ML13086A095 | 28 February 2013 | Duke Energy Waldrep B | Overall Integrated Plans in Response to 03/12/2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) | Other |
ML13171A301 | 21 June 2013 | Boska J Plant Licensing Branch II | Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | RAI |
ML13207A413 | 19 July 2013 | Duke Energy Batson S | Response to Requests for Additional Information Concerning Overall Integrated Plan with Regard to Requirements for Spent Fuel Pool Instrumentation | Response to RAI |
ML13246A009 | 29 August 2013 | Duke Energy Batson S | First Six-Month Status Report in Response to Letter Dated March 12, 2012 | Other |
ML13298A696 | 1 November 2013 | Richard Guzman Plant Licensing Branch II | Interim Staff Evaluation and Request for Additional Information - Oconee Nuclear Station, Units 1, 2, and 3 Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | RAI |
ML14028A512 | 4 February 2014 | NRC/NRR/DPR/MSD Mega-Tech Services | Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Oconee Nuclear Station, Units 1, 2, and 3, TAC Nos.: MF0782, MF0783, and MF0784 | Other |
ML13365A258 | 10 February 2014 | Jeremy Bowen NRC/NRR/DPR/MSD/MSPB | Interim Staff Evaluation Regarding Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) | Acceptance Review |
ONS-2014-028, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 February 2014 | Duke Energy Batson S | Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
ONS-2014-117, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) | 27 August 2014 | Duke Energy Batson S | Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) | Other |
ONS-2015-022, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 27 February 2015 | Duke Energy Batson S | Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
ONS-2015-023, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | 27 February 2015 | Duke Energy Batson S | Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | Other |
ML15160A664 | 10 June 2015 | Boska J Japan Lessons-Learned Division | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | Other |
ML15259A387 | 6 October 2015 | Boska J Japan Lessons-Learned Division | Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | Acceptance Review |