ML081000176 | 28 February 2008 | Entergy Bronson K | Request for Exemption from the Schedule Requirements of 10 CFR 50.75(f)(3) | Request |
ML081360402 | 30 May 2008 | James Kim NRC/NRR/ADRO/DORL/LPLI-1 | Environment Assessment Regarding the Exemption from the Schedule Requirements of 10 CFR 50.75(f)(3) | Approval |
ML081360326 | 9 June 2008 | James Kim NRC/NRR/ADRO/DORL/LPLI-1 | Exemption from the Schedule Requirements of 10 CFR 50.75(f)(3) | Approval |
ML082170672 | 16 July 2008 | TLG Services | Report, E11-5690-003, Preliminary Decommissioning Cost Analysis for the Pilgrim Nuclear Power Station. | Other |
ML082170377 | 31 July 2008 | Entergy Bronson K | Transmittal of Report Titled, Preliminary Decommissioning Cost Analysis. | Request |