MONTHYEARSBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters SBK-L-22113, Radiological Emergency Plan (Ssrep), Revision 792022-11-16016 November 2022 Radiological Emergency Plan (Ssrep), Revision 79 SBK-L-22114, Independent Spent Fuel Storage Installation (Isfsi), Cask Registration2022-11-0909 November 2022 Independent Spent Fuel Storage Installation (Isfsi), Cask Registration SBK-L-22112, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-11-0303 November 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22094, Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2022-10-26026 October 2022 Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) SBK-L-22105, Supplement to 2021 Annual Radioactive Effluent Release Report2022-10-24024 October 2022 Supplement to 2021 Annual Radioactive Effluent Release Report SBK-L-22103, 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan2022-10-12012 October 2022 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan SBK-L-22102, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-10-0606 October 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22080, Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 20222022-08-12012 August 2022 Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 2022 SBK-L-22054, SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0909 June 2022 SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections SBK-L-22044, 2021 Annual Radioactive Effluent Release Report2022-04-29029 April 2022 2021 Annual Radioactive Effluent Release Report SBK-L-22036, Steam Generator Tube Inspection Report2022-04-25025 April 2022 Steam Generator Tube Inspection Report SBK-L-22040, Radiological Emergency Plan (Ssrep), Revision 7822022-04-20020 April 2022 Radiological Emergency Plan (Ssrep), Revision 782 SBK-L-22024, Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2022-03-0707 March 2022 Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-22003, Inservice Inspection Examination Report2022-01-24024 January 2022 Inservice Inspection Examination Report SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan2022-01-0404 January 2022 Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases2021-12-29029 December 2021 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-21108, Core Operating Limits Report for Cycle 222021-11-0404 November 2021 Core Operating Limits Report for Cycle 22 SBK-L-21106, Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program2021-09-30030 September 2021 Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program SBK-L-21105, Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension2021-09-27027 September 2021 Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension SBK-L-21103, Request for Exercise of Enforcement Discretion2021-09-25025 September 2021 Request for Exercise of Enforcement Discretion SBK-L-21104, Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension2021-09-25025 September 2021 Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-09-22022 September 2021 Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21083, NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage2021-08-18018 August 2021 NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage SBK-L-21067, License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-07-21021 July 2021 License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21049, Revision to Updated Final Response to NRC Generic Letter 2004-022021-06-24024 June 2021 Revision to Updated Final Response to NRC Generic Letter 2004-02 SBK-L-21056, Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References:2021-05-20020 May 2021 Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References: SBK-L-21045, Submittal of 2020 Annual Radioactive Effluent Release Report2021-04-30030 April 2021 Submittal of 2020 Annual Radioactive Effluent Release Report SBK-L-21044, 2020 Annual Radiological Environmental Operating Report2021-04-30030 April 2021 2020 Annual Radiological Environmental Operating Report SBK-L-21042, Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations SBK-L-21033, Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements2021-03-24024 March 2021 Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements SBK-L-21023, Radiological Emergency Plan (Ssrep), Revision 772021-03-0404 March 2021 Radiological Emergency Plan (Ssrep), Revision 77 SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases2020-12-22022 December 2020 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-20149, Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-12-0808 December 2020 Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20146, One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c2020-12-0303 December 2020 One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c SBK-L-20144, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-23023 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20143, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-022020-11-19019 November 2020 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 SBK-L-20132, Fourth Interval Inservice Testing (IST) Program2020-10-21021 October 2020 Fourth Interval Inservice Testing (IST) Program SBK-L-20127, Generator Tube Inspection Report2020-10-20020 October 2020 Generator Tube Inspection Report SBK-L-20117, Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request2020-09-23023 September 2020 Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request SBK-L-20103, Inservice Inspection Examination Report2020-07-27027 July 2020 Inservice Inspection Examination Report SBK-L-20092, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-4182020-07-13013 July 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-418 SBK-L-20068, License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating2020-07-13013 July 2020 License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating SBK-L-20085, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-16016 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic SBK-L-20077, Core Operating Limits Report for Cycle 212020-06-0101 June 2020 Core Operating Limits Report for Cycle 21 SBK-L-20057, Response to Request for Additional Information Regarding Degraded Voltage Time Delay Setpoint License Amendment Request2020-05-20020 May 2020 Response to Request for Additional Information Regarding Degraded Voltage Time Delay Setpoint License Amendment Request 2023-06-22
[Table view] |
Text
FPL Energy Seabrook Station FPL Energy P.O. Box 300 Seabrook, NH 03874 Seabrook Station (603) 773-7000 August 8, 2008 SBK-L-08125 Docket No. 50-443 U.S. Nuclear Regulatory Commission Attn: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Seabrook Station Response to Clarifying Questions Related to Steam Generator Inspections Performed During the Eleventh Refueling Outage
References:
- 1. FPL Energy Seabrook letter to NRC, Response to Request for Additional Information Related to Steam Generator Inspections Performed During the Eleventh Refueling Outage, dated June 18, 2008.
- 2. Conference call between the NRC and FPL Energy Seabrook, July 15, 2008.
In Reference 1, FPL Energy Seabrook, LLC (FPL Energy Seabrook) provided its response to a request for additional information (RAI) regarding the Steam Generator Inservice Inspection Report for the Seabrook Station eleventh refueling outage. In Reference 2, the NRC posed three clarifying questions related to the FPL Energy Seabrook response to the RAI. The attachment to this letter provides the FPL Energy Seabrook response to the three clarifying questions.
Should you have any questions regarding the response to the clarifying questions, please contact Mr. Paul R. Willoughby at (603) 773-7350.
Sincerely, Gene St. Pierre Site Vice President cc: S.J. Collins, NRC Region I Administrator G.E. Miller, NRC Project Manager, Project Directorate 1-2 W.J. Raymond, NRC Senior Resident Inspector A0147 an FPL Group company
Attachment to SBK-L-08125
<I Attachment Response to Clarifying Questions Related to Steam Generator Inspections Performed During the Eleventh Refueling Outage Clarifying Question 1. Please clarify the cumulative EFPM (since the start of commercial operation) for all outages in the 90 EFPM sequential period. Please provide the cumulative EFPM at ORO0.
Please note the response to RAI 1 is not clear on the starting point for the cumulative EFPM provided in Table 1 (e.g. is the cumulative EFPMs starting after the accumulation of 120 EFPM or is it the cumulative since OR08). In addition, if Seabrook had accumulated 116 EFPM (per 10/12/04 letter) on its steam generators in OR08, it is not clear how you have calculated the start and stop points of the sequential periods considering the 120 month sequential period starts after the first in-service inspection (which presumably was 12 to 16 EFPMs in duration).
FPL Energy Response 1: As discussed with the NRC staff on July 15, 2008, FPL Energy provides the following tabulation of EFPM by cycle, cumulative EFPM per inspection period, and cumulative EFPM for each refueling outage.
Period Cycle EFPM Cumulative. EFPM Cumulative EFPM ORO0 1st ISI 10.90 10.90 10.90 1st Period 120 EFPM OR02 Inspection 10.60 10.60 21.50 OR03 Inspection 14.40 25.00 35.90 OR04 Inspection 14.50 39.50 50.40 OR05 Inspection 16.60 56.10 67.00 OR06 Inspection 17.80 73.90 84.80 OR07 Inspection 16.80 90.70 101.60 OR08 Inspection 14.90 105.60 116.50 End Point 1st Period 120.00 2 nd Period 90 EFPM OR09 Inspection 15.50 01.10 132.00 OR10 SKIP 16.80 17.90 148.80 ORll Inspection 16.80 34.70 165.60 OR12 SKIP 16.80 51.50 182.40 OR13 Inspection 16.80 68.30 199.20 OR14 SKIP 16.80 85.10 216.00 End Point 2 nd Period 90.00 Notes:
- 1) EFPM is estimated for OR13 and future.
- 2) As shown in the tabulation above, the first inspection period of 120 EFPM started after the first inspection in ORO 1.
Attachment Page 1 of 2
Clarifying Question 2. The response to RAI 3 is not clear on whether any other foreign objects/loose parts were detected. Please confirm that no other parts other than those described in response to RAI 3 were detected during FOSAR during OR1 1. Also, in the response to RAI 3, previous inspections of the tube support plate quatrefoil shaped holes were discussed. Please clarify when these previous inspections were performed.
FPLE Response: No other parts were found during FOSAR. Tube support plate inspections using UBIB (Upper Bundle In Bundle) tool were conducted during OR07 (Fall 2000) and OR08 (Spring 2002).
Clariflying Question 3. In tables 4 and 8 (SG A and C), it appears that FPLE had detected wear scars that occurred in prior cycles that were attributed to foreign objects/ loose parts that are no longer present at these locations. Please confirm this, understanding. In tables 6 and 10 (SG B and D), it appears the licensee detected new wear indications (i.e. not present in prior inspections) that were attributed to foreign objects. Please confirm that no foreign objects/loose parts (or potential loose parts for eddy current data) exist at these locations.
FPLE Response: The staff s understanding of wear attributed to foreign objects/loose parts in prior cycles is correct. There are no PLP (Possible Loose Part) signals at these tube locations. Tables 6 and 10 list new wear scars detected in ORl 1. There were no PLP signals associated with these indications. Visual inspections were not performed at these locations as no PLP was present and two of the locations were at the 6h tube support plate.
Attachment Page 2 of 2