Issue date | From | Title | Project stage | |
---|---|---|---|---|
ML15037A540 | 24 February 2015 | Brian Wittick License Renewal Projects Branch 2 | Project Manager Change for the License Renewal of Diablo Canyon Power Plant, Units 1 and 2, (TAC Nos. MF4019 and MF4020) | Other |
ML15202A098 | 21 July 2015 | Michael Wentzel Division of License Renewal | Slides for the August 5, 2015 Diablo Canyon Power Plant License Renewal Application Public Scoping Meeting | Meeting |
ML15233A518 | 28 August 2015 | Michael Wentzel License Renewal Projects Branch 2 | License Renewal Environmental Site Audit Regarding Diablo Canyon Power Plant, Units 1 and 2-SAMA | Other |
ML15233A491 | 1 September 2015 | Office of Nuclear Reactor Regulation | August 5, 2015, Public Scoping Meetings for the Environmental Review of the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application | Meeting |
ML15243A582 | 8 September 2015 | Michael Wentzel License Renewal Projects Branch 2 | License Renewal Environmental Site Audit Regarding Diablo Canyon Power Plant, Units 1 and 2 | Other |
ML15275A130 | 7 October 2015 | Michael Wentzel License Renewal Projects Branch 2 | Summary of the Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Environmental Review | Other |
ML15275A094 | 7 October 2015 | Michael Wentzel License Renewal Projects Branch 2 | Summary of the Severe Accident Mitigation Alternatives Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Review | Other |
ML15287A165 | 23 October 2015 | Michael Wentzel Division of License Renewal | Requests for Additional Information Related to the Diablo Canyon LRA Environmental Review - SAMA | RAI |
DCL-15-136, Response to Requests for Information Related to the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives | 12 November 2015 | Pacific Gas & Electric Allen B | Response to Requests for Information Related to the Environmental Review of the License Renewal Application - Severe Accident Mitigation Alternatives | Response to RAI |
ML15310A069 | 24 November 2015 | Michael Wentzel License Renewal Projects Branch 2 | Summary of Telephone Conference Call Held Between NRC and Pg&Amp;E Concerning the RAIs Pertaining to the DCPP LRA Environmental Review | RAI |
ML16271A439 | 7 October 2016 | Kevin Folk NRC/NRR/DLR/RERP | Project Manager Change for the License Renewal of Diablo Canyon Power Plant, Units 1 and 2 | Other |