Semantic search

Jump to navigation Jump to search
 Issue dateTitle
ML22292A03510 November 2022Issuance of Amendment No. 246 Secondary Containment and the Fuel Building Railroad Airlock (EPID L-2022- LLA-0055)
RS-22-020, Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock7 April 2022Request for License Amendment to Revise the Secondary Containment Design Basis to Credit the Fuel Building Railroad Airlock
ML22028A01131 January 2022Slides for Fbra Pre-submittal Meeting of 2022-01-31
ML21132A28828 June 2021Issuance of Amendment No. 238, Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4B
RS-20-052, Application to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Extended Completed Times-RITSTF Initiative 4b30 April 2020Application to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Extended Completed Times-RITSTF Initiative 4b
ML19168A08426 June 2019Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019
ML18127B72314 May 2018Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018
ML15342A3548 December 2015License Amendment Request Extension of Secondary Containment - NRC Pre- Application Meeting December 9, 2015
RS-14-006, Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Chapter 3 - Design of Structures, Components, Equipment, and Systems9 January 2014Clinton, Unit 1, Updated Safety Analysis Report, Revision 16, Chapter 3 - Design of Structures, Components, Equipment, and Systems
ML14015A0989 January 2014Updated Safety Analysis Report, Revision 16, Chapter 3 - Design of Structures, Components, Equipment, and Systems
RS-13-009, Clinton, Unit 1, Updated Safety Analysis Report, Revision 15, Chapter 3 - Design of Structures, Components, Equipment and Systems10 January 2013Clinton, Unit 1, Updated Safety Analysis Report, Revision 15, Chapter 3 - Design of Structures, Components, Equipment and Systems
ML13016A31510 January 2013Updated Safety Analysis Report, Revision 15, Chapter 3 - Design of Structures, Components, Equipment and Systems
IR 05000461/20120045 November 2012IR 05000461-12-004; 09/30/2012; Clinton Power Station; Maintenance Effectiveness
IR 05000461/20120036 August 2012IR 05000461-12-003, 04/01/12 - 06/30/12; Clinton Power Station, Unit 1; Adverse Weather Protection, Problem Identification and Resolution
U-603131, Application for Amend to License NPF-62,changing CPS Design Requirements for Physical Protection from Tornado Missiles for safety-related Equipment,As Described in Plant Usar. Revised USAR Pages,Encl1 March 1999Application for Amend to License NPF-62,changing CPS Design Requirements for Physical Protection from Tornado Missiles for safety-related Equipment,As Described in Plant Usar. Revised USAR Pages,Encl
05000461/LER-1997-032, Forwards LER 97-032-00,plant Was Outside Design Basis Due to Inadequate Tornado Missile Protection Caused by Design Error,Iaw 10CFR50.73 & 10CFR21.21.Commitments Made in Rept, Listed2 January 1998Forwards LER 97-032-00,plant Was Outside Design Basis Due to Inadequate Tornado Missile Protection Caused by Design Error,Iaw 10CFR50.73 & 10CFR21.21.Commitments Made in Rept, Listed
Information Notice 1996-64, Modifications to Containment Blowout Panels Without Appropriate Design Controls10 December 1996Modifications to Containment Blowout Panels Without Appropriate Design Controls
U-602500, Forwards Rev 6 to CPS USAR & 10CFR50.59 Rept Identifying SEs for Implemented Changes Affecting USAR for Period of 931210- 95042918 October 1995Forwards Rev 6 to CPS USAR & 10CFR50.59 Rept Identifying SEs for Implemented Changes Affecting USAR for Period of 931210- 950429
ML20040F2511 February 1982Forwards Schedule for Providing Info to Close SER Confirmatory Issues,In Response to NRC 820125 Request
ML20040F02727 January 1982Forwards Proposed Schedule for Providing Info to Close Draft SER Confirmatory Issues,Per 820125 Request
ML19348A01126 May 1981Forwards Supporting Info on Clinton FSAR Consisting of Responses to NRC Round 1 Questions Raised on Grand Gulf Fsar.Appropriate Text Page Changes Applicable to Clinton Station Are Provided in FSAR Amend 3,Apr 1981