Semantic search
Jump to navigation
Jump to search
Issue date | Title | From | To | |
---|---|---|---|---|
NRC Generic Letter 1988-03 | 17 February 1988 | NRC Generic Letter 1988-003: Resolution of Generic Safety Issue 93, Steam Binding of Auxiliary Feedwater Pumps. | Miraglia F Office of Nuclear Reactor Regulation | |
NRC Generic Letter 1988-07 | 7 April 1988 | NRC Generic Letter 1988-007: Modified Enforcement Policy Relating to 10 CFR 50.49 Environmental Qualification of Electrical Equipment Important to Safety for Nuclear Power Plants. | Miraglia F Office of Nuclear Reactor Regulation | |
ML20154K367 | 24 May 1988 | Confirms That Procedures Exist to Allow Operators to Both Recognize & Recover from Steam Binding in Auxiliary Feedwater (AFW) Sys,Per Generic Ltr 88-03, Steam Binding of AFW Pumps, Resolving Generic Issue 93 | Southern Nuclear Mcdonald R | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
ML20154F082 | 9 September 1988 | Clarifies 880524 Response to Generic Ltr 88-03 Re Steam Binding of Auxiliary Feedwater Pumps to Resolve Safety Issue 93.Check Valves Modified to Preclude Backleakage Associated W/Binding | Southern Nuclear Hairston W | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
ML20205M645 | 28 October 1988 | Notifies That 880524 & 0909 Submittals Provided Acceptable Response to Generic Ltr 88-03.Annunciators on Main Control Board Panel Would Provide Alert to Operators at Preset High Temp Alarm Level | Office of Nuclear Reactor Regulation Reeves E | Southern Nuclear Hairston W |
ML20247E933 | 18 May 1989 | Forwards Response to NRC Re Questionnaire on Backfitting Process & Estimated Implementation Costs for Certain Generic Issues | Southern Nuclear Hairston W | Office of Information Resources Management |
NRC Generic Letter 1990-04 | 25 April 1990 | NRC Generic Letter 1990-004: Request for Information on Status of Licensee Implementation of Generic Safety Issues Resolved with Imposition of Requirements or Corrective Actions | Partlow J Office of Nuclear Reactor Regulation | |
ML20058F892 | 31 October 1990 | Auxiliary Feedwater System RISK-BASED Inspection Guide for the J.M. Farley Nuclear Power Plant | Battelle Memorial Institute Vo T Harrison D Gore B Pugh R PACIFIC NORTHWEST NATION | Office of Nuclear Reactor Regulation |
IR 05000348/1997201 | 13 May 1997 | Insp Repts 50-348/97-201 & 50-364/97-201 on 970127-0314.No Violations Noted.Major Areas Inspected:Engineering, Auxiliary Feedwater Sys,Component Cooling Water Sys & Sys Interface Design Review | NRC (Affiliation Not Assigned) |