Issue date | Title | Topic | |
---|---|---|---|
ML17284A675 | 30 June 1998 | Ro:On 980617,flooding of RB Northeast Stairwell with Consequential Flooding of Two ECCS Pump Rooms.Caused by Inadequate Fire Protection Sys Design.Pumped Out Water from Affected Areas to Point Below Berm Areas of Pump Rooms | |
ML17292B228 | 14 January 1998 | Informs of Unexpected Change in Feedwater Temperature & Flow Indication Used to Calculate Plant Heat Balance During Routine Trending of Plant Computer Feedwater Temperatures on 980112.Corrective Actions Reduced Reactor Power to 99% | |
ML17292A792 | 9 April 1997 | Ro:On 970327,reactor Scrammed.Evaluation Results,Conclusions & Corrective Actions Will Be Shared W/Nrc Prior to Plant Startup from Maint & Refueling Outage | |
ML17292A590 | 8 November 1996 | Special Rept:On 961023,intermediate & High Range Stack Monitors PRM-RE-1B & PRM-RE-1C Declared Inoperable.Caused by Monitor Output Had Upward Trend Due to Electronic Noise Interference.Work Request Generated | Offsite Dose Calculation Manual |
ML17291B098 | 8 November 1995 | Special Rept:On 951026,RB Effluent Monitoring Sys Inoperable for 72 H Due to Failure of Mid Range Stack Monitor.Cryostat Cooling Assemblies for Mid & High Range Stack Monitors Returned to Vendor for Refurbishment | |
ML17291A978 | 18 August 1995 | Special Rept:On 950712,loose Part Detection Sys Channel 4 Failed Due to Electrical Noise During Daily Check.Channel 4 Will Remain Inoperable Until Next Forced or Scheduled Outage When Primary Containment de-inerted for Other Work | |
ML17291A696 | 16 March 1995 | Special Rept:On 950305,reactor Bldg Effluent Monitoring Sys Was Inoperable for 72 Hrs.Caused by Failure of Stack Monitor Detector.Stack Monitor Returned to Svc on 950314 | |
ML17291A413 | 26 September 1994 | Special Rept:On 940825,loose Part Detection Sys Channel Number Eight Actuated Associated MCR Alarm & on 940908 Subj Channel Began Alarming Due to Electronic Noise Originating in Drywell.Electronic Module of Channel Removed | |
ML17290A887 | 17 December 1993 | Special Rept:On 931116,loose Parts Detection Sys Channel 5 Did Not Pass Daily Channel Surveillance.Exact Cause Not Determined.Need to Provide Addl Notifications Should Other Channels Become Inoperable Not Necessary | |
ML17290A838 | 10 December 1993 | Special Rept:On 931126,main Control Room Received Stack Monitor Sys Trouble Annunciator & Status Display Indicated High Range Channel Failed self-test.Caused by Component Failure of Stack Monitor Detector.Replacement in Progress | |
ML17290A530 | 11 June 1993 | Special Rept:On 930503,space Frame & Attached Seismic Triaxial Peak Accelorograph (SEIS-TPA-1) Removed to Allow for Refueling of Reactor Core.Instrument Returned to Svc on 930607 | Earthquake |
ML17289B128 | 11 January 1993 | Update to 921007 Special Rept Re Inoperability of Loose Parts Detection Instrumentation Following Failure of Channel 1 on 921113.On 921128,constant Alarm Received on Channel 8. Maint Work Request Initiated to Repair Failed Channels | |
ML17289A916 | 7 October 1992 | Special Rept:On 920905,channel 1 on Main Steam Line D Nozzle in Drywell Did Not Pass Surveillance & Inoperable for More than 30 Days.Caused by Faulty Equipment in Drywell. Maint Work Request Initiated to Repair Failed Channel | |
ML17289A600 | 22 May 1992 | Special Rept:On 920420,seismic Triaxial Peak Accelerograph & Space Frame Removed to Allow Refueling of Reactor Core. Accelerometer Will Be Returned to Svc When Space Frame Reattached to Reactor Vessel Prior to Startup | Earthquake |
ML17286A940 | 15 July 1991 | Special Rept:On 910604,time History Triaxial Acceleration Sensor Found Malfunctioning During Performance of Seismic Sys Maint Activities.Failed Unit Returned Under Warranty to Supplier for Repair.Sys Now Fully Operational | Earthquake |
ML17285A800 | 19 October 1989 | Special Rept:On 891009,valve PSR-V-104 Isolated to Repair Leaking PASS Sample Valve PSR-V-616,resulting in PASS Being Inoperable.Plan Made to Replace Valve PSR-V-616 to Restore Sys by Jan 1990 | |
ML17285A733 | 14 September 1989 | Special Rept:On 890821,leakage Discovered in post-accident Sampling Sys Containment Valves When in Closed Position. Maint Work Requests Prepared to Repair post-accident Sampling Sys Containment Isolation Valves | |
ML17285A351 | 22 March 1989 | Special Rept:On 890306,post-accident Sampling Primary Coolant Radiation Monitor Inoperable.Caused by Excess Moisture.Pass Vacuum Pump PSR-P-702 Replaced W/New Pump & Bulkhead Fitting Repaired | |
ML17285A293 | 16 February 1989 | Special Rept:On 890203,plant Personnel Unable to Obtain Sample from PASS Due to Lack of Compression in Vacuum Pump. Caused by Broken Pump Shaft.Replacement Parts Currently on Order & Pump Will Be Repaired as Soon as Possible |