Issue date | From | Title | Site | Project stage | |
---|---|---|---|---|---|
ML15282A235 | 21 September 2015 | Tennessee Valley Authority | RHR Heat Exchange K-values Utilities in EPU Containment Analyses | Browns Ferry | Request |
ML15282A181 | 21 September 2015 | Tennessee Valley Authority | Non-Proprietary - Safety Analysis Report for Browns Ferry, Units 1, 2 and 3, Extended Power Uprate, Attachment 7 | Browns Ferry | Request |
ML15282A152 | 21 September 2015 | Tennessee Valley Authority Shea J W | Submits Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate | Browns Ferry | Request |
CNL-15-249, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 1, Spent Fuel Pool Criticality Safety Analysis Information | 15 December 2015 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 1, Spent Fuel Pool Criticality Safety Analysis Information | Browns Ferry | Supplement |
CNL-15-250, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 2, MICROBURN-B2 Information, Including Enclosures 2, 4, 6, and 7 | 15 December 2015 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 2, MICROBURN-B2 Information, Including Enclosures 2, 4, 6, and 7 | Browns Ferry | Supplement |
CNL-15-261, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 3, Interconnection System Impact Study Information | 18 December 2015 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 3, Interconnection System Impact Study Information | Browns Ferry | Supplement |
ML16032A044 | 1 February 2016 | US Dept of Interior Fish & Wildlife Service | FWS to NRC, Updated List of Threatened and Endangered Species that May Occur in Your Proposed Project Location for Browns Ferry EPU | Browns Ferry | Request |
ML16041A307 | 18 February 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16041A022 | 25 February 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16040A232 | 25 February 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16049A463 | 29 February 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-045, Proposed Technical Specifications (Ts)Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 6, Response to Request for Additional Information | 9 March 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (Ts)Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 6, Response to Request for Additional Information | Browns Ferry | Supplement |
ML16062A072 | 15 March 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-048, Supplement 7, Responses to Requests for Additional Information, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) | 24 March 2016 | Tennessee Valley Authority James Shea | Supplement 7, Responses to Requests for Additional Information, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) | Browns Ferry | Supplement |
ML16084A320 | 25 March 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-055, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 8, Response to Request for Additional Information | 28 March 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 8, Response to Request for Additional Information | Browns Ferry | Supplement |
ML16089A137 | 29 March 2016 | Farideh Saba Plant Licensing Branch II | NRR E-mail Capture - Correction to Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16064A286 | 4 April 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16091A071 | 7 April 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16085A301 | 11 April 2016 | Farideh Saba Plant Licensing Branch II | Regulatory Audit Plans for April 19 - 21, 2016, Audit at Excel Facility in Rockville, Maryland, in Support of Extended Power Uprate License Amendment Request | Browns Ferry | Other |
ML16085A079 | 14 April 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16102A339 | 14 April 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-069, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 11, Responses to Requests for Additional Information | 14 April 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 11, Responses to Requests for Additional Information | Browns Ferry | Supplement |
ML16104A245 | 20 April 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-077, for Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Update (EPU) - Supplement 14, Response to Request for Additional Information | 27 April 2016 | Tennessee Valley Authority James Shea | for Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Update (EPU) - Supplement 14, Response to Request for Additional Information | Browns Ferry | Supplement |
ML16105A441 | 27 April 2016 | Farideh Saba Plant Licensing Branch II | Regulatory Audit Plan for May 10-11, 2016, Audit at Excel Facility in Rockville, Maryland, in Support of Extended Power Uprate License Amendment Request | Browns Ferry | Other |
CNL-16-079, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 15, Responses to Requests for Additional Information | 11 May 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 15, Responses to Requests for Additional Information | Browns Ferry | Supplement |
ML16124A932 | 12 May 2016 | Farideh Saba Plant Licensing Branch II | Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16125A423 | 19 May 2016 | Lingham S Plant Licensing Branch II | Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
CNL-16-008, Update on Progress of Facility Modifications for MSIV Leak Rate | 26 May 2016 | Tennessee Valley Authority James Shea | Update on Progress of Facility Modifications for MSIV Leak Rate | Browns Ferry | Other |
CNL-16-091, Brown Ferry, Units 1, 2 & 3, Responses to Requests for Additional Information and Updates Associated with Interconnection System Impact Study Modifications on Proposed Technical Specifications Change TS-505 - Request for License Amendment | 27 May 2016 | Tennessee Valley Authority James Shea | Brown Ferry, Units 1, 2 & 3, Responses to Requests for Additional Information and Updates Associated with Interconnection System Impact Study Modifications on Proposed Technical Specifications Change TS-505 - Request for License Amendments | Browns Ferry | Response to RAI |
CNL-16-094, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 20, Responses to Requests for Additional Information | 9 June 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 20, Responses to Requests for Additional Information | Browns Ferry | Supplement |
ML16146A635 | 13 June 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16161A064 | 15 June 2016 | Farideh Saba Plant Licensing Branch II | Notice of Forthcoming Closed Meeting with Tennessee Valley Authority and Its Consultant, GEH, Regarding Steam Dryers Structural Adequacy for Browns Ferry Units 1, 2 & 3 Extended Power Uprate (EPU) License Amendment Request (LAR) | Browns Ferry | Meeting |
CNL-16-093, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate - Supplement 19, Responses to Requests for Additional Information | 17 June 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate - Supplement 19, Responses to Requests for Additional Information | Browns Ferry | Supplement |
ML16154A544 | 21 June 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
ML16168A026 | 23 June 2016 | Farideh Saba Plant Licensing Branch II | Summary Report for the April 19 to 21, 2016 Audit in Support of Replacement Steam Dryer Review Associated to Extended Power Uprate License Amendment Request (CAC Nos. MF6741, MF6742, and MF6743) | Browns Ferry | Other |
CNL-16-105, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 22, Responses to Requests for Additional Information | 24 June 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 22, Responses to Requests for Additional Information | Browns Ferry | Supplement |
ML16125A406 | 6 July 2016 | Farideh Saba Plant Licensing Branch II | Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16127A609 | 6 July 2016 | Farideh Saba Plant Licensing Branch II | NRC Letter Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16125A084 | 7 July 2016 | Lingham S Plant Licensing Branch II | Approval for Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16130A600 | 7 July 2016 | Farideh Saba Plant Licensing Branch II | Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16173A026 | 7 July 2016 | Farideh Saba Plant Licensing Branch II | Approval for Request for Withholding Information from Public Disclosure | Browns Ferry | Withholding Request Acceptance |
ML16176A316 | 11 July 2016 | Farideh Saba Plant Licensing Branch II | Summary Report for the May 3 to May 5, 2016 Audit in Support Containment Accident Pressure Associated to Extended Power Uprate License Amendment Request | Browns Ferry | Other |
CNL-16-109, Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 23, Miscellaneous Updates | 13 July 2016 | Tennessee Valley Authority James Shea | Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 23, Miscellaneous Updates | Browns Ferry | Supplement |
CNL-16-119, Brown Ferry Nuclear Plant, Unit 1, 2 and 3 - Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate - Supplemental Information Related to Replacement Steam Dryers | 13 July 2016 | Tennessee Valley Authority James Shea | Brown Ferry Nuclear Plant, Unit 1, 2 and 3 - Proposed Technical Specifications Change TS-505 - Request for License Amendments - Extended Power Uprate - Supplemental Information Related to Replacement Steam Dryers | Browns Ferry | Supplement |
ML16193A460 | 21 July 2016 | Farideh Saba Plant Licensing Branch II | June 23, 2016, Summary of Closed Meeting with Tennessee Valley Authority Regarding the Structural Adequacy of Steam Dryers for Extended Power Uprate License Amendment Request for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (MF6741, MF6742 | Browns Ferry | Meeting |
ML16194A229 | 21 July 2016 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Related to License Amendment Request Regarding Extended Power Uprate | Browns Ferry | RAI |
CNL-16-116, Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 25 | 27 July 2016 | Tennessee Valley Authority James Shea | Response to Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 25 | Browns Ferry | Supplement |
CNL-16-118, Response to Request for Additional Information on Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 27 | 29 July 2016 | Tennessee Valley Authority James Shea | Response to Request for Additional Information on Proposed Technical Specifications (TS) Change TS-505 - Request for License Amendments - Extended Power Uprate (EPU) - Supplement 27 | Browns Ferry | Supplement |