Text

Enclosure contains SECURITY RELATED INFORMATION- WITH OLD UNDER 10 CFR 2.390. Upon separation, this page may be de-controlled.

NE)<TeraM ENERGY~ *_;.>~

~~ SEABROOK April 26, 2018 Docket No. 50-443 SBK-L-18081 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Revision 2 to the Cyber Security Plan (CSP) for Seabrook Station In accordance with 10 CFR 50.4(b)(4), "Security plan and related submissions," and 10 CFR 50.54(p)(2), "Conditions oflicenses," NextEra Energy Seabrook, LLC submits Revision 2 to the Seabrook Station Cyber Security Plan (CSP).

The Cyber Security Plan has been revised to correct typographical errors in section 4.3 to accurately describe system boundary levels.

One (1) CD-ROM containing Security Related Information is included in this submission. The CD-ROM labeled "NextEra Energy Seabrook Cyber Security Plan" contains the following files:

001 CYBER SECURITY PLAN_002 (SRI) (368,640bytes) 002 CSP Rev 2 approvals (337,920 bytes 003 CSP R2 5054p (207,868 bytes)

There are no regulatory commitments contained in this correspondence.

Should you have any question regarding this submittal, please contact Bruce Fielding (bruce.fielding@nexteraenergy.com), Security Manager, at (603) 773-7021.

Sincerely, NextEra Energy Seabrook, LLC PO Box 300, Seabrook, NH 03874

Enclosure contains SECURITY RELATED INFORMATION- WITHOLD UNDER 10 CFR 2.390. Upon separation, this page may be de-controlled.

Nuclear Regulatory Commission SBK-L-18081 /Page 2 NEXTeraM E~

Enclosure - SRI CD-ROM labeled "NextEra Energy Seabrook Cyber Security Plan" cc: Regional Administrator, Region I (with enclosure)

USNRC Project Manager, Seabrook Station (without enclosure)

Senior Resident Inspector, USNRC, Seabrook Station (without enclosure)

Enclosure contains SECURITY RELATED INFORMATION- WITH OLD UNDER 10 CFR 2.390. Upon separation, this page may be de-controlled.

NE)<TeraM ENERGY~ *_;.>~

~~ SEABROOK April 26, 2018 Docket No. 50-443 SBK-L-18081 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Revision 2 to the Cyber Security Plan (CSP) for Seabrook Station In accordance with 10 CFR 50.4(b)(4), "Security plan and related submissions," and 10 CFR 50.54(p)(2), "Conditions oflicenses," NextEra Energy Seabrook, LLC submits Revision 2 to the Seabrook Station Cyber Security Plan (CSP).

The Cyber Security Plan has been revised to correct typographical errors in section 4.3 to accurately describe system boundary levels.

One (1) CD-ROM containing Security Related Information is included in this submission. The CD-ROM labeled "NextEra Energy Seabrook Cyber Security Plan" contains the following files:

001 CYBER SECURITY PLAN_002 (SRI) (368,640bytes) 002 CSP Rev 2 approvals (337,920 bytes 003 CSP R2 5054p (207,868 bytes)

There are no regulatory commitments contained in this correspondence.

Should you have any question regarding this submittal, please contact Bruce Fielding (bruce.fielding@nexteraenergy.com), Security Manager, at (603) 773-7021.

Sincerely, NextEra Energy Seabrook, LLC PO Box 300, Seabrook, NH 03874

Enclosure contains SECURITY RELATED INFORMATION- WITHOLD UNDER 10 CFR 2.390. Upon separation, this page may be de-controlled.

Nuclear Regulatory Commission SBK-L-18081 /Page 2 NEXTeraM E~

Enclosure - SRI CD-ROM labeled "NextEra Energy Seabrook Cyber Security Plan" cc: Regional Administrator, Region I (with enclosure)

USNRC Project Manager, Seabrook Station (without enclosure)

Senior Resident Inspector, USNRC, Seabrook Station (without enclosure)