ML21123A240 | 22 February 2022 | PRM-50-112 - Congressional Letters, Denial of Petition for Rulemaking Determining Which Structures, Systems, and Components and Functions Are Important to Safety | ||
ML18180A418 | 2 July 2018 | Harris Brunswick | Audit Plan for Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components Forr Nuclear Power Reactors (EPID L-2018-LLA-0008; L-2018-LLA-0034) | |
ML16335A344 | 12 December 2016 | Harris | Request for Withholding Information from Public Disclosure | |
ML16300A180 | 27 October 2016 | Harris | Verbal Authorization of Relief Request I3R-16, for Reactor Vessel Closure Head Penetration Nozzle Repair Technique, Inservice Inspection Program -Third 10-Year Interval | |
ML16235A238 | 17 October 2016 | Harris Robinson | Summary of the July 12-13, 2016 Audit Supporting the U.S. Nuclear Regulatory Commission Review of DPC-NE-1008-P, Nuclear Design Methodology Using CASMO-5/SIMULATE-3 for Westinghouse Reactors | |
ML16267A029 | 29 September 2016 | Harris | SFP Pre-Submittal Meeting Slides - BWR Storage Rack Inserts, Updated NCS Analysis at Harris Nuclear Plant | |
ML16040A231 | 29 February 2016 | Harris Robinson | Request for Withholding Information from Public Disclosure for Shearon Harris Nuclear Power Plant, Unit 1, and H.B. Robinson Steam Electric Plant, Unit 2 | |
ML16028A197 | 8 February 2016 | Harris | Request for Additional Information Regarding License Amendment Request for a Temporary Change to Technical Specifications for the 'A' Emergency Service Water Pump Replacement | |
ML15342A205 | 8 January 2016 | Robinson | Regulatory Audit in Support of License Amendment Request to Adopt NFPA 805 | |
ML15342A043 | 6 January 2016 | Harris | Supplemental Safety Evaluation to Relief Request I3R-15 for Reactor Vessel Closure Head Penetration Nozzle Repair Technique, Inservice Inspection Program - Third 10-Year Interval | |
ML15343A071 | 23 December 2015 | Robinson | September 22-26, 2014, Summary of H. B. Robinson Steam Electric Plant, Unit 2 - Audit Associated with License Amendment Request to Transition to the National Fire Protection Association 805 Standard | |
ML15343A065 | 23 December 2015 | Robinson | Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Technical Specification Change to Reactor Coolant System Pressure and Temperature Limits | |
ML15344A030 | 17 December 2015 | Harris Robinson | Request for Additional Information Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5, Thermal Hydraulic Statistical Core Design Methodology (MF5872/MF5873) | |
ML15309A728 | 1 December 2015 | Harris Robinson | Acceptance of Requested Licensing Action Regarding Duke Energy Progress, Inc. Application to Revise Technical Specifications to Adopt Methodology Report | |
ML15202A475 | 24 September 2015 | Harris | Summary of Meeting with Duke Energy Progress, Inc. to Discuss Shearon Harris Nuclear Power Plant, Unit 1, Proposed License Amendment Request Regarding Technical Specifications for the Pressurizer and Main Steam Line Safety Valves (MF6233) | |
ML15222B175 | 8 September 2015 | Robinson | Issuance of Amendment to Modify Technical Specification 3.8.1, Diesel Generator Testing Requirements | |
ML15215A651 | 10 August 2015 | Harris Robinson | Duke Energy Progress, Inc., for H. B. Robinson, Unit 2 and Shearon Harris, Unit 1, Request for Additional Information Regarding Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5 (TAC Nos. MF5872 | |
ML15159A602 | 6 July 2015 | Brunswick | Order Approving Direct Transfer of Licenses and Approving Conforming Amendments | |
ML15159A677 | 6 July 2015 | Brunswick | FRN, Direct Transfer of Licenses; Order; Issuance | |
ML15159A632 | 6 July 2015 | Harris Brunswick | Letter Approving Direct Transfer of Control of Licenses and Conforming Amendments | |
ML15107A425 | 17 April 2015 | Harris | 4/20/2015, Forthcoming Closed Meeting with Duke Energy Progress, Inc. to Discuss Shearon Harris Nuclear Power Plant, Unit 1, Relief Request I3R-15 Revision and Supplement, Reactor Vessel Closure Head Nozzle Repair Technique, Inservice Inspe | |
ML14125A471 | 9 May 2014 | Surry | Relief from the Requirements of the ASME Code | |
ML14115A199 | 30 April 2014 | Surry | Relief from the Requirements of the ASME OM Code | |
ML14113A346 | 25 April 2014 | Surry | Relief from the Requirements of the ASME Code | |
ML14073A405 | 24 April 2014 | Surry | Issuance of Amendment for the Technical Specifications Changes Related to Snubber Surveillance Requirements | |
ML14111A241 | 23 April 2014 | Surry | Relief from the Requirements of the ASME Code | |
IR 05000250/2013002 | 24 April 2013 | Turkey Point | IR 05000250-13-002, 05000251-13-002, on 01/01/2013 - 03/31/2013, Turkey Point Nuclear Power Plant, Units 3 and 4, Component Design Basis Inspection, Occupational ALARA Planning and Controls, and Problem Identification and Resolution | |
IR 05000250/2012005 | 30 January 2013 | Turkey Point | IR 05000250-12-005 & 05000251-12-005, 10/01/2012 - 12/31/2012, Turkey Point Nuclear Power Plant, Units 3 and 4, Licensed Operator Requalification Program | |
IR 05000250/2010010 | 6 January 2011 | Turkey Point | IR 05000250-10-010; Florida Power & Light Company; 11/29/210 - 12/03/2010; Turkey Point Nuclear Plant, Unit 3, Inspection Report | |
IR 05000250/2010002 | 28 April 2010 | Turkey Point | IR 05000250-10-002 and 05000251-10-002, on 01/01 - 03/31/2010, Turkey Point, Units 3 & 4, Integrated Inspection Report, Plant Modifications | |
IR 05000250/2008007 | 17 April 2008 | Turkey Point | IR 05000250-08-007, 05000251-08-007 on 03/17/08 - 03/21/08 for Turkey Point - NRC Follow-Up Problem Identification and Resolution Inspection Report | |
IR 05000250/2007009 | 24 January 2008 | Turkey Point | IR 05000250-07-009, 05000251-07-009; on 12/17/2007 - 12/21/2007; Turkey Point Nuclear Plant, Units 3 & 4; Follow-up Inspection of Substantive Cross-cutting Issue in the Area of Identification and Resolution of Problems |