Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML23089A36430 March 2023Decommissioning Funding Status Report
ML23089A37230 March 2023Decommissioning Funding Status Report
ML23089A38530 March 2023Decommissioning Funding Status Report
ML21145A21713 May 2021Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion SlidesCoatings
Aging Management
License Renewal
ML21091A09826 March 2021Decommissioning Funding Status Report
ML21085A56625 March 2021Decommissioning Funding Status Report
ML21085A55325 March 2021Decommissioning Funding Status Report
ML19092A29326 March 2019Decommissioning Funding Status Report
ML19092A29426 March 2019Decommissioning Funding Status Report
ML18092A08021 March 2018Decommissioning Funding Status Report
ML17094A52030 March 2017Submittal of Decommissioning Funding Status Report
ML17094A52230 March 2017Submittal of Decommissioning Funding Status Report
ML17094A51830 March 2017Submittal of Decommissioning Funding Status Report
ML15244B18224 August 2015Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Spent Fuel Pool Instrumentation
ML15244B20224 August 2015Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)FLEX
Spent Fuel Pool Instrumentation
ML15093A10426 March 2015Decommissioning Funding Status Report
ML15093A10326 March 2015Decommissioning Funding Status Report
ML15093A10226 March 2015Decommissioning Funding Status Report
ML15069A2332 March 2015Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Boric Acid
FLEX
Spent Fuel Pool Instrumentation
ML15069A2292 March 2015Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)FLEX
Spent Fuel Pool Instrumentation
ML15069A2312 March 2015Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Safe Shutdown
Boric Acid
Ultimate heat sink
FLEX
Spent Fuel Pool Instrumentation
Earthquake
ML14245A40226 August 2014Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)FLEX
Spent Fuel Pool Instrumentation
ML14245A40026 August 2014Six-month Status Report in Response to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-015)FLEX
Spent Fuel Pool Instrumentation
ML14245A40126 August 2014Six-month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12051)Spent Fuel Pool Instrumentation
ML14098A26031 March 2014Decommissioning Funding Status Report
ML14069A01428 February 2014Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Boric Acid
High winds
Ultimate heat sink
Tornado Missile
Safe Shutdown Earthquake
Internal Flooding
FLEX
ML14069A01328 February 2014Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Safe Shutdown
Boric Acid
High winds
Ultimate heat sink
Internal Flooding
FLEX
Tornado Missile Protection
Earthquake
ML14069A01128 February 2014Six-Month Status Report in Response to March 12. 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Spent Fuel Pool Instrumentation
ML14069A01227 February 2014Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Boric Acid
High winds
Shutdown Margin
Ultimate heat sink
Safe Shutdown Earthquake
FLEX
Design basis earthquake
B.5.b Mitigating Strategies
Earthquake
ML14069A01527 February 2014Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Boric Acid
High winds
Ultimate heat sink
Tornado Missile
Safe Shutdown Earthquake
Internal Flooding
Hydrostatic
FLEX
Tornado Generated Missile
Design basis earthquake
B.5.b Mitigating Strategies
Earthquake
ML14069A01027 February 2014Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Spent Fuel Pool Instrumentation
ML13242A01123 August 2013Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)Boric Acid
Tornado Missile
Safe Shutdown Earthquake
Hydrostatic
FLEX
ML13242A01423 August 2013Connecticut, Inc. & Millstone Power Station Units 2 and 3 Six-Month Status Report in Response to Letter Dated March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel PoolSpent Fuel Pool Instrumentation
ML13242A01523 August 2013Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)Spent Fuel Pool Instrumentation
ML13242A01223 August 2013Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)Boric Acid
Safe Shutdown Earthquake
FLEX
ML13242A01323 August 2013Six Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)Boric Acid
Safe Shutdown Earthquake
FLEX
ML13242A01623 August 2013Virginia Electric & Power Company Surry Power Station Units 1 & 2 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent FuelSpent Fuel Pool Instrumentation
ML13098A08728 March 2013Decommissioning Funding Status Report
ML12307A03725 October 2012Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Spent Fuel Pool Instrumentation
ML13031A63512 August 2012Status Report on Unidentified Leakage for Vermont Yankee, Pilgrim, and Millstone, Units 2 and 3
ML12122A07114 May 2012Enclosure 1: April 2012 Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206Fukushima Dai-Ichi
Design basis earthquake
Earthquake
Fire Protection Program
ML12082A17822 March 2012Decommissioning Funding Status Report
ML12024A37628 December 2011State-of-the-Art Reactor Consequence Analyses, Current Status and Next Steps
ML11272A12927 September 2011Post-Earthquake Restart Readiness Determination Plan Status UpdateSafe Shutdown
Safe Shutdown Earthquake
Operating Basis Earthquake
Nondestructive Examination
Design basis earthquake
Earthquake
ML11090037529 March 2011Decommissioning Funding Status Report
ML10091012730 March 2010Decommissioning Funding Status Report
ML08091009428 March 2008Decommissioning Funding Status Report
ML06087052928 March 2006Decommissioning Funding Status Report
ML05089041829 March 2005Decommissioning Funding Status Report Notification of Intent to Remove Parent Guarantee
ML0506300702 March 2005January Monthly Report on the Status of Open TIAs Assigned to NRR