58, 24 December 2024)
- ML19345A578 + (15:40:59, 24 December 2024)
- 05000029/LER-1977-010, Forwards LER 77-010/03L-0 + (15:41:01, 24 December 2024)
- ML19345A575 + (15:41:02, 24 December 2024)
- 05000029/LER-1977-019-03, /03L-0:on 770402,radioactive Gaseous Waste Monitor Loop Seal Discharge Monitor Alarm Failed to Operate.Caused by Alarm Setpoint & Meter Pointer Contacts Being Corroded. Contacts Cleaned,Mylar Film & Protective Tape Replaced + (15:41:04, 24 December 2024)
- 05000029/LER-1977-019, Forwards LER 77-019/03L-0 + (15:41:06, 24 December 2024)
- 05000029/LER-1977-025-03, /03L-0:on 770503,when Component Cooling Radiation Monitor Channel Drawer Removed,Cables Dropped Into Uncovered High Voltage Power Supply Used for Loop Seal Discharge Monitor Causing Short Circuit & Failure of Monitor + (15:41:08, 24 December 2024)
- ML19345A570 + (15:41:09, 24 December 2024)
- ML19345A568 + (15:41:11, 24 December 2024)
- 05000029/LER-1977-025, Forwards LER 77-025/03L-0 + (15:41:12, 24 December 2024)