ML20296A276 | 6 October 2020 | Lake Engineering Co. - Third Interim Notification Per 10 CFR Part 21 - Degraded Snubber SF1154 Hydraulic Fluid Batch No. 17BLVS293 | |
ML19080A059 | 8 March 2019 | Interim Report of Potential 10CFR Part 21, Eaton A200 Series Starters/Contactors | |
ML19029A155 | 27 December 2018 | 10 CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10CFR21-0123, Rev. 1 | |
ML18353A428 | 30 November 2018 | Engine Systems, Inc., 10CFR21-0123, Rev. 0, for a 10CFR21 Reportable Condition on Emd Fuel and Soakback Pumps | |
ML17355A139 | 5 December 2017 | Potentially Degraded Snubber SF1154 Hydraulic Fluid Batch 14ELVS145 Final Report Per 10 CFR Part 21 | |
ML17081A453 | 20 March 2017 | Part 21 - Plastic Jar Dedication Sampling | |
ML16313A062 | 18 October 2016 | C&D Technologies, Inc. - 10 CFR Part 21 Evaluation Regarding Terminal Welding Failure in 3DCU-9 Batteries | |
ML16252A274 | 29 August 2016 | Azz/Nli - Part 21 Report - Potential Allen Bradley Timing Relay | |
ML15134A016 | 1 May 2015 | Part 21 Report Regarding Potentially Unqualified Component in Certain Allen Bradley Timing Relays | |
ML14204A707 | 23 July 2014 | Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV | |
ML14210A010 | 23 July 2014 | Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve | Safe Shutdown Shutdown Margin Scram Discharge Volume |
ML13165A342 | 12 June 2013 | 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers | |
ML13044A075 | 8 February 2013 | Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology | |
ML12347A308 | 12 December 2012 | Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology | |
ML12319A012 | 27 September 2012 | Error in Main Steam Line High Flow Calculational Methodology | |
ML12158A447 | 6 June 2012 | Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld | |
ML12094A371 | 2 April 2012 | Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations | |
ML112700067 | 26 September 2011 | GE-Hitachi Part 21 Reportable Condition Notification: Failure to Include Seismic Input in Channel-Control Blade Interference Customer Guidance | Safe Shutdown Earthquake Channel-control blade interference |
ML102520219 | 3 September 2010 | Part 21 - Failure to Include Seismic Input in Reactor Control Blade Customer Guidance | Safe Shutdown Earthquake Operating Basis Earthquake Channel-control blade interference |
ML101530564 | 28 May 2010 | Part 21 Notification from C & D Technologies, Inc., Post Corrosion on Dcu Batteries | |
ML050630244 | 2 March 2005 | Part 21 Report Concerning MCPR Limits and MCPR Monitoring |