Issue date | Title | Topic | |
---|---|---|---|
ML23065A321 | 28 March 2023 | Regulatory Audit Plan and Setup of Online Reference Portal for License Amendment Request to Clarify Support System Requirements for the Residual Heat Removal & Control Room Air Conditioning Systems | Probabilistic Risk Assessment |
ML23068A377 | 20 March 2023 | Regulatory Audit Plan and Setup of Online Reference Portal for License Amendment Request and Exemption for Fuel Transition to Framatome Gaia Fuel (EPID L-2022-LLA-0150 and EPID L-2022-LLE-0030) - Nonproprietary | Shutdown Margin Anticipated operational occurrence Probabilistic Risk Assessment License Renewal Exemption Request Earthquake Fuel cladding |
ML22061A004 | 7 March 2022 | Audit Questions for License Amendment Request to Revise Technical Specifications to Adopt TSTF-505 and TSTF-439, Revision 2 | Internal Flooding Probabilistic Risk Assessment Open Phase Condition Large early release frequency Offsite Circuit |
ML22048A002 | 18 February 2022 | Regulatory Audit Plan and Setup of Online Reference Portal for License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2 and TSTF-439, Revision 2 | Internal Flooding Probabilistic Risk Assessment |
ML21197A063 | 23 July 2021 | Audit Plan and Setup of Online Reference Portal for License Amendment Request Risk-Informed Approach for Closure of Generic Safety Issue-191 | Boric Acid Probabilistic Risk Assessment Coatings Surveillance Frequency Control Program Exemption Request |
ML21110A123 | 27 April 2021 | Audit Questions for License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors | High winds Internal Flooding Probabilistic Risk Assessment FLEX Tornado Generated Missile |
ML21039A222 | 18 February 2021 | Audit Plan and Setup of Online Reference Portal for License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | High winds Internal Flooding Probabilistic Risk Assessment |
ML18156A404 | 19 June 2018 | Regulatory Audit Plan for September 18-19, 2018, in Support of License Amendment Request to Incorporate New Technical Specification 3.7.20 | Mission time Anticipated operational occurrence Battery sizing |
ML17177A446 | 6 July 2017 | Audit Plan for Licensee Responses Concerning Seismic Hazard Reevaluations Related to Request for Information -(50.54(F) Letter) Regarding Recommendation 2.1 of the Near-Term Task Force | Probabilistic Risk Assessment Fukushima Dai-Ichi Earthquake |
ML16259A189 | 5 December 2016 | Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | |
ML15309A326 | 9 November 2015 | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | FLEX Spent Fuel Pool Instrumentation |
ML14356A003 | 10 February 2015 | Audit of Licensee Responses to the Expedited Seismic Evaluation Process to Support Implementation of Near-Term Task Force Recommendation 2.1, Seismic | Safe Shutdown |
ML14083A620 | 26 March 2014 | Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 | Fukushima Dai-Ichi Spent Fuel Pool Instrumentation |