ML15065A03127 February 2015Arizona Public Service
Mims D
License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-439-A, Revision 2, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCORequest
ML15218A30031 July 2015Arizona Public Service
Lacal M
License Amendment Request to Revise Technical Specifications to Adopt TSTF-505-A, Revision 1, Risk-Informed Completion TimesRequest
ML15303A0989 November 2015Watford M
Plant Licensing Branch IV
Acceptance Review Letter, License Amendment Request, Adopt Technical Specification Task Force (TSTF)-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4bAcceptance Review
ML16060A00226 February 2016Watford M
Plant Licensing Branch IV
NRR E-mail Capture - Palo Verde, Units 1, 2, and 3: Draft Request for Additional Information Amendment to Adopt TSTF-505 (CAC Nos. MF6576 MF6577 and MF6578)Draft RAI
ML16064A4977 March 2016Siva Lingam
Plant Licensing Branch IV
Request for Additional Information, Adopt Technical Specification Task Force (TSTF)-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4bRAI
NL-17-0447, Response to Request for Additional Information on Technical Specifications Change to Adopt Risk Informed Completion Times14 April 2017Southern Nuclear
Wheat J
Response to Request for Additional Information on Technical Specifications Change to Adopt Risk Informed Completion TimesResponse to RAI
ML17307A1883 November 2017Arizona Public Service
Lacal M
License Amendment Request Supplement for Risk-Informed Completion TimesSupplement
ML18074A02020 March 2018NRC/NRR/DRA
Casto G
Fpra FAQ 16-0011 Closure MemoRequest
ML18094B1124 April 2018Siva Lingam
Plant Licensing Branch IV
NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001)RAI
ML18124A0113 May 2018Siva Lingam
Plant Licensing Branch IV
NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001)RAI
ML18138A48018 May 2018Arizona Public Service
Lacal M
Response to Request for Additional Information for Risk-Informed Completion TimesResponse to RAI
ML18152B8741 June 2018Arizona Public Service
Lacal M
Response to Electrical Engineering Operating Reactor Branch (Eeob) Request for Additional Information for Risk-Informed Completion TimesRequest
ML18221A51023 August 2018Michael Orenak
Plant Licensing Branch IV
Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001)RAI
ML18264A31821 September 2018Arizona Public Service
Lacal M
Response to Request for Additional Information for Risk-Informed Completion TimesResponse to RAI
ML18278A2955 October 2018Arizona Public Service
Lacal M
Response to Request for Additional Information for Risk-Informed Completion Times Supplemental Responses for Items 17.f and 21Supplement
ML18275A27510 October 2018Michael Orenak
Plant Licensing Branch IV
Summary of September 14, 2018, Clarification Call with Arizona Public Service to Discuss the Incomplete Responses in the May 18, 2018, Letter the Adoption of Rict (CAC Nos. MF6576, MF6577, MF6578; EPID L-2015-LLA-0001)Other
ML19085A52529 May 2019Siva Lingam
Plant Licensing Branch IV
Issuance of Amendments Nos. 209, 209, and 209 - Regarding Adoption of Risk Informed Completion Times in Technical Specifications (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001)Approval