 Issue dateTitleFromTo
NRC Generic Letter 1995-0717 August 1995NRC Generic Letter 1995-007: Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate ValvesCrutchfield D
Office of Nuclear Reactor Regulation
ML20094L32014 November 1995Provides Results of Plant Evaluations Performed in Response to NRC 950817 GL 95-07, Pressure Locking & Thermal Binding of SR Power Operated Gate ValvesFirstEnergy
J. J. Barton
Office of Information Resources Management
Information Notice 1996-05, Partial Bypass of Shutdown Cooling Flow from Reactor Vessel18 January 1996Partial Bypass of Shutdown Cooling Flow from Reactor VesselCrutchfield D
Office of Nuclear Reactor Regulation
Information Notice 1996-08, Thermally Induced Pressure Locking of a High Pressure Coolant Injection Gate Valve5 February 1996Thermally Induced Pressure Locking of a High Pressure Coolant Injection Gate ValveCrutchfield D
Office of Nuclear Reactor Regulation
ML20100P4681 March 1996Provides Notification of Extension to Previous Commitment to Evaluate Potential Gate Valve Thermal Binding at Lower Temp Differentials,Per GL 95-07FirstEnergy
Roche M
Office of Information Resources Management
ML20117F10411 April 1996Response to NRC GL 95-07 Pressure Locking & Thermal Binding of Safety Related Power Operated Gate ValvesFirstEnergy
Tabone J
ML20117F0939 May 1996Forwards Oyster Creek Nuclear Generating Station Evaluation of GL 95-07, Pressure Locking & Thermal Binding of Safety- Related Power-Operated Gate ValvesFirstEnergy
Roche M
Office of Information Resources Management
Information Notice 1996-49, Thermally Induced Pressurization of Nuclear Power Facility Piping20 August 1996Thermally Induced Pressurization of Nuclear Power Facility PipingMartin T
Office of Nuclear Reactor Regulation
ML20117K6955 September 1996Responds to RAI Re GL 95-07, Pressure Locking & Thermal Binding SR Power-Operated Gate ValvesFirstEnergy
Roche M
Office of Information Resources Management
Information Notice 1997-07, Problems Identified During Generic Letter 89-10 Closeout Inspections6 March 1997Problems Identified During Generic Letter 89-10 Closeout InspectionsMartin T
Office of Nuclear Reactor Regulation
ML20207H37210 June 1999Informs That Attached Draft Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding, Was Transmitted by Facsimile to G Busch of Gpu Nuclear to Be Discussed in Conference Call Scheduled for 990614NRC (Affiliation Not Assigned)
Pastis H
NRC (Affiliation Not Assigned)
ML20212A79213 September 1999Forwards Second RAI Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, Issued on 950817 to PlantNRC (Affiliation Not Assigned)
Pastis H
FirstEnergy
Roche M
IR 05000219/200400531 January 2005IR 05000219-04-005 on 10/01/04 -12/31/04 for Oyster Creek Generating Station; Event Follow-up and Access Control to Radiologically Significant AreasNRC/RGN-I/DRP/PB7
Eselgroth P
AmerGen
Crane C
IR 05000219/20050026 May 2005IR 05000219-05-002; on 01/01/05 - 03/31/05; for Oyster Creek Generating Station; Maintenance Risk Assessment and Emergent Work Evaluation, Operability Evaluations, Radioactive Gaseous and Liquid Effluent Treatment and Monitoring SystemsArthur Burritt
NRC/RGN-I/DRP/PB7
AmerGen
Crane C
ML20311A4846 November 20172017 Q1-Q4 ROP Inspection FindingsOffice of Nuclear Reactor Regulation