JAFP-17-0077, Mitigating Strategies Assessment (MSA) for the Reevaluated Flooding Hazards Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima.. | 27 July 2017 | Exelon Joseph Pacher | Mitigating Strategies Assessment (MSA) for the Reevaluated Flooding Hazards Pursuant to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1: Flooding of the Near-Term Task Force Review of Insights from the Fukushima.. | Request |
ML17355A110 | 12 December 2017 | Submittal of Revised Mitigating Strategies Assessment Report for Flooding | Request | |
ML17321B040 | 18 December 2017 | Joseph Sebrosky Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment(Cac Nos. MF7919 and MF7920; EPID L-2016-JLD-0007) | Other |
ML18019A269 | 12 February 2018 | Joseph Sebrosky Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment | Other |
ML17234A432 | 12 February 2018 | Joseph Sebrosky Japan Lessons-Learned Division | Flood Hazard Mitigation Strategies Assessment | Other |
ML18071A169 | 22 March 2018 | Valentin M Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment | Acceptance Review |
L-18-096, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI - Notification of Petition for Bankruptcy | 2 April 2018 | FirstEnergy Moul D | ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI - Notification of Petition for Bankruptcy | Request |
L-18-109, Certification of Permanent Cessation of Power Operations for Beaver Valley Power Station. Unit Nos. 1 and 2. Davis-Besse Nuclear Power Station. Unit No. 1. and Perry Nuclear Power Plant. Unit No. 1 | 25 April 2018 | FirstEnergy Nuclear Generation Moul D FirstEnergy Solutions Corp | Certification of Permanent Cessation of Power Operations for Beaver Valley Power Station. Unit Nos. 1 and 2. Davis-Besse Nuclear Power Station. Unit No. 1. and Perry Nuclear Power Plant. Unit No. 1 | Request |
ML18108A694 | 3 May 2018 | Juan Uribe Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment | Other |
ML17249A730 | 9 May 2018 | Boska J Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment | Other |
ML18045A052 | 27 June 2018 | Juan Uribe Beyond-Design-Basis Management Branch | Flood Hazard Mitigating Strategies Assessment (Public) | Other |
ML18275A296 | 26 September 2018 | Duke Energy Guill P | NRR E-mail Capture - (External_Sender) Brunswick Flooding MSA Review | Request |
ML18284A397 | 30 October 2018 | Frankie Vega Beyond-Design-Basis Management Branch | Flood Hazard Mitigation Strategies Assessment | Other |
L-18-252, Request for Deferral of Actions Related to Beyond-Design-Basis External Events Flooding Actions | 7 December 2018 | FirstEnergy Hamilton D | Request for Deferral of Actions Related to Beyond-Design-Basis External Events Flooding Actions | Request |
L-19-193, Resumption of Actions Related to Beyond-Design-Basis External Events Flooding Actions | 30 August 2019 | FirstEnergy Payne F | Resumption of Actions Related to Beyond-Design-Basis External Events Flooding Actions | Other |