 Issue dateTitleTopic
ML19214A11915 August 2019Regulatory Audit Summary for June 18 to June 19, 2019 Audit, Regarding License Amendment Request for Changes to the Intake Structure Physical Security ClassificationSafe Shutdown
Probabilistic Risk Assessment
Met Tower
Cyber Security
FLEX
ML18254A04022 January 2019Staff Review of Seismic Probabilistic Risk Assessment Associated with Reevaluated Seismic Hazard Implementation of the Near Term Task Force Recommendation 2.1: SeismicSafe Shutdown Earthquake
Internal Flooding
Probabilistic Risk Assessment
FLEX
Fukushima Dai-Ichi
Seismically rugged
Large early release frequency
Earthquake
Backfit
ML18211A3228 August 2018Staff Review of Spent Fuel Pool Evaluation Associated with Reevaluated Seismic Hazard Implementation Near-Term Task Force Recommendation 2.1: SeismicSafe Shutdown Earthquake
Probabilistic Risk Assessment
Fukushima Dai-Ichi
Earthquake
ML16176A0581 December 2016NRC Report for the Audit of Pacific Gas and Electric Company'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Diablo Canyon Power Plant, Unit Nos. 1 and 2 (CAC Nos. MF6039 andFukushima Dai-Ichi
ML16279A34327 October 2016Audit Report for 8/3-4/16, Nrr/Dra/Arcb Regulatory Audit at Westinghouse Facility in Rockville, MD, to Support Review of License Amendment Request for Adoption of Alternative Source TermMet Tower
ML16063A17014 March 2016Regulatory Audit Report for the January 12-14, 2016 Audit at the Westinghouse Facility in North Bethesda, Maryland, for the License Amendment Request for Alternate Source Term
ML16053A32323 February 2016Audit Report for 01/12-14/2016 Regulatory Audit at Westinghouse Facility to Support Review of License Amendment Request for Revision of the UFSAR for Beacon MethodologyShutdown Margin
ML15345A09311 January 2016Audit Report Regarding Pacific Gas and Electric Company'S Seismic Site Response Related to the Near-Term Task Force Recommendation 2.1 - Seismic for: Diablo Canyon Power Plant, Units 1 and 2Fukushima Dai-Ichi
Earthquake
ML15345A02111 January 2016Audit Report Regarding Pacific Gas and Electric Company'S Seismic Source Models Related to Near-Term Task Force Recommendation 2.1 - Seismic for Diablo Canyon Power Plant, Unit Nos. 1 and 2Fukushima Dai-Ichi
Earthquake
ML15289A37030 October 2015Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051Safe Shutdown
Shutdown Margin
Internal Flooding
FLEX
Spent Fuel Pool Instrumentation
ML15223A9682 September 2015Redacted, Regulatory Audit Report for June 22-26, 2015 Audit at the Westinghouse Facility in Warrendale, PA, to Support Digital Replacement of Process Protection System License Amendment Request (TAC ME7522-ME7523)
ML15135A00826 May 2015Audit of Licensee'S Management of Regulatory Commitments, Audit Performed April 22-May 13, 2015Probabilistic Risk Assessment
ML15103A01019 May 2015Redacted, Regulatory Audit Report for June 3-5, 2014 Audit at the Invensys Operations Management Facility in Lake Forest, CA, to Support Digital Replacement of Process Protection System License Amendment Request
ML13018A1494 March 2013Regulatory Audit Report for 11/13-16/2012 Audit at the Invensys Operations Management Facility in Lake Forest, CA, to Support Digital Replacement of Process Protection System License Amendment Request (TAC ME7522-ME7523)Cyber Security
ML11357011017 January 2012Audit of Licensee'S Management of Regulatory Commitments, Audit Performed October 18-21, 2011Boric Acid
ML10169032111 August 2010Audit Report for Plant Aging Management Programs for DCPP, Units 1 and 2Boric Acid
High Radiation Area
Fire Barrier
Hydrostatic
Coatings
Nondestructive Examination
VT-2
Aging Management
Fire Protection Program
Dissimilar Metal Weld
ML10189083216 July 2010Audit Report Regarding the Diablo Canyon Nuclear Power Plant License Renewal Application Scoping and Screening MethodologySafe Shutdown
Aging Management
ML08280034222 October 2008Audit of Pacific Gas and Electric Company'S Management of Regulatory Commitments (TACs MD9667 and MD9668)Weld Overlay
ML0517103585 July 2005Audit of Pacific Gas & Electric'S Management of Regulatory CommitmentsB.5.b