RNP-RA/02-0129, Response to Regulatory Information Summary 2002-009, Preparation and Scheduling of Operator Licensing Examinations

From kanterella
Jump to navigation Jump to search
Response to Regulatory Information Summary 2002-009, Preparation and Scheduling of Operator Licensing Examinations
ML022480019
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 08/29/2002
From: Fletcher B
Carolina Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/02-0129
Download: ML022480019 (3)


Text

C407 SCP&L A Progress Energy Company Serial: RNP-RAI02-0129 AUG 2 9 2002 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 RESPONSE TO REGULATORY INFORMATION

SUMMARY

2002-09, "PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS" Ladies and Gentlemen:

H. B. Robinson Steam Electric Plant (HBRSEP), Unit No. 2, is providing a completed NRC Form 536, "Operator Licensing Examination Data," as an attachment to this letter. This completed form is being provided in accordance with NRC Regulatory Issue Summary 2002-09, "Preparation and Scheduling of Operator Licensing Examinations." Data estimates are provided for initial operator licensing examination needs, including an estimate of the number of applicants to be examined and intentions regarding preparation of the examinations.

If you have any questions concerning this matter, please contact Mr. C. T. Baucom.

Sincerely, B. L. Fletcher III Manager - Regulatory Affairs DJS/djs Attachment c: NRC Resident Inspector, IBRSEP L. A. Reyes, NRC, Region II R. Subbaratnam, NRC, NRR Robinson Nuclear Plant 3581 West Entrance Road H-artsville SC29550 iDV

U. S. Nuclear Regulatory Commission Attachment to Serial: RNP-RA/02-0129 2 Pages NRC Form 536 OPERATOR LICENSING EXAMINATION DATA

NRC FORM 536 U S NUCLEAR REGULATORY COMMISSION APPROVED BY 0MB NO 3150-0131 EXPIRES 07/31/2002 (8-2000) Estimated burden per response to comply with this voluntary Information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> This information collection is used to plan budgets and resources for operator examinations Send comments regarding burden OPE RATOR LICENSING estimate to the Records Management Branch (T-6 E6) U S Nuclear Regulatory ICommission, Washington, DC 20555-0001 or by interet email to EXAMINATION DATA !blsl@nrc gov. and to the Desk Officer Ofce of Information and Reglatory SAar OB-10202 (3150-0131)

_ fice of Management an udget Washington, DC 20503 If a means used to impose an information collection does not display a currently valid 0MB control number, the NRC may rot conduct or sponsor, and a person Is not required to respond to, the information collection FACILITY NRC REGION H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261/LICENSE NO. DPR-23 11 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 1 0 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSING EXAMINATIONS PROPOSED NUMBER CY 2003 CY 2004 CY 2005 CY 2006 NUMBER OF REACTOR 0 7 0 6 OPERATORS NUMBER OF SENIOR REACTOR OPERATORS-INSTANT 0 2 0 3 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 3 0 3 NUMBER OF SENIOR REACTOR 0 0 0 0 OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE N/A 09/03/2004 N/A 04/21/2006 ALTERNATE DATE N/A 09/10/2004 N/A 04/28/2006 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2003 CY 2004 PROPOSED NUMBER FIRST SECOND THIRD FIRST SECOND THIRD ESTIMATED NUMBER OF CANDIDATES 0 9 0 0 0 0 NRC FORM 536 (8- 2000)