Acceptance of Requested Licensing Action Regarding Duke Energy Progress, Inc. Application to Revise Technical Specifications to Adopt Methodology Report
ML15309A728
Person / Time
Site: Harris, Robinson  Duke Energy icon.png
Issue date: 12/01/2015
From: Martha Barillas
Plant Licensing Branch II
To: Repko R
Duke Energy Progress
Barillas M
References
CAC MF6648, CAC MF6649
Download: ML15309A728 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 1, 2015 Mr. Regis T. Repko Senior Vice President Governance, Projects and Engineering Mail Code EC07H P.O. Box 1006 Charlotte, NC 28201-1006

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, AND H. B.

ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: DUKE ENERGY PROGRESS, INC.'S APPLICATION TO REVISE TECHNICAL SPECIFICATIONS TO ADOPT METHODOLOGY REPORT DPC-NE-1008-P, REVISION 0 (CAC NOS. MF6648 AND MF6649)

Dear Mr. Repko:

By letter dated August 19, 2015 (Agencywide Documents Access and Management System Accession No. ML15236A044), Duke Energy Progress, Inc. (Duke Energy) requested amendments to the technical specifications of Renewed Facility Operating License No. NPF-63 for the Shearon Harris Nuclear Power Plant, Unit 1 (Harris), and Renewed Facility Operating License No. DPR-23 for the H. B. Robinson Steam Electric Plant, Unit No. 2 (Robinson), for the review, approval, and adoption of DPC-NE-1008-P, Revision 0, "Nuclear Design Methodology Using CASM0-5/SIMULATE-3 for Westinghouse Reactors," to allow Duke Energy to perform reactor physics calculations as part of the reload design safety analysis for Shearon Harris and Robinson. Approval of the new methodology at Harris and Robinson will allow Duke Energy to perform the subject analysis at each plant, as opposed to utilizing contract services. This license amendment request (LAR) is requesting plant-specific approval of the CASM0-5/SIMULATE-3 methodology for application to Shearon Harris and Robinson only.

The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plants.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original

applications. Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review for plant specific applicability at Shearon Harris and Robinson, and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment.

In its letter, Duke Energy requested approval of this LAR by December 31, 2016, to support the Shearon Harris Cycle 22 core design, expected to commence operation in spring 2018. The previously approved Duke Energy methodology CASM0-4 and other methodology submittals required over a 12 month review schedule due to the complexity of the technical review.

Precedence has shown that new methodologies take between 18 to 24 months to complete the review and Duke's requested due date may not be met.

Given the lesser the scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me at (301) 415-2760 or Martha.Barillas@nrc.gov.

Docket Nos. 50-261 and 50-400 cc: Mr. Benjamin C. Waldrep Site Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd.

M/C HNP01 New Hill, NC 27562-0165 Mr. Richard Michael Glover Site Vice President H. B. Robinson Steam Electric Plant Duke Energy 3581 West Entrance Road, RNPA01 Hartsville, SC 29550 Distribution via Listserv Sincerely,

~~

Martha Barillas, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

ML15309A728 OFFICE NRR/DORL/LPLI 1-2/PM NRR/DORL/LPLI 1-2/LA NAME MBarillas (LRonewicz for) BClavton DATE 11/10/2015 11/10/2015 OFFICE NRR/DORL/LPLll-2/BC NRR/DORL/LPLll-2/PM NAME (RSchaaf for) BBeasley MBarillas DATE 12/01/2015 12/01/2015