MONTHYEARVR-SECY-23-0095, Recommendation to Discontinue the Mississippi Agreement State Program'S Probationary Period (Wright)2023-11-27027 November 2023 VR-SECY-23-0095: Recommendation to Discontinue the Mississippi Agreement State Program'S Probationary Period (Wright) VR-SECY-23-0072, Final Agency Decision to Implement the Flexible Work Model (Wright)2023-10-30030 October 2023 VR-SECY-23-0072: Final Agency Decision to Implement the Flexible Work Model (Wright) SECY-23-0021, VR-SECY-23-0021: Proposed Rule: Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (Rin 3150-AK31) (Wright)2023-10-0202 October 2023 VR-SECY-23-0021: Proposed Rule: Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors (Rin 3150-AK31) (Wright) VR-SECY-22-0098, Rulemaking Options for Revising Security Requirements for Facilities Storing Spent Nuclear Fuel and High-Level Radioactive Waste (Wright)2023-09-21021 September 2023 VR-SECY-22-0098: Rulemaking Options for Revising Security Requirements for Facilities Storing Spent Nuclear Fuel and High-Level Radioactive Waste (Wright) VR-SECY-23-0075, Wyoming'S Proposal to Amend the Existing Agreement to Regulate the Processing of Source Material to Extract Mineral Resources Other than the Uranium or Thorium Content (Wright)2023-09-19019 September 2023 VR-SECY-23-0075: Wyoming'S Proposal to Amend the Existing Agreement to Regulate the Processing of Source Material to Extract Mineral Resources Other than the Uranium or Thorium Content (Wright) VR-SECY-23-0010, - Recommendation for Approval to Retire the Reactor Oversight Process Performance Indicator for Licensee Alert and Notification System Availability and to Develop a Performance Indicator for Emergency Response Facility and E2023-09-0101 September 2023 VR-SECY-23-0010 - Recommendation for Approval to Retire the Reactor Oversight Process Performance Indicator for Licensee Alert and Notification System Availability and to Develop a Performance Indicator for Emergency Response Facility and E ML23207A1802023-07-26026 July 2023 VR-COMJMB-23-0001: Establishing Commission Expectations for the Effectiveness, Efficiency, and Timeliness of New Reactor Reviews (Crowell) SECY-23-0055, VR-SECY-23-0055: Options for Licensing Emerging Technologies Used for Remediation of Mine Waste (Wright)2023-07-21021 July 2023 VR-SECY-23-0055: Options for Licensing Emerging Technologies Used for Remediation of Mine Waste (Wright) ML23158A2382023-06-0202 June 2023 VR-COMAXC-23-0001: Enabling the Mission - a Measured Approach to the Future of Work (Hanson) SRM-COMSECY-23-0008, VR-COMSECY-23-0008: Request to Solicit for the Appointment of Two New Members on the Advisory Committee on Reactor Safeguards (Crowell)2023-05-24024 May 2023 VR-COMSECY-23-0008: Request to Solicit for the Appointment of Two New Members on the Advisory Committee on Reactor Safeguards (Crowell) VR-COMSECY-23-0008, Request to Solicit for the Appointment of Two New Members on the Advisory Committee on Reactor Safeguards (Hanson)2023-05-24024 May 2023 VR-COMSECY-23-0008: Request to Solicit for the Appointment of Two New Members on the Advisory Committee on Reactor Safeguards (Hanson) ML23158A2412023-05-19019 May 2023 VR-COMAXC-23-0001: Enabling the Mission - a Measured Approach to the Future of Work (Crowell) ML23158A2402023-05-18018 May 2023 VR-COMAXC-23-0001: Enabling the Mission - a Measured Approach to the Future of Work (Baran) VR-SECY-23-0029, Rulemaking Plan for the Implementation of Changes to Reflect Advanced Reactor Export Licensing Considerations (Caputo)2023-04-28028 April 2023 VR-SECY-23-0029: Rulemaking Plan for the Implementation of Changes to Reflect Advanced Reactor Export Licensing Considerations (Caputo) ML23158A2392023-04-18018 April 2023 VR-COMAXC-23-0001: Enabling the Mission - a Measured Approach to the Future of Work (Wright) SECY-22-0109, VR-SECY-22-0109: Proposed Rule: Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Caputo)2023-01-0909 January 2023 VR-SECY-22-0109: Proposed Rule: Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Caputo) VR-SECY-22-0109, Proposed Rule: Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Baran)2022-12-20020 December 2022 VR-SECY-22-0109: Proposed Rule: Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Baran) VR-COMSECY-22-0012, Renewal of Licensing Support Network Advisory Review Panel Charter (Crowell)2022-10-12012 October 2022 VR-COMSECY-22-0012: Renewal of Licensing Support Network Advisory Review Panel Charter (Crowell) SECY-22-0033, CTH-SECY-22-0033: Proposed Rule - Alternatives to the Use of Credit Ratings (NRC-2017-0021; Rin 3150-AJ92) (Hanson)2022-07-29029 July 2022 CTH-SECY-22-0033: Proposed Rule - Alternatives to the Use of Credit Ratings (NRC-2017-0021; Rin 3150-AJ92) (Hanson) VR-SECY-22-0033, Proposed Rule - Alternatives to the Use of Credit Ratings (NRC-2017-0021; Rin 3150-AJ92) (Baran)2022-07-29029 July 2022 VR-SECY-22-0033: Proposed Rule - Alternatives to the Use of Credit Ratings (NRC-2017-0021; Rin 3150-AJ92) (Baran) SECY-22-0062, VR-SECY-22-0062: Final Rule: NuScale Small Modular Reactor Design Certification (Rin 3150-AJ98; NRC-2017-0029) (Hanson)2022-07-29029 July 2022 VR-SECY-22-0062: Final Rule: NuScale Small Modular Reactor Design Certification (Rin 3150-AJ98; NRC-2017-0029) (Hanson) VR-SECY-22-0062, Final Rule: NuScale Small Modular Reactor Design Certification (Rin 3150-AJ98; NRC-2017-0029) (Baran)2022-07-29029 July 2022 VR-SECY-22-0062: Final Rule: NuScale Small Modular Reactor Design Certification (Rin 3150-AJ98; NRC-2017-0029) (Baran) VR-SECY-22-0053, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections Periodicity (Baran)2022-07-18018 July 2022 VR-SECY-22-0053: Recommendations for Modifying the Reactor Oversight Process Engineering Inspections Periodicity (Baran) VR-SECY-20-0045, Population Related Siting Considerations for Advanced Reactors (Baran)2022-06-28028 June 2022 VR-SECY-20-0045: Population Related Siting Considerations for Advanced Reactors (Baran) VR-SECY-22-0046, Report to Congress on Abnormal Occurrences: Fiscal Year 2021 (Hanson)2022-06-27027 June 2022 VR-SECY-22-0046: Report to Congress on Abnormal Occurrences: Fiscal Year 2021 (Hanson) SECY-22-0036, VR-SECY-22-0036: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses--10-year Environmental Regulatory Update (NRC-2022-0087) (Hanson)2022-06-17017 June 2022 VR-SECY-22-0036: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses--10-year Environmental Regulatory Update (NRC-2022-0087) (Hanson) VR-SECY-22-0036, Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses--10-year Environmental Regulatory Update (NRC-2022-0087) (Baran)2022-06-17017 June 2022 VR-SECY-22-0036: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses--10-year Environmental Regulatory Update (NRC-2022-0087) (Baran) VR-SECY-22-0004, Proposed Rule: Items Containing Byproduct Material Incidental to Production (Rin 3150-AJ54; NRC-2015-0017)(Baran)2022-05-16016 May 2022 VR-SECY-22-0004: Proposed Rule: Items Containing Byproduct Material Incidental to Production (Rin 3150-AJ54; NRC-2015-0017)(Baran) COMSECY-22-0006, VR-COMSECY-22-0006: Request to Solicit for the Appointment of New Members on the Advisory Committee on Reactor Safeguards (Baran)2022-05-12012 May 2022 VR-COMSECY-22-0006: Request to Solicit for the Appointment of New Members on the Advisory Committee on Reactor Safeguards (Baran) VR-COMSECY-22-0006, Request to Solicit for the Appointment of New Members on the Advisory Committee on Reactor Safeguards (Wright)2022-05-12012 May 2022 VR-COMSECY-22-0006: Request to Solicit for the Appointment of New Members on the Advisory Committee on Reactor Safeguards (Wright) VR-SECY-22-0014, Report to Congress on Abnormal Occurrences: Fiscal Year 2021 (Hanson)2022-04-29029 April 2022 VR-SECY-22-0014: Report to Congress on Abnormal Occurrences: Fiscal Year 2021 (Hanson) SECY-22-0024, VR-SECY-22-0024: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Baran)2022-04-0505 April 2022 VR-SECY-22-0024: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Baran) VR-SECY-22-0024, Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Wright)2022-04-0505 April 2022 VR-SECY-22-0024: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Wright) VR-SECY-20-0098, Path Forward and Recommendations for Certain Low-Level Radioactive Waste Disposal Rulemaking (Baran)2022-04-0505 April 2022 VR-SECY-20-0098: Path Forward and Recommendations for Certain Low-Level Radioactive Waste Disposal Rulemaking (Baran) SECY-21-0066, VR-SECY-21-0066: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296)2022-02-24024 February 2022 VR-SECY-21-0066: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) VR-SECY-21-0066, Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Baran)2022-02-18018 February 2022 VR-SECY-21-0066: Rulemaking Plan for Renewing Nuclear Power Plant Operating Licenses - Environmental Review (Rin 3150-AK32; NRC-2018-0296) (Baran) SRM-COMSECY-22-0001, VR-COMSECY-22-0001: Renewal of Advisory Committee on the Medical Uses of Isotopes (ACMUI) Charter (Baran)2022-01-10010 January 2022 VR-COMSECY-22-0001: Renewal of Advisory Committee on the Medical Uses of Isotopes (ACMUI) Charter (Baran) VR-SECY-17-0083, Re-Evaluation of Category 3 Source Security and Accountability in Response to SRM-COMJMB-16-0001 (Wright)2021-12-0909 December 2021 VR-SECY-17-0083: Re-Evaluation of Category 3 Source Security and Accountability in Response to SRM-COMJMB-16-0001 (Wright) COMSECY-21-0014, VR-COMSECY-21-0014: Access Authorization Fees (Wright)2021-10-13013 October 2021 VR-COMSECY-21-0014: Access Authorization Fees (Wright) VR-COMSECY-21-0014, Access Authorization Fees (Baran)2021-10-0606 October 2021 VR-COMSECY-21-0014: Access Authorization Fees (Baran) VR-COMSECY-21-0010, Revision of the Reactor Oversight Process Public Radiation Safety Significance Determination Process (Baran)2021-08-12012 August 2021 VR-COMSECY-21-0010: Revision of the Reactor Oversight Process Public Radiation Safety Significance Determination Process (Baran) VR-SECY-19-0095, Discontinuation of Rulemaking - Enhanced Security of Special Nuclear Material (Hanson)2021-08-0404 August 2021 VR-SECY-19-0095: Discontinuation of Rulemaking - Enhanced Security of Special Nuclear Material (Hanson) VR-COMSECY-21-0009, Request to Solicit for the Appointment of a New Member on the Advisory Committee on Reactor Safeguards (Hanson)2021-07-22022 July 2021 VR-COMSECY-21-0009: Request to Solicit for the Appointment of a New Member on the Advisory Committee on Reactor Safeguards (Hanson) VR-SECY-21-0011, Denial of Petition for Rulemaking on Protection of Digital Computer and Communication Systems and Networks (PRM-73-18; NRC-2014-0165) (Baran)2021-06-28028 June 2021 VR-SECY-21-0011: Denial of Petition for Rulemaking on Protection of Digital Computer and Communication Systems and Networks (PRM-73-18; NRC-2014-0165) (Baran) VR-SECY-19-0100, Discontinuation of Rulemaking -Independent Spent Fuel Storage Installation Security Requirements (Baran)2021-06-14014 June 2021 VR-SECY-19-0100: Discontinuation of Rulemaking -Independent Spent Fuel Storage Installation Security Requirements (Baran) SECY-18-0005, VR-SECY-18-0005: Policy Statement on Enhancing Participation in U.S. Nuclear Regulatory Commission Public Meetings2021-02-19019 February 2021 VR-SECY-18-0005: Policy Statement on Enhancing Participation in U.S. Nuclear Regulatory Commission Public Meetings VR-SECY-21-0006, Request by Nextera Energy Duane Arnold, LLC for Exemptions from Certain Emergency Planning Requirements for the Duane Arnold Energy Center2021-02-11011 February 2021 VR-SECY-21-0006: Request by Nextera Energy Duane Arnold, LLC for Exemptions from Certain Emergency Planning Requirements for the Duane Arnold Energy Center SECY-20-0056, VR-SECY-20-0056: Advance Notice of Proposed Rulemaking-Alternatives to the Use of Credit Ratings (Rin 3150-AJ92)2020-11-23023 November 2020 VR-SECY-20-0056: Advance Notice of Proposed Rulemaking-Alternatives to the Use of Credit Ratings (Rin 3150-AJ92) SECY-20-0082, VR-SECY-20-0082: Rulemaking Plan to Extend the Duration of the AP1000 Design Certification2020-11-17017 November 2020 VR-SECY-20-0082: Rulemaking Plan to Extend the Duration of the AP1000 Design Certification SECY-20-0088, VR-SECY-20-0088: Proposed Evaluation Policy Statement2020-11-10010 November 2020 VR-SECY-20-0088: Proposed Evaluation Policy Statement 2023-09-21
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
POLICY ISSUE NOTATION VOTE RESPONSE SHEET TO: Annette L. Vietti-Cook, Secretary FROM: Commissioner Baran
SUBJECT:
SECY-19-0126: Closure of Petition for Rulemaking on Categorization of the Licensee Fee Category for Full-Cost Recovery (PRM-170-7; NRC-2018-0172)
Approved X Disapproved Abstain Not Participating COMMENTS: Below X Attached X None I approve the recommendation to close the petition for rulemaking. I also approve publication of the Federal Register notice announcing this decision and issuance of the accompanying letter, subject to the attached edits. As the notice explains, NRC addressed the unique fee issues for uranium water treatment licensees in the Fiscal Year 2019 fee rule.
Entered in "STARS" Yes X ATURE I//7 / l-"
No DATE
[7590-01-P]
NUCLEAR REGULATORY COMMISSION 10 CFR Part 170
[Docket No. PRM-170-7; NRC-2018-0172]
Categorization of the Licensee Fee Category for Full-Cost Recovery JMB edits AGENCY: Nuclear Regulatory Commission.
ACTION: Petition for rulemaking; closure of petition.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) has partially granted and partially denied a request to amend the NRCs regulations for licensing fees assessed to certain water treatment facilities. The request was submitted by Christopher S. Pugsley, Esq., on behalf of Water Remediation Technology, LLC, in a petition for rulemaking.
This action closes the petition docket.
DATES: The docket for the petition for rulemaking, PRM-170-7, closed on [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].
ADDRESSES: Please refer to Docket ID NRC-2018-0172 when contacting the NRC about the availability of information for this petition. You may obtain publicly-available information related to this action by any of the following methods:
- Federal Rulemaking Web Site: Public comments and supporting materials related to this petition can be found at https://www.regulations.gov by searching on the petition Docket ID NRC-2018-0172 or the fiscal year (FY) 2019 proposed and final fee
for 10 CFR part 171 annual fees under the NRCs regulations, and the nature of its licensed operations, it should be re-designated under the 10 CFR part 170 fee category and charged a fixed-fee amount.
The NRC reviewed PRM-170-7, WRTs public comment on the FY 2018 proposed fee rule, and related documentation and addressed the first two requests raised in the petition in its FY 2019 fee rule, issued on May 17, 2019 (84 FR 22331). At the time of filing of the petition, an entity that removed uranium from drinking water at community water systems (e.g., WRT) was viewed as a fee category 2.A.(5) licensee under §§ 170.31 and 171.16. Additionally, at that time, fee category 2.A.(5) required full-cost recovery of fees under 10 CFR part 170 for all licensing and inspection activities and assessed an annual fee. Although the petitioner recovers sufficient quantities of uranium to require an NRC license, its licensed material is not sold for profit; rather, the licensed material is a waste product from its water treatment process. These types of uranium recovery licensees are, therefore, distinguishable from those licensees that profit from concentrating uranium as source material.
Based on its review, the NRC concluded that full-cost recovery was not warranted for licensees that do not profit from concentrating uranium. Therefore, in its FY 2019 proposed fee rule, the NRC addressed the first two of the three petition requests by proposing to eliminate eliminating fee category 2.A.(5) under §§ 170.31 and 171.16, and re-categorize existing and future uranium water treatment licensees to fee category 2.F. Because of the elimination of fee category 2.A.(5) and respective re-categorization to fee category 2.F., uranium water treatment licensees such as WRT shifted from a 10 CFR part 170 full-cost fee category to a flat-fee category. Since the small entity regulations pertain to 10 CFR part 171 annual fees Moreover, licensees in the 2.F. fee category, including WRT, now applied to WRT, the annual fee for uranium water treatment, licensees may now qualify for the small entity reduced fee. The NRC 5
finds this action addresses the first two issues submitted in the petition.; Tthe NRC is denying the third change requested by the petitioner.
IV. Reasons for Denial The petitioners third request in the petition was related to the timeframe to appeal the assessment of fees under § 170.11(c). The petitioner stated that it disagrees with the timeframe to appeal the assessment of fees under § 170.11(c), as revised in the FY 2018 fee rule, and requested that the NRC extend the timeframe to apply for a fee exemption from 90 to 180 days. The petitioner asserted that the current regulation does not allow an applicant or licensee enough time to assess NRC's billings, its progress on an application or other work, and whether there are grounds for an exemption request.
The petitioner also stated that an applicant or licensee should not be restricted regarding when it can request an exemption.
The 90-day timing requirement only applies to those exemption requests for special projects submitted under § 170.11(a)(1), which states that no application fees, license fees, renewal fees, inspection fees, or special project fees shall be required for a special project that is a request/report submitted to the NRC. Therefore, the 90-day timeframe is limited to only those who are seeking fee exemptions after submitting a request or report to the NRC. This timing requirement does not apply to applicants or licensees that submit an application for the licensing activities addressed in the petition (i.e., license amendments, license renewal, and inspections). For these licensing activities, an applicant or licensee may request an exemption at any time. In addition, pursuant to § 15.31, Disputed debts, the NRC provides the regulatory framework, including the timing requirement, by which a debtor may dispute a debt. Under
§ 15.31(a), [a] debtor who disputes a debt shall explain why the debt is incorrect in fact 6
or in law within 30 days from the date that the initial demand letter was mailed or hand-delivered. The debtor may support the explanation by affidavits, cancelled checks, or other relevant evidence, and the petitioner did not indicate any concerns related to changing this requirement. For these reasons, the NRC is denying the third change requested by the petitionerIssue 3.
V. Conclusion For these reasons cited in this document, the NRC has granted the first two requested changes inIssues 1 and 2 of PRM-170-7 in the FY 2019 final fee rule, and is denying the third requested changeIssue 3. This action closes docket PRM-170-7.
Dated at Rockville, Maryland, this day of , 2019.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook, Secretary of the Commission.
7
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 JMB edits Christopher S. Pugsley Esq., on behalf of Water Remediation Technology, LLC Environmental and Regulatory Affairs 5525 West 56th Avenue, Suite 100 Arvada, CO 80002
Dear Mr. Pugsley:
I am responding to the petition for rulemaking (PRM) submitted on behalf of Water Remediation Technology, LLC, to the U.S. Nuclear Regulatory Commission (NRC) dated July 2, 2018 (Accession No. ML18214A757 in the NRCs Agencywide Documents Access and Management System). The petition requested that the NRC amend its regulations under Part 171 of Title 10 of the Code of Federal Regulations (10 CFR) to re-categorize licensees performing water treatment services from a full-cost recovery category to a category with fixed annual fees.
Secondly, the petition also asked NRC to address consistency issues between 10 CFR Parts 170 and 171 for small entities. Lastly, the petition also asked NRC to consider amending language under 10 CFR 170.11 to extend the timeframe from 90 to 180 days in which a licensee may appeal the assessment of fees and apply for a fee exemption.
The petition was docketed as PRM-170-7 on August 2, 2018, and the NRC published a notice of docketing in the Federal Register (FR) on November 2, 2018 (83 FR 55113). The NRC received one comment on the petition regarding the NRCs consideration of the petition in the fiscal year (FY) 2019 proposed fee rule (84 FR 578; January 31, 2019) in favor of the changes as proposed.
Based on its review, the NRC concluded that full-cost recovery was not warranted for licensees that do not profit from concentrating uranium. Therefore, in its FY 2019 proposed fee rule, the NRC addressed the first two of the three petition requests by proposing to eliminate fee category 2.A.(5) under §§ 170.31 and 171.16 and re-categorize existing and future uranium water treatment licensees to fee category 2.F. Because of the elimination of fee category 2.A.(5) and respective re-categorization to fee category 2.F., uranium water treatment licensees such as Water Remediation Technology shifted from a 10 CFR Part 170 full-cost fee category to a flat-fee category. Since the small entity regulations pertain to 10 CFR Part 171 annual fees now applied to Water Remediation Technology, the annual fee for uranium water treatmentMoreover, licensees in the 2.F. fee category, including WRT, may now qualify for the small entity reduced fee. The NRC finds this action addresses the first two issues submitted in the petition.
The third petition request was related to the timeframe to appeal the assessment of fees under 10 CFR 170.11(c). The 90-day timing requirement only applies to those exemption requests for special projects submitted under § 170.11(a)(1), which states that no application fees, license fees, renewal fees, inspection fees, or special project fees shall be required for a special project that is a request/report submitted to the NRC. Therefore, the 90-day timeframe is limited to only those who are seeking fee exemptions after submitting a request or report to the NRC. This
Pugsley timing requirement does not apply to applicants or licensees that submit an application for the licensing activities addressed in the petition (i.e., license amendments, license renewal, and inspections). For these licensing activities, an applicant or licensee may request an exemption at any time. In addition, pursuant to § 15.31, Disputed debts, the NRC provides the regulatory framework, including the timing requirement, by which a debtor may dispute a debt. Under
§ 15.31(a), [a] debtor who disputes a debt shall explain why the debt is incorrect in fact or in law within 30 days from the date that the initial demand letter was mailed or hand-delivered.
The debtor may support the explanation by affidavits, cancelled checks, or other relevant evidence, and the petition did not indicate any concerns related to changing this requirement.
For these reasons, the NRC is denying the third change request by the petitioner.
Upon publication of the enclosed notice, the NRC will close the docket for PRM-170-7. You may direct any questions regarding this matter to Gregory Trussell by calling 301-415-6244 or by e-mailing Gregory.Trussell@nrc.gov.
Sincerely, Annette L. Vietti-Cook, Secretary of the Commission