Issue date | Title | From | To | |
---|---|---|---|---|
NRC Generic Letter 1988-07 | 7 April 1988 | NRC Generic Letter 1988-007: Modified Enforcement Policy Relating to 10 CFR 50.49 Environmental Qualification of Electrical Equipment Important to Safety for Nuclear Power Plants. | Miraglia F Office of Nuclear Reactor Regulation | |
IR 05000155/1988008 | 17 May 1988 | Insp Rept 50-155/88-08 on 880413-14 & 0503-05.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Activities Including Review of Programs | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) Ward K Danielson D | |
ML20207B320 | 25 July 1988 | Responds to Generic Ltr 88-01 Re NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping.Util Intention Is to Continue W/Implementation of IGSCC Insp Program as Previously Submitted.No IGSCC Detected | Consumers Energy Berry K | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
ML20245B995 | 18 April 1989 | Forwards Request for Addl Info Re 880725 Response to Generic Ltr 88-01.Response Requested within 60 Days of Ltr Date | Office of Nuclear Reactor Regulation Pulsifer R | Consumers Energy Berry K |
ML20245E967 | 23 June 1989 | Responds to 890418 Request for Addl Info Re Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping | Consumers Energy Berry K | Office of Information Resources Management |
IR 05000155/1989012 | 12 July 1989 | Insp Rept 50-155/89-12 on 890612-14,20-22,26-28 & 0705-06. No Violations or Deviations Noted.Major Areas Inspected: Programs,Procedures,Observation of Work Activities & Data Review | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) Ward K Danielson D | |
NRC Generic Letter 1989-21 | 19 October 1989 | NRC Generic Letter 1989-021: Request for Information Concerning Status of Implementation of Unresolved Safety Issue (USI) Requirements | Partlow J Office of Nuclear Reactor Regulation | |
NRC Generic Letter 1990-04 | 25 April 1990 | NRC Generic Letter 1990-004: Request for Information on Status of Licensee Implementation of Generic Safety Issues Resolved with Imposition of Requirements or Corrective Actions | Partlow J Office of Nuclear Reactor Regulation | |
NRC Generic Letter 1990-05 | 15 June 1990 | NRC Generic Letter 1990-005: Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping | Partlow J Office of Nuclear Reactor Regulation | |
ML20059B632 | 22 August 1990 | Forwards Revised Engineering Analysis of Generic Ltr 88-01 on Plant Temp Pressure Limits in Support of Licensee 900110 Tech Spec Change Request,Per NRC Request | Consumers Energy Eddy J | Office of Information Resources Management |
ML20128C434 | 29 January 1993 | Forwards Rev 3 to Updated Final Hazards Summary Rept | Hoffman D Consumers Energy | |
ML20217G494 | 23 April 1998 | Informs That Previous Commitments Will Not Be Retained Due to Permanent Cessation of Big Rock Point Plant Operation. Commitments Associated W/Nrc Insp Repts,Encl | Consumers Energy Powers K | Office of Information Resources Management |
ML20236T665 | 21 July 1998 | Provides Remaining Responses to NRC 980416 RAI Re Big Rock Plant'S Proposed Defueled Tech Specs.Proposed Defueled Tech Specs & Bases,Encl | Consumers Energy Powers K | Office of Information Resources Management |
ML20198K661 | 24 December 1998 | Safety Evaluation Supporting Amend 120 to License DPR-6 | NRC (Affiliation Not Assigned) |